This document contains a Quality Assurance Surveillance Plan (QASP) for a federal contract to conduct site preparation activities on national forest lands in Michigan. The contract requires the contractor to cut and process all tree species less than 6 inches in diameter at breast height across multiple sites in preparation for reforestation. Performance will be evaluated based on ensuring at least 95% of qualifying trees are removed on each site, with inspection plots used to validate completion. Acceptance requires meeting the 95% threshold, with rework allowed once if it is initially below standard. Surveillance methods include visual walkthroughs and inspection plots to validate removal rates. The Department of Agriculture Forest Service will administer the small business set-aside contract in accordance with FAR parts 12, 13, and 19 for timely completion by the end date.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 3. Maps.pdf | ||
| 5. Experience Questionnaire.docx | DOCX document | |
| 4. Michigan Statewide WD 1981-0136.pdf | ||
| 1. Statement of Work.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Quality Assurance Surveillance Plan
Contents
| Project Name | 3 | |
| Solicitation / Contract Number | 3 | |
| Section 1: Introduction | 3 | |
| 1.1 | Purpose | 3 |
| 1.2 | QASP Relation to the Contract | 3 |
| 1.2.1 | QASP Revisions | 3 |
| 1.2.2 | Surveillance of Performance Progression | 3 |
| 1.3 | QASP Relation to the Quality Control Plan (QCP) | 3 |
| Section 2: Performance Description | 3 | |
| 2.1 | Performance Standards and Acceptable Quality Levels (AQLs) | 3 |
| 2.1.1 | Allowable Deviation | 4 |
| 2.1.2 | Substantially Complete | 4 |
| 2.2 | Non-Performance | 4 |
| 2.2.1 | Documentation | 4 |
| 2.2.2 | Remedial Actions | 4 |
| Section 3: Contractor and Government Responsibilities | 4 | |
| 3.1 | Contractor Responsibility | 4 |
| 3.2 | Government Responsibility | 5 |
| 3.2.1 | Contracting Officer (CO) | 5 |
| 3.2.2 | Contracting Officer Representative (COR) | 5 |
| Section 4: Surveillance Methods to Perform Quality Assurance | 5 | |
| 4.1 | Surveillance Methods | 5 |
| 4.2 | Analysis and Results | 6 |
| Appendix A: Performance Requirement Summaries | 8 | |
| Appendix B: Example Contract Daily Dairy | 9 |
Project Name HMNF Site Prep Hughes Brittle
Solicitation / Contract Number Insert Solicitation / Contract Number
Section 1: Introduction This Quality Assurance Surveillance Plan (QASP) is pursuant to the requirements listed in the performance work statement (PWS) entitled [Site Prep Hughes Brittle]. This plan sets forth the procedures and guidelines that the USDA, [Forest Service] will use in ensuring the required performance standards or services levels are achieved by the contractor.
1.1 Purpose
The purpose of the QASP is to describe the systematic methods used to measure performance and to identify the reports required and the resources to be employed. The QASP provides a means for evaluating whether the contractor is meeting the performance standards identified in the PWS. This QASP is designed to define roles and responsibilities, identify the performance objectives, define the methodologies used to monitor and evaluate the contractor’s performance, describe quality assurance reporting, and describe the analysis of quality assurance monitoring results.
1.2 QASP Relation to the Contract
1.2.1 QASP Revisions
The Contracting Officer Representative (COR) may make revisions or changes to the QASP procedures and surveillance methods or increase or decrease the degree of surveillance methods at any time during the contract performance period. Changes to the Metric must be incorporated into the PWS, Performance Requirement Summary (PRS) and QASP by a bilateral modification to contract that is issued by the Contracting Officer (CO). A copy of the QASP is provided to the contractor to enable the contractor to enhance its Quality Control (QC) program to perform in accordance with its Quality Control Plan (QCP).
1.2.2 Surveillance of Performance Progression
As the performance period progresses, the levels of surveillance may be altered for service areas where performance is either consistently excellent or unsatisfactory. If consistently good performance, then the amount of surveillance may be reduced. If observations reveal consistent deficiencies, increased surveillance may be implemented.
1.3 QASP Relation to the Quality Control Plan (QCP)
The QCP is a required element of contract and the Contractor shall adhere to its established quality control processes and procedures in managing and performing work as described in the contract. While the QCP represents the way in which the Contractor will ensure its quality and timeliness of services, as defined in the PWS, the QASP represents the way in which the Government personnel specified in Section 3: Contractor and Government Responsibilities, Paragraph 3.2, Government Responsibilities will evaluate the contractor’s performance. The contractor’s QC program and the residual organization’s QASP should be complementary programs that ensure successful contractor performance.
Section 2: Performance Description Performance of the contractor will be monitored through the surveillance methods described in Section 4: Surveillance Methods to Perform Quality Assurance to assess the Contractor’s performance against PWS requirements.
2.1 Performance Standards and Acceptable Quality Levels (AQLs) For selected activities in the PWS, the PRS provides a performance standard and an AQL. A performance standard is the expected level of contractor performance. An AQL defines the level of performance that is satisfactory. Depending on the service evaluated and the evaluation method selected, performance standards and AQLs may be stated as a number of occurrences or as a percentage. Performance standards and AQLs for random sampling and 100 percent inspection are generally stated as percentages. For periodic inspections, performance standards may be stated as either percentages or as absolute numbers.
The contract requires the Contractor to perform all work as specified. Any inaccuracies or omissions in services or products are referred to as “defects” on the part of the Contractor. The Contractor shall be responsible for all identified defects and may be required to perform the work at no cost to the government. The AQLs take into account that in some instances an allowable level of deficiencies (deviations) is possible while overall performance continues to meet the government’s desired level of service.
2.1.1 Allowable Deviation
The AQLs define the level or number of performance deficiencies the Contractor is permitted to reach under this contract. AQLs take into account the difference between an occasional defect and a gross number of defects. AQLs can be expressed as a percentage of or as an absolute number (e.g., three per month). There may be instances where 100 percent compliance is required, and no deviation is acceptable (e.g., where safety is involved).
2.1.2 Substantially Complete
In some cases, service outputs are evaluated using subjective values (e.g., excellent, satisfactory, unsatisfactory). The criteria for acceptable performance and for defects must be defined for these service outputs. The concept of “substantially complete” should be the basis for inspections based on subjective scales. Work is considered “substantially complete” where there has been no significant departure from the terms of the contract and no omission of essential work. In addition, the Contractor has performed the work required to the best of its ability and the only variance consists of minor omissions or deficiencies.
2.2 Non-Performance
Non-performance occurs when the contractor’s performance does not meet the AQL for a given requirement. Requirements may contain multiple performance elements, and therefore, deficiencies may occur in one or more aspects of performance (e.g., timeliness, accuracy, completeness, etc.) or subject areas of effort.
When surveillance indicates that the contractor's service output is not in compliance with the contract requirements, the Contracting Officer’s Representative (COR) must determine whether the Contractor or the Government caused the deficiency. If the cause of the defect rests with the Government, corrective action must be taken through Government channels. If the cause of the defect is due to action or inaction by the contractor, the contractor is responsible for correction of the problem at no additional expense to the Government.
2.2.1 Documentation
Documentation of work non-performed or unacceptable work is essential for tracking Contractor performance. The COR will document deficient work by compiling facts describing the inspection methods and results and to substantiate nonconformance with the contract. A sample documentation reporting form is provided in Appendix B: Example Discrepancy Report. The documentation, with any recommendations, will be forwarded to the CO. In the case of the Contractor, the COR will decide whether to elevate the problem to the CO for corrective action.
2.2.2 Remedial Actions
The Federal Acquisition Regulation allows for penalties in the event that the Contractor fails to perform the required services. Penalties are defined as those actions taken under the direction of the CO against the contractor within the general provisions of the contract for nonconformance to the PWS and PRS.
Section 3: Contractor and Government Responsibilities
3.1 Contractor Responsibility
The Contractor is responsible for delivering products or services in accordance with the contract. Implementing its QCP, which describes the Contractor’s methods for ensuring all products and services under the contract meet established performance standards and AQLs. Maintaining, and providing for audit, quality control records and reports and all records associated with the investigation and complaint resolutions. Appointing a single quality control point-of-contact to act as a central recipient of communication from the COR or CO.
3.2 Government Responsibility
3.2.1 Contracting Officer (CO)
The CO is responsible for administering and monitoring contract compliance, contract administration, and cost control and for resolving any differences between the observations documented by COR and the contractor’s performance. The CO may delegate various day-to-day contract administration duties to a Administering ACO (ACO) and/or the COR for performance management and administrative actions such as invoice approval and issuance of Contract Discrepancy Reports may be, and normally are, delegated by the CO to the COR. The CO shall approve any revisions to the QASP processes or standards.
3.2.2 Contracting Officer Representative (COR)
The COR, is designated in writing, by the CO. The COR will ensure that the QA function is properly executed, plays a key role in contract administration and performs the contract surveillance and monitoring. Some key contract administration duties include, but are not limited to, performs surveillance as required by this QASP; make recommendations to the CO for issuance of Contract Discrepancy Reports or letters of commendation and acceptance or rejection of completed work and for administrative actions based on unsatisfactory or non-performed work, and revisions or changes to the QASP; and assists the CO in identifying necessary contract modifications and preparing reports of Contractor performance and cost.
The COR may use the form(s) included in the Appendices to perform the inspection or other forms as approved by the CO.
Section 4: Surveillance Methods to Perform Quality Assurance
4.1 Surveillance Methods
The surveillance methods used in the QA process are the Government’s tools to monitor the Contractor’s products and services. The best means of determining whether the Contractor has met all contract requirements is to inspect the Contractor’s service products and analyze the results. Further, documented inspection results are an effective tool in contract administration that can confirm the successful achievement of all performance requirements or highlight areas where defects exist and improvements are necessary.
4.1.1 Contractor Quality Control
The general Quality Control Plan must demonstrate how the Contractor will assure quality to meet the requirements and specifications of the contract. The Plan shall describe how quality will be monitored to assure the performance standards are met, the supervision of crew and work, and personnel that will be performing the quality control. Quality control shall include monitoring quality while work is in progress and upon completion.
4.1.2 Government Inspection
The Government shall inspect compliance with specifications and to provide the basis for computing performance. Inspections will consist of visual observations of cut and processed or broken-down trees through a walkthrough of complete areas. If noncompliance is suspected, the inspector will perform inspection plots which will be located throughout the completed areas to obtain a representative sample of the work. Each individual site will be inspected separately, and inspection results on one site will not be averaged with inspection results on other sites. The Government will inspect each site by using, as a minimum, one plot per five acres at a plot radius of 16.7 feet. Inspector will compare stumps with remaining trees less than 6 inches diameter and calculate the total remaining percentage of trees. At least 95% of trees within specifications need to be cut and processed or broken down. Determination of the acceptability of the work performed will be based on these inspections, which will be considered conclusive, except as otherwise provided in the contract.
Example of acceptable inspection plots results:
8 (total trees within spec. not removed) / 200 (total trees within spec. removed) = 4% (percent of trees within spec. remaining)
If total percentage is less than or equal to 5%, completed work is acceptable.
Example of unacceptable inspection plots results:
16 (total trees within spec. not removed) / 180 (total trees within spec. removed) = 8.8% (percent of trees within spec. remaining)
If total percentage is greater than 5%, completed work is unacceptable.
4.1.3 Rework
If AQL is below 95%, rework will be required. Reworked areas will be reinspected and receive a new AQL. Contractors will receive only one rework attempt per site.
4.1.4 Acceptance
Work on individual sites will be accepted following the final inspection by the COR. Work with a 95% AQL or better will be accepted at full payment. If complete work falls below 95% AQL, rework will be required. If reworked sites fall below 95% AQL, no payment will be issued for this site.
4.2 Analysis and Results
When the inspections validations have been completed, the COR will perform an analysis of the Contractor’s performance. The purpose of the analysis is to ensure Government is receiving high-quality products and services from the Contractor. The COR will review the results, rate the Contractor’s compliance with the performance standards and AQLs, and characterize the Contractor’s overall performance. Analysis of all types of contract monitoring will result in one of the following outcomes:
4.2.1 Acceptable
Contractors meet 95% AQL upon visual observation through walkthroughs or inspection plots. The Government may reduce its level of surveillance when the COR determines that the Contractor provides sustained performance that significantly exceeds the requirements with no significant deficiencies.
4.2.2 Unacceptable
Contractors do not meet 95% AQL upon visual observation through walkthroughs and/or inspection plots. Inspection plots will be conducted, and rework may be required.
[THIS PAGE IS FOR INFORMATIONAL PURPOSES]
The Contacting Officer must include as attachments or exhibits the appropriate performance requirement summary, forms, checklists, etc. in the QASP that will be used during surveillance / monitoring for the applicable contract.
Appendix A: Example Performance Requirement Summaries The following documents are examples only, which is not all inclusive, that can be revised and used, if applicable, in the QASP as attachments or exhibits.
PERFORMANCE REQUIREMENT SUMMARY
Contract Line Item – Work Requirements
Task / Critical Sub tasks
Inspection requiements Acceptable Quality Level (AQL)
Method of Surveillance
Line item 1&2
Cut and process or breakdown all trees less than 6 inches DBH.
At least 95% of all trees less than 6 inches DBH must be cut and processed or broken down via masticator or similar equipment.
No more than 5% of trees less than 6” DBH should be remaining upon completion of the site.
AQL determinations are made by the COR upon inspection of the work.
These determinations are unilateral and not protest able.
At least 95% of all trees less than 6 inches DBH are cut and processed or broken down via masticator or similar equipment.
Visual Inspection and/or Inspection Plots.
| Schedule (non-line item) |
| Timely Completion of the contract work. |
| Per the Work Schedule, the Contractor will complete all work prior to the contract end date. |
AQL determinations are made by the COR upon inspection of the work, These determinations are made unilateral and not protest able.
| All work must be completed by the contract end date. |
| Visual and/or GPS |
Appendix B: Contract Daily Diary image1.png image2.jpeg