2. Statement Of Work - Sun Shelter.docx

DOCX document 27 KB Posted

Attached to
Sun Shelter Electrical Upgrades Federal contract opportunity
Solicitation number
W50S6N22Q0010
Issued by
Department of the Army Alabama Army National Guard

View the file

Other files for this federal contract opportunity

Other files attached to Sun Shelter Electrical Upgrades, newest first.
File Type Posted
2.1 Appendix 1 - Project Drawing (Rev 1 - 6_23_2022).pdf PDF
2. SOW - Sun Shelter Elec Upgrades (Rev 2 - 6_23_2022).docx DOCX document
2.1 Appendix 1 - Project Drawing.pdf PDF
Solicitation W50S6N21Q0010.docx DOCX document
2.3 Appendix 3 - Government Furnished Material.pdf PDF
WDOL Wage Rates.pdf PDF
Clause Listing W50S6N22Q0010.pdf PDF
2.2 Appendix 2 - Electrical Panel Details (for reference only).pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sun Shelter Electrical Upgrades Aircraft Ramp Alabama Air National Guard

187th FW 5187 Selma Hwy Montgomery, AL 36108

General Information The Air National Guard has a requirement to provide electrical outlets and communications conduit and boxes at eleven Sun Shelters on the 187th Fighter Wing aircraft ramp. The work covered by this Statement of Work consists of furnishing all labor, equipment, and travel to make the needed repairs. The government will provide a portion of the materials as Government Furnished Materials (GFM), and the contractor will be required to provide the remaining materials needed to complete the work. A list of government furnished materials is shown in Appendix 3.

General Scope of Work:

The project is being managed from the 187th Civil Engineer Squadron (187th CES) and 187th Contracting offices located at Montgomery Air National Guard Base in Montgomery, Alabama. A contracting officer’s representative (COR) will be designated at the 187th CES.

Description of Work:

The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials not listed in Appendix 3, supervision, and other items needed to install electrical outlets and communications conduit at the 187th FW as defined below:

Install EMT, boxes, enclosures, and pull strings at eleven aircraft sun shelters as depicted in the Project Drawing in Appendix 1.

Government Furnished Material is listed in Appendix 3. Contractor to provide all additional material to complete this requirement.

Cabling to be installed by others.

Provide one quad 120VAC outlet at all twelve aircraft sun shelters.

Contractor to provide all materials required to power electrical outlets.

Mount receptacles at 48” AFG, next to comm boxes in the requirement above, on columns of sun shelters.

Receptacles shall be contained in a weatherproof in-use type cover.

Each Receptacle to be GFCI type.

See Appendix 2 for existing electrical panel details. These details are provided for reference only. The contractor is required to verify existing conditions of the electrical panels.

Period of performance:

The period of performance shall be 30 days after notice to proceed following contract award.

Place and hours of Performance The contractor is responsible for conducting business between the hours of 0700-1700 hours Tuesday thru Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings.

The project location is in a controlled area. The 187th CES will provide an escort for all contractor personnel within the controlled area.

If contractor desires to work on Mondays prior coordination with the 187th CES will be required to obtain an escort to the work area.

The Contractor must at all times maintain an adequate workforce for the uninterrupted execution of all tasks defined within this SOW when the Government facility is not closed for the above reasons.

Recognized Holidays:

New Year’s Day
Labor Day
Martin Luther King Jr.’s Birthday
Columbus Day
Washington’s Birthday
Veterans Day
Memorial Day
Thanksgiving Day
Juneteenth National Independence Day
Christmas Day

Independence Day

Prior to the award of the contract the Contractor will attend a Pre-Bid Conference at a time and date determined by the 187th Contracting Office. During this conference the Contractor will visit the site and conduct a preliminary walk-through with 187th CES personnel. During the site visit, the Contractor will identify any issues that may conflict with or affect the outcome of the work. The Contractor is expected to include any cost required for the accommodation of such items within the original cost proposal.

Disposal Requirements:

The Contractor is responsible for the collection and disposal of all debris, rubble, residue and waste material generated in the execution of work under this contract. All such materials shall be disposed of at an off base landfill by the CONTRACTOR or location specified by 187th Civil Engineer personnel. The CONTRACTOR is not permitted to deposit any such materials in base trash collection containers or at any on base location without prior approval of the Contracting Officer.

Existing Conditions:

The Contractor is responsible for returning all conditions of the site to the condition it was in prior to work beginning, to include but not limited to soils, grass, pavements, and utilities.

Security Access and General Protection/Security Policy and Procedures. This standard language is for contractor employees with an area of performance within Government controlled installation, facility, or area. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

For Contractors that do not require CAC, but require access to a DoD Facility and/or Installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (AFI 10-245, AFI 31-101 and AFMAN 31-113), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

Antiterrorism Awareness Level I Training (AT Level I). This standard language is for contractor employees with an area of performance within a US Government controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access to US Government installations, facilities and controlled access areas shall complete AT Level I training within XX calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. AT Level I may be accomplished by a Level I qualified instructor; completing the Force Protection computer-based training (CBT) course on the Advanced Distributed Learning System (ADLS), or Joint Knowledge Online at http://jko.jten.mil. Tracking for each contractor or subcontractor employee is the responsibility of the COR or unit AT Representative.

Attachment(s) Appendix 1 – Project Drawing Appendix 2 – Electrical Panel Details (for reference only) Appendix 3 – Government Furnished Materials

File details come from the government source that posted it. Updated .