2. Statement of Work.docx
DOCX document 2 MB Posted
- Attached to
- Ryan Willis Allotment Boundary Fence Federal contract opportunity
- Solicitation number
- 12970223Q0096
- Issued by
- Department of Agriculture Forest Service
About this file
This statement of work outlines requirements for a fence removal and replacement project on the Kaibab National Forest. The Forest Service seeks a contractor to remove approximately 17,400 feet of fencing damaged in the 2020 Mangum Fire, and install new barbed and smooth wire fencing according to the specifications provided. Key requirements include clearing vegetation from the right-of-way, removing burned fencing materials, installing new T-post and steel brace assemblies in a four-wire configuration per the indicated spacing, and ensuring access for maintenance. The Forest Service will provide fencing materials for pickup at the Tanglefoot work center, and the contractor must transport all equipment and materials to and from the project sites located approximately 35 miles east of Fredonia, Arizona. All work must be completed within 180 days of the notice to proceed.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 12970223Q0096.pdf | ||
| 1. Schedule of items.xlsx | XLSX spreadsheet | |
| 3. AZ202300030-06-09-2023.txt | TXT text file |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Kaibab National Forest - North Kaibab Ranger District Ryan – Willis Allotment Boundary Fence – Wire Removal and Replacement
Scope of Work:
The 2020 Mangum fire damaged approximately 53 miles of allotment fencing on the North Kaibab Ranger District. The purposes of this project are to: 1. Remove all damaged fence wire and 2. Install new wire to return the fence to “like new” condition. The total length of this project is approximately 17,400 feet. Specifically, this project includes:
1. Clearing workable right-of-way (approximately 17,400’) along the damaged portion of two fences. Note: (This right-of-way was cleared in 2021 and 2022. Only a minimal amount of clearing is anticipated to be needed for this project).
2. Remove and properly dispose of all burned wire and steel fence material from the existing fences. Note: (These fences were partially reconstructed in 2021 and 2022. Most of the needed bracing and post replacement was completed at that time. The primary objective of this project is to remove and replace the burned wire).
3. Replace approximately 17,400’ of barbed and smooth wire to return fences to “like new” condition.
All new fencing materials will be supplied by the Kaibab NF at the Tanglefoot work center in Fredonia, AZ. Contractor will be required to transport materials from Tanglefoot to the project site and transport all removed and unused new fence material back to the Tanglefoot work center.
Based on negotiated agreements, a skid-steer mountable wire roller and post driver may be provided by the Forest Service to facilitate removal and installation/repair of subject fences.
Location:
The projects are located approximately 35 miles east of Fredonia, AZ along the Cooper Ridge area of the Kaibab Plateau. The vicinity location and project sites are shown on the attached maps (Figures 1 and 2).
Requirements:
Remove and replace fencing wire from approximately 17,400 feet of the Ryan–Willis Allotment boundary fences that were damaged in the 2020 Mangum Fire.
All fencing materials will be supplied by the Kaibab NF at the Tanglefoot work center in Fredonia, AZ. Contractor will be required to transport materials from Tanglefoot work center to the project sites and to return any unused materials back to Tanglefoot.
A minimal amount of the fence right-of-way may need to be cleared to a sufficient width (see “Deliverables and Specifications”) to allow access so that damaged fence material can be safely removed, new fencing can be installed and future maintenance on those fences can be accomplished by the grazing permittee.
All damaged and/or non-serviceable fence materials will need to be removed from each fence. Metal posts, wire, clips and staples will need to be removed from the project site and will be recycled by the contractor or delivered to the metal scrap pile at Tanglefoot work center.
The two damaged fences will then be reconstructed to “like new” condition according to the design specifications shown in the “Deliverables and Specifications” shown below. The replacement fence design will be constructed of barbed & smooth wire with T-posts and steel braces.
Any “tie” into existing fences, natural barriers, or other structures shall equal or exceed the quality of the new fence installation.
Any alterations or additions outside of the statement of work must be approved by the Kaibab NF prior to making adjustments. Federally protected plants, animals, cultural resources, and historically significant properties shall not be harmed or destroyed during the installation of the fence.
All work shall be done in a manner that minimizes soil and vegetation disturbance and the movement of sediment and other pollutants into streams and water bodies. Any engine oil, lubricants, or other chemical pollutants spilled during construction shall be safely collected and properly disposed of by the contractor.
To minimize the spread of non-native seeds into the Forest, all equipment will need to be pressure washed and cleaned by the contractor prior to entering the Forest. Equipment will also need to be inspected by a Forest Service officer prior to entering the National Forest.
Contractor must provide all fire safety equipment on motorized vehicles at all times. At a minimum vehicles must be equipped with an axe, shovel and fire extinguisher.
Access To Project Sites:
Vehicle access to the project sites will be through highway 89A and Forest Service Road 248 ad 248A.
Fence #1 (West of Forest Road 248A) is expected to be approximately 12,200 feet in length will have equipment access to approximately 95+% of it’s length. The remainder of this fence runs across draws where work will need to be accomplished by hand.
Fence #2 (East of Forest Road 248A) is expected to be approximately 5,200 feet in length will have equipment access to approximately 95+% of it’s length. The remainder of this fence runs across draws where work will need to be accomplished by hand.
All access to fence locations will be off of existing roads. Equipment/materials may be staged at FS approved locations during fence installation. ATV and UTV’s may be used to transport materials during fence installation with minimal disturbance of soils and prior approval from the FS.
DELIVERABLES and SPECIFICATIONS:
Right-of-Way Clearing:
Right-of-way clearing will be accomplished to the following specifications as topography and natural features allow:
1. Right-of-way will be cleared of brush and trees a sufficient distance to allow small vehicle access (UTV or skid steer) to travel on one side of the fence. This distance should be approximately 15 feet. Both sides of the fence will need to be cleared to allow easy foot access to build and maintain the fence.
2. To remove fuel build up - clear brush and trees within 10 feet from both sides of the fence as follows:
A) All Juniper and Oak under 6 inches in diameter.
B) All Aspen, Ponderosa and Pinion pine under 10 inches in diameter.
C) All dead or dying Aspen, Ponderosa and Pinion pine (regardless of diameter or distance) that are leaning towards and can reasonably be expected to fall across the fence.
D) Lop and scatter all woody brush and tree material away from the fence location. Do not pile material.
E) To speed decomposition, cut or break scattered brush and tree material so the top edge is within 24 inches of the ground surface.
FIGURE 1 – PROJECT VICINITY MAP
FIGURE 2 – PROJECT SITE MAP
Fence Construction and Repair -
End Brace Assemblies End brace assemblies shall be installed where there is only one direction of pull on the brace assembly, such as at gates or where the fence meets a natural barrier. Horizontal brace assemblies shall be used for all end bracing.
End bracing shall be installed on each side of drainages and stream channels where the fence may be damaged by trapped debris during runoff or flood events.
A diagonal brace may be used instead of an additional horizontal brace where double bracing is needed. The diagonal brace shall be doweled, or welded to the brace post at least 36 inches above the ground.
Figure 3. Figure 4.
Figure 5.
Steel and Concrete Brace Assemblies Steel angle iron or steel pipe set in concrete may be used for end and line bracing. Steel and concrete brace assemblies shall be constructed as single or double span horizontal brace assemblies, or as a diagonal brace assembly.
Steel Brace Assemblies Steel angle iron or steel pipe set in may be used for end and line bracing. Steel and concrete brace assemblies shall be constructed as single or double span horizontal brace assemblies, or as a diagonal brace assembly. Steel pipe posts may be used if they can be driven into the ground at least 36 inches deep into soil that provides a solid, unmovable anchor.
Figure 6
Figure 7
Anchor and Brace Posts All anchor and brace posts shall be set in the ground at least 36 inches. Anchor and brace posts shall be long enough to extend at least 4 inches above the top wire of the fence.
Setting Steel Posts in Concrete If necessary to provide sufficient strength, steel pipe posts shall be set in a hole at least 36 inches deep and 12 inches in diameter. The bottom of the steel post shall be placed on a rock. The hole shall be filled with concrete in such a way as to allow the concrete to flow around the base of the post. The top of the concrete shall be mounded above ground level and sloped away from the post to prevent water from ponding around the base of the post. In areas with over 12” average annual precipitation, steel pipe posts shall be capped to prevent precipitation from entering the pipe.
Horizontal and Diagonal Braces Horizontal braces shall be at least 5 feet long and attached to the upper 1/4 of the anchor and brace posts.
Tension Wires for Wooden Brace Assemblies The tension wire on horizontal brace assemblies shall be attached diagonally from approximately 4 inches above the horizontal brace on the brace posts, to just above ground level on the anchor post. The tension wires shall be twisted together until the brace assembly is rigid.
Line Post and Stays Line posts shall be set in a straight line between brace assemblies with not more than 12 inches of deviation.
“T-posts” shall be driven into the ground until the top of the anchor plate is below ground level. Steel “T” posts shall be long enough to be driven into the ground above the anchor plate, and extend 4 inches above the top wire.
Wooden posts or steel pipe shall be used at points in the fence line whenever there is a 5 to 15 degree change fence direction. Double H braces (wood or steel pipe) or trees will be used whenever a 15 degree or greater change in direction is made.
Fence Wire
Wire Spacing Standard 4-Wire 18"- 24"- 34"- 44" Bottom Wire (Type) Smooth barbless wire
Wire Attachment Fence wires shall be firmly attached to the anchor post on each end of a fence section by double wrapping the wire around the anchor post and tying it off.
Wires shall be attached to all line posts using staples, tie wires, or manufactured wire fasteners of good quality.
Figure 8. Wire attachment to T-posts
Tie wires for attaching fence wires to posts shall be 16 gauge or heavier galvanized steel.
Wire Splicing When splicing of wire is necessary, either the “Western Union” or “loop splice” is acceptable.
Figure 9. Western Union Splice
Figure 10. Loop Splice
Fence Line Sections
The maximum line post spacing for standard fence line sections is as follows:
· 20 feet with 3 stays.
Figure 11. Fence Anchors
Fence anchors shall be installed when the bottom wire is more than 6 inches above the design height above the ground.
Anchor weights for holding down fence wires crossing drainages or depressions shall weigh at least 50 pounds or be equivalent to a 1 cubic foot concrete block. They shall be attached with 9 gauge or heavier smooth wire.
Water Gaps Where the fence crosses a drainage more than 40 feet wide, end bracing shall be installed on each side of the drainage. Water gap fence section materials shall equal the quality of the adjoining fence. They shall be assembled as a separate unit to protect the main fence from damage. The ends of the water gap fence wires shall be attached to a separate steel or wooden line post attached to the end brace using lightweight wire or staples that will allow the water gap to break away from the end braces in a flood event without damaging the end braces and adjacent fence sections.
Figure 12. Water Gaps
For deep narrow drainages, a separate fence section can be installed below the main fence. This separate fence section shall not be attached to the main fence.
Figure 13. Swinging Water Gap
Gates Wire gates across roads shall have stays at least every 3 feet to ensure they are visible to vehicles. They shall be secured to the end brace assemblies with smooth 9 gauge galvanized wire, or fence wire.
Affix gate posts to corner/stretch braces. Ensure gate is tight when closed but easy to open and close.
Figure 14. Texas Style Wire Gates
Wire Attachment to Living Trees
Fence wires may be attached to living Douglas Fir, Juniper or Ponderosa Pine trees under the following conditions:
1) Trees are in healthy, growing condition and are free from disease
2) Trees are greater than 18” in diameter
3) Trees must be growing in a vertical or nearly vertical direction
4) Wires and staples must not touch the tree directly when installed and for the future life of the tree (see figure 15).
This will require using a single “nailer” (or wood board at least 1-1/2” thick and 3” across) to attach wires to one side of a tree, or multiple “nailers” if wires are to be wrapped around the tree; 5) a sufficient number of “nailers” shall be used so that, at no time in the future will tree growth result in wires touching the tree; 6) if wires are placed only on one side of the tree, they must be placed so that pressure from the tensioned wires will pull into the tree not away from it.
Figure 15. Wire Attachment to Living Tree
Contractor Furnished Items:
Contractor will furnish all labor and equipment needed for transportation of personnel, equipment and materials to and from the project site.
*Government Furnished Items:
Kaibab NF will furnish the following materials:
T-Posts T-Post clips Cedar posts Lodge poles Timber Screws Staples Barbed wire Smooth wire HDPE Wire Stays Cable wire Nailer boards
*Based on negotiated agreements, a skid-steer mountable brush cutter, wire roller and post driver may be provided by the Forest Service to facilitate clearing, removal and installation/repair of fences discussed in this Statement of Work.
Period of Performance:
The time period for the fence installation is: 180 days after issue of NTP.
image6.png image7.png image8.png image9.jpeg image10.jpeg image11.png image12.png image13.png image14.png image15.png image1.png image2.jpeg image3.jpeg image4.png image5.png