This file is a comprehensive technical specification document for a potable water distribution system project issued by the Possum Valley Municipal Authority in Pennsylvania. The project involves the supply and installation of approximately 1,379 linear feet of 6-inch ductile iron water pipe with necessary service lines, connections, and disconnections to existing pipe along Center Mills Road between Carlisle Road and Aspers North Road. The work encompasses multiple divisions including general requirements, site work (excavation and backfill, shoring, erosion and sedimentation control, boring and jacking), pipe and valve installation, testing and sterilization, and valve vault construction. Sealed bids are due December 9, 2026 at 3:30 PM via PennBid, with the project affecting ten identified Adams County tax parcels. The specifications reference numerous ANSI/AWWA standards and provide detailed requirements for materials, installation methods, quality assurance, and construction procedures.

The project is partially funded through a federal Community Development Block Grant (CDBG) from the U.S. Department of Housing and Urban Development, making it subject to Davis-Bacon wage determinations and prevailing wage standards. All bids must be accompanied by 5% bid security, with the successful bidder required to furnish additional bonds as prescribed. The bidder must comply with the Public Works Employment Verification Act (43 P.S. 167.1-167.11) and submit required verification forms. The specifications establish detailed technical requirements for ductile iron pipe (Grade 60-42, Class 52), PVC pressure pipe (DR-18), mechanical joints, service lines, valves, fire hydrants, and all appurtenances, along with comprehensive procedures for excavation, backfilling, erosion control, hydrostatic testing, disinfection, and bacteriological sampling prior to system activation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TABLE OF CONTENTS

DIVISION 1 – GENERAL REQUIREMENTS

Section 01320 – Submittals

DIVISION 2 – SITE WORK

Section 02300 – Excavation and Backfill
Section 02310 – Shoring
Section 02320 – Erosion and Sedimentation Control
Section 02400 – Boring and Jacking
Section 02590 – Pipe, Valves & Appurtenances & Installation Methods
Section 02592 –Testing & Sterilization
Section 02710 – Valve Vaults
Section 02712 – Residential Meter Installation
Section 02950 – Resurfacing and Restoration

DIVISION 3 – CONCRETE

Section 03300 – Cast-In-Place Concrete

APPENDIX

Detail Drawings and Construction Requirements for Public Water System and Appurtenances

Detail #1 – Fire Hydrant & Valve Detail #2– Service Line Connections Detail #3– Earth Dam Detail #4– Concrete Thrust Block Detail #5– Paving Restoration Detail #6– Trench Section – Ductile Iron Pipe Detail #7– Casing Installation Detail #8– Stream Crossing Detail #9- Gate Valve Installation Detail #10– Combination Air/Vacuum Valve Detail #11– Pressure Reducing Valve Detail #12– Blowoff Detail #13– Domestic Long Lateral Water Meter Installation

DIVISION 1 - GENERAL REQUIREMENTS

SECTION 01320 - SUBMITTALS

PART 1 - GENERAL

1.01 SUBMISSIONS REQUIRED

A.General: The descriptions under the SUBMITTALS Article in each in each Specifications Section indicates the type of submission required. Make submissions to the address given as the Office of the OWNER OR OWNER REPRESENTATIVE.
B.Definition: The term shop drawing used throughout this Section includes manufacturer’s product data in the forms of descriptive literature, specifications and published detail drawings, and also CONTRACTOR prepared drawings, certified test records or reports and such other information required by the specifications.

1.02 PROGRESS SCHEDULE OF SUBMITTALS

A. Promptly after the award of Contract, submit a progress schedule of submittals to the OWNER OR OWNER REPRESENTATIVE for approval, indicating the proposed dates of submission and the number for the various types of Work. Arrange submission dates in the proper sequence of the importance of the Work to the progress of construction.

1.03 CONSTRUCTION PROGRESS SCHEDULE

A.Within forty-five days after issuance of the Notice To Proceed, submit to the OWNER OR OWNER REPRESENTATIVE five copies of a practicable and feasible progress schedule showing the order in which the Work is to be carried on, the dates on which prominent features will start (including procurement of materials and equipment), and the contemplated dates for completing same.
B.Prepare the schedule in chart form of suitable scale so as to appropriately indicate the percentage of Work completed at any time.
C.The General Construction CONTRACTOR will prepare the progress schedule and the CONTRACTORs holding other contracts in the Project shall cooperate in its preparation. The final progress schedule must have the approval of all CONTRACTORs.
D.The General Construction CONTRACTOR shall revise the Construction Progress Schedule as directed by the OWNER OR OWNER REPRESENTATIVE until finally approved by him and after such approval; all CONTRACTORs shall strictly adhere to such schedule unless, upon written order of the OWNER OR OWNER REPRESENTATIVE, it is changed; additionally it is agreed that the OWNER reserves the right to determine the order of precedence and the times at which various portions of the Work are to be performed, all at no additional cost to the OWNER.
E.At the end of each month the General Construction CONTRACTOR shall update the Construction Progress Schedule by entering the actual progress of the Work on the schedule. The CONTRACTORs holding other contracts in the Project shall submit their progress to the General Construction CONTRACTOR so he can include their progress on the schedule. The General Construction CONTRACTOR shall deliver five copies of the updated Construction Progress Schedule to the OWNER OR OWNER REPRESENTATIVE immediately after its completion.
F.If the monthly update of the Construction Progress Schedule indicates variations in the schedule as previously approved, the General Construction CONTRACTOR along with the CONTRACTORs holding other contracts in the Project, shall submit a revised Construction Progress Schedule to the OWNER OR OWNER REPRESENTATIVE for approval in accordance with requirements previously specified.
G.After the OWNER OR OWNER REPRESENTATIVE’s approval of the Construction Progress Schedule, it will be distributed by the General Construction CONTRACTOR to all other CONTRACTORs.

1.04 SUBMISSION OF SHOP DRAWINGS

A. The following requirements for shop drawing submissions apply to all CONTRACTORs.

B. Submit five copies of each shop drawing in a timely manner to avoid delay in the work.

C. Each submission of the shop drawings must be accompanied by a letter of transmittal listing the items in the submission. Each shop drawing must be marked with the name of the Project and the name of the CONTRACTOR and will be numbered consecutively.

D. When making a submission for approval, the CONTRACTOR shall do so with the understanding that he is considered to have checked the items in the shop drawing before submitting them and that he is satisfied that, in their present state, they not only meet the requirements of the Contract Documents, but will present no difficulties in erection and completing his Contract, and shall clearly note his approval on all shop drawings prior to their submission to the OWNER OR OWNER REPRESENTATIVE. Failure of the CONTRACTOR to note his approval will be reason for the OWNER OR OWNER REPRESENTATIVE to return such submission to the CONTRACTOR unchecked. If it appears that shop drawings submitted by the CONTRACTOR to the OWNER OR OWNER REPRESENTATIVE have not been properly checked, even though the CONTRACTOR’s approval has been noted thereon, it will also be considered reason for the OWNER OR OWNER REPRESENTATIVE to return such submission to the CONTRACTOR unchecked.

E. If shop drawings show variations from the Contract requirements because of standard shop practice or other reasons, the CONTRACTOR shall make specific mention of such variations in his letter of submission in order that (if accepted) suitable action may be taken for proper adjustment in the Contract; otherwise the CONTRACTOR will not be relieved of the responsibility for executing the Work in accordance with the Contract even though the shop drawings have been approved.

F. The approval of the shop drawings will be general and shall not relieve the CONTRACTOR from the responsibility for proper fitting and construction of the Work nor from furnishing materials and work required by the Contract which may not be indicated on the shop drawings when approved.

G. After review by the OWNER OR OWNER REPRESENTATIVE shop drawings will be returned marked as follows: “Approved”, “Approved With Changes Noted”, “Returned for Correction”, or “Not Approved”.

1.Approved: When shop drawings are returned “Approved”, that means the shop drawings have been found to be in conformance with the Contract Documents. The OWNER OR OWNER REPRESENTATIVE’s approval of the shop drawings does not relieve the CONTRACTOR from responsibility for errors or discrepancies in such shop drawings.
2.Approved with Changes Noted: When shop drawings are returned “Approved With Changes Noted” that means the shop drawings have been found to be in conformance with the Contract Documents, provided the changes noted by the OWNER OR OWNER REPRESENTATIVE are incorporated in the shop drawings. Shop drawings returned “Approved With Changes Noted” will not require resubmission.
3.Returned for Correction: When shop drawings are returned noted “Returned for Correction” that means that the CONTRACTOR should make the required corrections and resubmit five copies of the corrected shop drawings to the OWNER OR OWNER REPRESENTATIVE.
4.Not Approved: When shop drawings are returned “Not Approved” that means the CONTRACTOR will make completely new shop drawings and submit five copies to the OWNER OR OWNER REPRESENTATIVE for review.

PART 2 - PRODUCTS

NOT APPLICABLE TO THIS SECTION

PART 3 - EXECUTION

NOT APPLICABLE TO THIS SECTION

END OF SECTION

DIVISION 2 - SITEWORK

SECTION 02300 - EXCAVATION AND BACKFILL

PART 1 - GENERAL

1.01 SCOPE OF WORK

A. This section consists of all excavation and backfill activities involved in work under this contract.

1.02 QUALITY ASSURANCE

A. Source Quality Control:

1.The OWNER/OWNER REPRESENTATIVE reserves the right to require advanced examination or testing according to methods referenced or by other methods chosen.
a.If testing is required, the testing laboratory shall furnish both OWNER/OWNER REPRESENTATIVE and CONTRACTOR two (2) copies of test result reports.

b. Above reports shall be considered as sufficient evidence of acceptance or rejection of the materials represented.

c. The OWNER/OWNER REPRESENTATIVE reserves the right to accept certificates of approved quality materials from an approved source in lieu of laboratory testing, or to require both.

1.03 REFERENCES

A. American Society for Testing and Materials:

1. ASTM D698-12(2021) Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Standard Effort (12 400 ft-lbf/ft3 (600 kN-m/m3)).

2. ASTM D1556/D1556M-15e1 Standard Test Method for Density and Unit Weight of Soil in Place by Sand-Cone Method.

3. ASTM D2774-21a; Standard Practice for Underground Installation of Thermoplastic Pressure Piping.

4. ASTM D6938-17ae1 Standard Test Methods for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth).

B. Commonwealth of Pennsylvania Department of Transportation (PA DOT), Specifications Publication 408, and as supplemented:

1. PA DOT Pub. 408 Section 703.2 Coarse Aggregate.

2. PA DOT Pub. 408 Section 703.3 Select Granular Material (2RC)

1.04 SUBMITTALS

A. Test Reports:

1. Upon request from the OWNER/OWNER REPRESENTATIVE, submit laboratory aggregate test reports based on requirements stated in Source Quality Control.

2. Compaction density test reports shall be based on method of density determination as specified in the above Reference Standards and/or the method as approved by the OWNER/OWNER REPRESENTATIVE.

B. Certificates: Submit certificate from aggregate supplier based on requirements stated in the Source Quality Control, when required by the OWNER/OWNER REPRESENTATIVE.

1.05 JOB CONDITIONS

A. The CONTRACTOR shall perform this work only when weather and soil conditions are suitable for the performance of this work.

1.Neither frozen earth nor excessively wet materials shall be used for backfill.
2.Prior to use, moisten dry backfill not having sufficient moisture to obtain satisfactory placement or compaction.

B. Excavations shall be kept free from water at all times during the performance of work under this section. Water from the trenches shall be disposed of in such a manner that it doesn't cause injury or damage. Dewatering shall be in compliance with Section 02320, Erosion and Stabilized Sedimentation Control Plan. Keep gutters, sewers, drains and ditches open at all times for surface drainage.

C. Protection: The CONTRACTOR shall assume all risks resulting from the presence or proximity of overhead or underground public utility and private lines, pipes, conduits and support for the previously mentioned. Also, damages and expenses for direct or indirect injury to structures, persons or property will solely be the CONTRACTOR's responsibility. The CONTRACTOR shall perform all work in conformance with PA Act 172 (PA One Call).

D. Removal of Obstructions:

1. Remove, realign or change the direction of above or below ground utilities and their appurtenant supports, if such is required in the opinion of the OWNER/OWNER REPRESENTATIVE. Additional precautions concerning obstructions as follows:

a. Do not interfere with persons, firms, corporations or utilities employing protective measures, removing, changing or replacing their property or structures, but allow said persons, firms, corporations or utilities to take such measures as they may consider necessary or advisable under the circumstances.

b. Break through and reconstruct if necessary, the invert or arch of any sewer, culvert or conduit that may be encountered if the said structure is in such a position, in the judgment of the OWNER/OWNER REPRESENTATIVE, as not to require its removal, realignment or complete reconstruction.

E. Explosives and Blasting: Use and store explosives in accordance with requirements of Federal, State and local laws, rules, regulations, precautions, orders and decrees. Additionally comply with the following:

1. Do not use methods of blasting which will result in breakage beyond work areas or which is dangerous to the public or destructive to property.

2. The CONTRACTOR is solely responsible for injury to persons or property as a result of his use of explosives.

3. Notify utility and property owners prior to blasting.

4. Provide competent, licensed blaster to supervise blasting.

F. Excess Materials:

1. It is the CONTRACTOR's responsibility to dispose of excess backfill material should the property owner not want the material left on his premises.

2. No right of property in materials is granted to the CONTRACTOR of excavated materials prior to backfilling. This does not relieve the CONTRACTOR of his/her responsibility of disposing of material described above.

G. Accommodation of Traffic: Do not obstruct streets, roads and highways, unless the Municipality or Governing Agency authorizes in writing the complete closing of the street, road or highway. Employ such measures as may be necessary to keep the street, road or highway open and safe for traffic. Maintain a straight and continuous passageway on sidewalks and over crosswalks, at least three (3) feet wide and free from obstructions. DO NOT OBSTRUCT FIRE HYDRANTS.

1. At the shutdown of work at the end of the day all streets shall be left in such condition whereby they can be readily opened and safely traveled in cases of emergency such as fire or for ambulance service.

H. Structure Supports: Where passing buildings or any structure which by their construction or position might bring a great pressure upon the trenches, the right is reserved by the OWNER/OWNER REPRESENTATIVE to require that such buildings or structures be underpinned or supported and protected, or special sheeting be driven or that short lengths of trench be opened at one time.

I. Removal of Rock by Means Other Than Blasting: Where removal of rock by means other than blasting is required, in accordance with requirements of State and local laws, rules and regulations, and utility owner requirements, remove by the use of mechanical surface impact equipment, or by drilling and hydraulic rock splitting equipment, or by other methods acceptable to the OWNER/OWNER REPRESENTATIVE.

J. Borrow Material: When the requirement quantity of backfill material exceeds the quantity of suitable on site material, provide borrow material. If borrow material is needed, notify the OWNER/OWNER REPRESENTATIVE sufficiently in advance to permit the OWNER/OWNER REPRESENTATIVE to verify such need and to view the proposed borrow pit to determine the material suitability. Borrow excavation will be subject to the OWNER/OWNER REPRESENTATIVE's approval whose written consent shall be obtained prior to its use.

K.Stream Crossings: Excavate trenches in stream crossings to the depth shown on the Drawings or otherwise required by the ENGINEER.
1.Material excavated may be used as backfill if it meets the requirements for backfill, unless specifically prohibited by any state agency having jurisdiction.
2.Make all necessary provisions for cofferdamming, dewatering and removal of excess excavated material.
3.Maintain the flow in the stream at all times.
4.Where rock is encountered in the stream crossings, do not use forms to construct the concrete encasement. Place concrete on firm rock below the pipe and against firm rock on both sides of the pipe to provide a firm bond between the encasement and the rock. Should the CONTRACTOR excavate beyond the dimensions specified herein before for concrete encasement he will be required to furnish and place all additional concrete required beyond the dimensions shown on the Drawings at his own expense and no separate or additional compensation will be paid therefore.

5. Construct stream crossing in accordance with additional requirements specified in Section 02320 - Soil Erosion & Sedimentation Control Plan.

L. Water Service Lines: Copper water service lines will be placed in trench on clean native material and backfilled with clean earth backfill.

PART 2 - PRODUCTS

2.01 MATERIAL

A. Backfill: On site excavated soil or soil-rock mixed materials free of topsoil, plant life, lumber, metal, refuse and rock or similar hard objects larger than six inches in any dimension. Rock to soil ratio shall not exceed one part rock to three parts soil.

B. Clean Earth Backfill: On site excavated material free of plant life, lumber, metal, refuse and rocks or similar hard objects larger than one inch in any dimension. Rock to soil ratio shall not exceed one part rock to three parts soil. Suitable retained material shall be considered in this category.

C. Aggregate Backfill: Select Granular Material (2RC) conforming to PA DOT Pub. 408 Section 703.3.

D. 2A Aggregate Backfill: Coarse Aggregate conforming to PA DOT Pub. 408 Section 703.2.

E. Pipe Bedding:

1. First Class Bedding: Coarse Aggregate conforming to PA DOT Pub. 408 Section 703.2.

a. For piping having a diameter of 21-inch and less use AASHTO NO. 8 Coarse Aggregate.

b. For piping having a diameter of 24-inch and larger use AASHTO No. 57 Coarse Aggregate.

2. Initial Backfill: Same as First Class Bedding.

F. Concrete Cradle and Encasement: Per requirements of Cast-In-Place Concrete and of the following class:

1. Class B: 3000 psi.

G. Underground Warning Tape:

1. Printed polyethylene tape, 3-inches minimum width, color coded, one-inch minimum lettering, printed with name of utility buried below, and suitable for installation in all types of soil.

H. Foundation Backfill: AASHTO No. 3 Coarse Aggregate conforming to PA DOT Pub. 408 Section 703.2.

PART 3 - EXECUTION

3.01 PREPARATION

A. Excavation:

Excavation shall be accomplished as specified above. The ENGINEER and the OWNER reserve the right to limit the length that a trench may be opened in advance of the pipe laid. No trench shall be opened more than 200 feet in advance of the pipelines laid, without the permission of the ENGINEER. Where a rock excavation is encountered, all trenches must be fully opened at least 30 feet in advance of any pipe being laid.

B. Preparation of Surfaces:

1. Do not remove trees in rights-of-ways except by authorization of the OWNER/OWNER REPRESENTATIVE.

2. Perform authorized tree removal, including stumps and debris, by methods meeting the OWNER/OWNER REPRESENTATIVE's approval.

3. Perform authorized shrubbery removal, store shrubs in protected manner and replant or replace such shrubbery.

4. Trim merchantable timber of limbs and tops, and unless otherwise directed by the OWNER/OWNER REPRESENTATIVE, saw timber into eight (8) foot sections. Stockpile timber at locations designated by the OWNER REPRESENTATIVE. Merchantable timber is timber larger than six (6) inches in smallest diameter from which saw logs, pulpwood, posts, poles, ties or cordwood can be produced.

3.02 PERFORMANCE

A. Sheeting and Shoring: Perform Sheeting and Shoring in accordance with Section 02310 of these Specifications.

B. Erosion and Sedimentation Control: Perform Erosion and Sedimentation Control in accordance with Section 02320 of these Specifications.

C. Excavating: Perform excavation and backfilling using machinery except that hand excavation and backfilling may be required where necessary to protect existing structures, utilities or private or public properties.

1. Begin excavation in trenches at the control point having the lower invert and proceed upgrade.

2. Remove rock to subgrade at least thirty (30) feet in advance of pipe laying.

D. Excavated Materials Storage: In areas where working space is limited, remove the excavated materials from the first 100-feet of any opening, when required by the OWNER/OWNER REPRESENTATIVE, as soon as such is excavated; store and return same for backfilling where required. In no case will the CONTRACTOR be allowed to cast excavated material beyond the curb or right-of-way line or sidewalk or lawn.

E.Do not perform trenching, backfilling or compacting when weather conditions or the condition of materials are such, in the opinion of the ENGINEER, that work cannot be performed satisfactorily.
F.Do not use frozen materials as backfill material not having sufficient moisture to obtain satisfactory placement or compaction.
G.Prior to use, moisten dry backfill material not having sufficient moisture to obtain satisfactory placement or compaction.
H.Plan work so as to provide adequate protection during storms with provisions available at all time for preventing flood damage. Protect installed piping and other work at all times against damage from uplift due to high ground water levels.
I.Accommodation of Drainage: Keep gutters, sewers, drains and ditches open at all times for surface drainage. No damming or ponding or water in gutters or other waterways will be permitted, except where stream crossings are necessary and then only to an extent, which the ENGINEER shall consider necessary. Do not direct water flows across or over pavements except through approved pipes or properly constructed troughs. When so required, provide pipes or troughs of such sizes and lengths as may be required, and place the same as required. Perform grading in the vicinity of trenches so that the ground surface is properly pitched to prevent water running into the trenches.
J.Pumping: Keep excavation free from water at all times during the performance of the work under this project. Build dams and other devices necessary for this purpose, and provide and operate pumps of sufficient capacity for dewatering the excavations. Provide for the disposal of the water removed from excavations in such manner as not to cause injury to the public health, to public or private property, to the work of others, to any portion of the work completed or in progress or produce an impediment to the use of streets, roads and highways.
K.When it is necessary to haul soft or wet soil material over roadways, use suitably tight vehicles to prevent spillage. Clear away spillage of materials on roadways caused by hauling.
L.Provide effective dust control by sprinkling water, use of calcium chloride or any other method approved by ENGINEER. Employ dust control when, where and in a manner required by ENGINEER.
M.Temporary Protective Construction:
1.Temporary Fence Barricade: Erect and maintain substantial temporary fences surrounding excavation to prevent unauthorized persons entering such areas.
2.Temporary Fence: Where necessary, to keep one side of streets or roadway free from obstruction or to keep material piled along side of the trench from falling on private property outside the right-of-way, erect and maintain a safe and substantial fence.
3.Barricades: Furnish and erect substantial barricades at crossings of trenches, or along trenches, to protect the traveling public.
4.Excavation Covers: Cover open excavation when work therein is suspended or left unattended, such as at the end of a workday. For such covers, use materials of sufficient strength and weight to prevent their removal by unauthorized persons.
5.Remove temporary protective construction at the completion of work on the Project.
N.Accommodation of Traffic: Do not obstruct streets, roads and highways, unless the OWNER authorizes in writing the complete closing of the street, road or highway, employ such measures at no expense to the OWNER as may be necessary to keep the street, road or highway open and safe for traffic. Maintain a straight and continuous passageway on sidewalks and over crosswalks, at least three feet wide and free from obstructions. DO NOT OBSTRUCT FIRE HYDRANTS.
O.Explosives and Blasting: Use and store explosives in accordance with requirements of Federal, State and local laws, rules, regulations, precautions, orders and decrees. Additionally comply with the following:
1.Do not use methods of blasting which will result in breakage beyond trenching areas or which is dangerous to the public or destructive to property.
2.The CONTRACTOR is solely responsible for injury to persons or property as a result of his use of explosives.
3.Schedule blasting in the proximity of proposed new concrete work prior to placement of concrete.
4.Notify utility owners having structures of other installations (if any) above or below ground in proximity to the trenching work prior to use of explosives. Such notice must be given sufficiently in advance to enable the utility owners to take such steps, as they may deem necessary to protect their property from injury. Such notice shall not relieve the CONTRACTOR of responsibility of damage resulting from his use of explosives. The right is reserved to direct that rock within five feet of pipe, conduit or other structures encountered in the trench be removed by methods other than blasting.
5.Provide competent, licensed blaster to supervise blasting.
6.Cease blasting operations when street paving adjacent to trench is damaged. Repair damaged street paving.
P.Removal of Rock by Means Other Than Blasting: Where removal of rock by means other than blasting is required, in accordance with the requirements of State and local laws, rules and regulations, and utility owner requirements, remove by the use of mechanical surface impact equipment, or by drilling and hydraulic rock splitting equipment, or by other methods.

R. Trench Width and Depth:

1.Trench widths shall be such to provide a free working space on each side of the pipe as laid, but shall not exceed the outside diameter of the barrel of the pipe plus sixteen inches at a point one foot above the top of the pipe.
2.Trench Depth: Excavate the trench to a minimum of four (4) inches or one-fourth of the internal pipe diameter, whichever is greater, below the invert of the pipe. The trench depth shall be adequate so that the pipe will have a minimum of four (4) feet of cover the top of the pipe.

S. Additional Excavation: Do not excavate below depths indicated or specified except where unstable or unsuitable material is encountered at subgrade. Excavate such material to the increased depth as may be required by the OWNER/OWNER REPRESENTATIVE and refill to the proposed subgrade with thoroughly compacted Foundation Backfill material.

T. Backfilling: Perform trench backfilling and backfilling excavations for other in line structures by methods which will result in thorough compaction of backfilled material without displacement of the grade and alignment of the pipeline and its appurtenances and minimum settlement of backfilled material. Displacement of the pipeline and settlement of backfill shall be considered evidence of improper workmanship or inclusion of unsuitable backfill materials, or both, and will require regrading and realigning the pipeline and removing and recompacting settled material.

1.All backfill material shall be free from cinders, ashes, refuse, vegetable or organic material, boulders, rocks or stones, frozen soil, or other unsuitable material.
2.Perform final embedment of trench in accordance with these Specifications. The initial backfill/embedment shall be placed in 4-inch layers to a point of a minimum of 12 inches above the top of the pipe.
3.Following final embedment fill remainder of trench with materials as specified below. Exercise care to carry backfill up evenly on opposite sides of piping.
a)Paved Areas: Aggregate backfill (2RC) compacted in (6-8) inch layers.
b)Unpaved Areas: Backfill compacted in six-inch layers to bottom of topsoil. Replace topsoil to approximate depth of existing final refill operation and crown to such a height as directed by the OWNER/OWNER REPRESENTATIVE. From 1 foot above the top of the pipe to the subgrade of the pavement, material containing stones up to 8 inches in their greatest dimension may be used, unless otherwise specified.
U.Earth Dams in first class bedding installation, construct earth dams composed of clean earth backfill material.
1.Location: At a point not less than (3) feet upstream from inline structure; in trenches for service connections at a point not less than three (3) feet from the main water trench; in main water trenches at 100 foot intervals; and trenches at such other locations required by the OWNER/OWNER REPRESENTATIVE.
2.Place clean earth backfill material from subgrade to one (1) foot depth over top of pipe. Length shall be as shown on the Earth Dam Drawing Detail.
3.Place earth dam material by hand and compact with proper tools designed for such purpose.

SECTION 02310 - SHORING

PART 1 - GENERAL

1.01 QUALITY ASSURANCE

A. Requirements of Regulatory Agencies:

1.Shoring materials and installation work shall conform to Federal, State and local laws, rules, regulations, requirements, precautions, orders and decrees. Work shall conform to all OSHA requirements.
2.Provide material for shoring, sheeting bracing and/or trench boxes and drive or set in place in accordance with Federal, State and local laws for excavations and construction; and as may be required to protect the workers and the public, or to maintain the trench widths specified in Section 02300 regardless of whether the same is or is not considered necessary by the CONTRACTOR.
3.Trench supporting shall be individually designed by a registered professional engineer for trench conditions where necessary.

1.02 JOB CONDITIONS

A. Responsibility for Condition of Excavation:

1. The failure or refusal of the AUTHORITY / AUTHORITY REPRESENTATIVE to suggest the use of bracing or sheeting, or better quality, grade, or section, or larger sizes of steel, or to suggest sheeting, bracing, struts, or shoring to be left in place, shall not in any way or to any extent relieve the CONTRACTOR of any responsibility concerning the condition of excavation or of any of his obligations under the Contract, nor impose any liability on the ENGINEER, AUTHORITY REPRESENTATIVE, or the AUTHORITY; nor shall any delay, whether caused by any action or want of action on the part of the CONTRACTOR, or by any act of the ENGINEER, the AUTHORITY, or their agents, or employees, resulting in the keeping of any excavation open longer than would otherwise have been necessary, relieve the CONTRACTOR from the necessity of properly and adequately protecting the excavation from caving or slipping, nor from any of his/her obligations relating to injury to persons or property.

PART 2 - PRODUCTS

2.01 MATERIALS

A. Steel Materials: Steel sheet piling and bracing of suitable, and as designed by a professional engineer where required.

B. Trench Boxes (Also called trench shields): Specially manufactured structures consisting of two large plates, which are parallel to trench walls, and horizontal cross members that hold the plates apart. Workers shall stay between plates when below grade.

PART 3 - EXECUTION

A. Using skilled labor, drive or set sheet piling, bracing, shoring or trench boxes in place and arranged such that they may be withdrawn or moved as structures, and without injury to or settlement of adjacent structures and pavements.

B. When tight plank or steel sheeting is required, drive such sheeting in advance of the excavation. Make joints of tongue and groove or interlocking type and as watertight as possible.

C. Where the maximum width of trench may be exceeded under these Specifications and where permitted by Federal and State regulations, the sides of the trench may be sloped; the slope shall begin at a point of 12 inches above the top of the pipe. Install sheeting to support the vertical part of the excavation as required by Federal and State regulations.

D. Remove sheeting, bracing and shores as trenches and other excavations are being backfilled, except where and to such an extent as the ENGINEER/AUTHORITY may require, in writing, that same be left in place or where he/she shall permit the CONTRACTOR to leave same in place at the CONTRACTOR’s own request and cost.

1. In withdrawing sheeting and sheet piling, exercise care to insure that all voids or holes left by planks as they are withdrawn, are backfilled and thoroughly rammed with thin rammers provided especially for that purpose.

2. Exercise care to carry backfill up evenly on all sides of items installed in excavations.

E. Cut off sheeting or sheet piling left in place whenever and at such points as the ENGINEER / AUTHORITY shall require and remove from the work the portion cut off. No additional compensation will be allowed for cutting and removal.

SECTION 02320 – EROSION AND SEDIMENTATION CONTROL

PART 1 - GENERAL

1.01 SCOPE OF WORK

A. The purpose of this Erosion and Sedimentation Control Plan is to provide the CONTRACTOR with general guidelines as well as specific techniques for minimizing erosion and sedimentation during and after construction of the project. During construction all attempts shall be made to minimize the potential for erosion and sedimentation problems. All work shall comply with the approved Project Plans and the permits that have been issued for this project.

PART 2 - PRODUCTS

A. Products used to control erosion and sedimentation are as follows. They will be used to temporarily control erosion, primarily at the sites where soil removed from the trench is wasted or stored. They will also be used if protection is required at construction sites that cross small streams. See drawings for item descriptions not included here.

1. Straw bales shall be wire or nylon bound bales.

2. Silt socks shall be constructed of a geotextile fabric (filter cloth) that is manufactured specifically for this purpose.

3. Posts for silt socks shall be either wood or steel with a minimum length of 24 inches.

PART 3 - EXECUTION

A. The CONTRACTOR shall adhere to the following requirements in an effort to control erosion and sedimentation.

1.The CONTRACTOR shall not disturb ground cover areas beyond those necessary to satisfactorily complete the required work.
2.All temporarily stockpiled fill at the site will be covered or otherwise stabilized to prevent erosion when precipitation is imminent. Grassy areas between the construction area and stream shall be maintained.
3.The following temporary methods to control erosion are to be followed:
a.Silt socks shall be constructed along the downslope of the work areas to filter any silt-laden runoff from the construction area. Place silt socks around temporary stockpiled topsoil or other soil material. Construction details for silt sock installations are included on the plans.
b.Temporary seeding shall be performed as outlined under seed mixtures.
4.Permanent seeding shall be performed as outlined later in this section.
5.Where wind and dust erosion is a problem, the unstable surface shall be sprinkled, or a dust suppressor will be supplied. Prompt establishment of vegetative soil cover and placement of gravel in specified areas will minimize wind erosion and dust problems.
6.The CONTRACTOR is responsible for ensuring that sediment is not transported from the construction site.
7.Before any construction commences all erosion control measures and silt socks must be in place. They must remain in place and be maintained until the construction area can be permanently stabilized.
8.Silt socks shall be constructed along the downslope section of the construction area. Maintain silt socks by removing sediment when it reaches 1/2 the height of sock.
9.A stabilized construction entrance will be constructed. Maintain by replacing rock as necessary.

10. A rock filter will be placed surrounding the inlet to the existing storm sewer. Maintain by cleaning and replacing rock as necessary.

11. In the event that the site is not permanently stabilized within 14 days, temporary seeding shall take place. All areas of slopes of 3 horizontal to 1 vertical or less shall be temporarily or permanently stabilized within (7) days. Temporary seeding shall be as follows:

a.Apply (1) ton of lime per acre.
b.Apply fertilizer at the rate of 50-50-50 lbs. per acre of N, P205 and K2O, respectively.
c.Place mixture of annual ryegrass at the rate of 40 lbs. per acre. This mixture may vary depending on seasonal conditions.
d.Mulch with straw or hay at the rate of (3) tons per acre.

12. Permanent stabilization shall be as follows:

a.Remove coarse fragments from surface and till top soiled areas to a depth of 3 inches (min.).
b.Seeding: Apply seed uniformly. When not using a hydro seeder, seed should be applied to a maximum depth of 1/4 inch on clayey soils and 1/2 inch on sandy soils. Seed mixture shall be a suitable combination of grasses suited for the type of soil and the desired conditions. All seed specifications such as purity, ready germ, total germ, etc., shall be in accordance with the Penn State Agronomy Guide. Seeded areas shall be protected by Mulching in accordance with PennDOT Publication 408. Liming and fertilizer shall be applied as required to obtain a uniform erosion resistant vegetative coverage. The following rates (per acre) represent an estimate of the required amount. The CONTRACTOR may need to exceed or may be able to reduce the rate indicated.

(1) One ton of lime per acre.

(2) 1000 lbs. per acre using 10 -10 -10.

c.Do not sow immediately following rain or when ground is too dry or during windy periods.
d.If areas are to remain disturbed from November 1 through March 1 (non-growing season), the CONTRACTOR shall protect seed areas by seeding and mulching, sodding, or by placement of matting as necessary. This work shall be done in accordance with PennDOT Publication 408.

13. Wastewater Collection Mains and Lines in Off-Street Rights-of-Way Including Collection System Adjacent to Streams:

The following are erosion control procedures and techniques to be employed when constructing sewers and/or water mains in off-street rights-of-way including those adjacent to streams:

a.Where possible material excavated from trenches shall be cast on the high side of the trench to allow erosion runoff from the excavated material to be intercepted by the trench.
b.All material not replaced in the trenches shall be removed and disposed of promptly and in a manner that minimizes erosion. Disposal sites where the material is stored shall be protected by sedimentation basins and/or silt socks. Where the material is spread, the material shall be stabilized with the appropriate ground cover.
c.All trench dewatering shall be to a properly constructed and maintained sedimentation area.
d.Excess material shall not be temporarily stored unless the CONTRACTOR can demonstrate that it is adequately protected from erosion and sedimentation. No stockpiling of soil material shall take place on asphalt.

14. Dewatering Sewer/Water Line Trenches and Excavation Pits:

If the occasion should arise that excavations will need to be dewatered so that construction can resume and pumping is required one of the following methods, whichever is most applicable, shall be used:

a.Discharge over areas with extensive vegetation. Check for signs of soil removal over the discharge area. If so, discontinue pumping and construct a sediment trapping facility in accordance with Adams County Conservation District standards and details.
b.Construct a compost sock sediment trap. Socks should be staked with two 2”X2”X4’ wooden stakes per PA Standard Construction Detail #3-11. Effluent from the sediment trap should be spread over a vegetated area.
c.Construct a temporary lagoon (silt holding basin) for pumping discharge or applying silt-laden runoff. Allow for the following conditions:

(1) A detention time of approximately two hours.

(2) A two foot freeboard.

(3) Prevent short-circuiting with the use of plywood baffles.

d. Discharge directly to the stream without a method of filtering silt will be prohibited.

15. Construction Sequence:

a.Notify the appropriate County Conservation Districts a minimum of (7) days prior to the start of construction or in accordance with the permit.
b.Perform construction stake out and locate all underground utilities relative to and in the vicinity of this project per PA State Regulations.
c.Install stabilized construction entrance, silt socks, rock filter, and all Erosion and Sediment Control Measures.
d.Perform construction activities, final grading, and permanent stabilization. Spread topsoil over areas prior to planting.
e.Following establishment of permanent seeding relative to all earth moving activities to a point where 70% minimum uniform perennial vegetative cover has been established, the erosion and sediment control measures shall be removed.

16. Additional Sewer/Water Main Installation Specifications

a.Limit advance clearing and grubbing operation to a distance equal to two times the length of pipe installation that can be completed that day.
b.Limit daily trench excavation to the length of pipe placement installation and backfilling that can be completed each day.
c.On the day following pipe placement and trench backfilling, the disturbed areas shall be graded to final contours and appropriate temporary erosion control measures installed. Seeding and mulching of all disturbed areas shall be done at the end of each week.
d.Place excavated material on upslope side of trench. All material not used in backfill shall be stockpiled and temporarily seeded.

17. Collection System Construction Involving Stream Crossings:

The following are erosion control procedures and techniques to be employed in the construction of stream crossings:

a.All work shall be done in a manner that will minimize erosion and runoff of silt-laden water to the stream.
b.After starting construction of an individual crossing, work shall be continuous until that crossing is complete. This shall include removal of all temporary construction and erosion control devices and the grading, seeding, and mulching of disturbed areas as required.
c.Stream crossings made in accordance with any of the General Permit issued by the Department of Environmental Protection for the particular stream crossing. A copy of the General Permit for this stream crossing is found in these specifications (if applicable).
18. Erosion Control Facilities Temporary Maintenance Schedule:

The CONTRACTOR shall implement the following maintenance schedule at a minimum. Maintenance shall begin immediately following installation of the erosion and sediment control measures and shall be followed until the facility is removed in accordance with this plan:

MeasureScheduleDescription
Silt SocksDaily & after allInspect, repair, and remove
Storm Eventssediment when accumulation reaches 1/2 height of sock (above ground).

Seeded/Mulched Weekly Inspect, replace any materials Areas necessary. Reseed as req’d.

Temporarily Weekly & After Inspect, Re-seed. Repair silt sock Stockpiled Soil all storm events if necessary. Remove sediment from silt sock at 1/2 height of sock.

DIVISION 2 - SITEWORK

SECTION 02400 - BORING AND JACKING

PART 1 - GENERAL

1.01SCOPE OF WORK
A.This section consists of all work associated with installing sewer or water line in a liner conduit under highways by trenchless methods.

B. Related Work Specified Elsewhere:

1.Shoring: Section 02310
2.Excavation and Backfill: Section 02300

3. Pipe, Valves and Appurtenances & Installation Methods: Section 02590

4. Cast-In-Place Concrete: Section 03300

1.02SUBMITTALS
A.Workmen Qualifications:

1. Use only personnel thoroughly trained and experienced in the skills required.

B.Design Criteria:
1.Encasing conduit under highways shall be of sufficient strength to support all superimposed loads, including an American Association of State Highway and Transportation Officials H-20 Loading with 50% added for impact.
C.Source Quality Control:
1.Shop Tests: Each pipe manufacturer must have facilities to perform listed tests. The ENGINEER reserves the right to require the manufacturer to perform such additional number of tests as the ENGINEER may deem necessary to establish the quality of the material offered for use.
MATERIALTEST METHODNUMBER OF TESTS

a. Steel Pipe ASTM A53/A53M-20 As specified in ASTM A53/A53M-20

2. Laboratory Tests: The ENGINEER reserves the right to require that laboratory tests also be conducted on materials that are shop tested. Furnish without compensation, labor, materials, and equipment necessary for collecting, packaging, and identifying representative samples of materials to be tested and the shipping of such samples to the Testing Laboratory.

1.03SUBMITTALS
A.Shop Drawings and Product Data: Furnish completely dimensioned shop drawings, cuts or other data as required to provide a complete description of Products to be installed.
B.Certificates: Certified records or reports of results of shop tests, such records or reports to contain a sworn statement that shop tests have been made as specified.
C.Furnish to the ENGINEER, detail drawings, accompanied by design calculations, for boring pits including sheeting and bracing therefore, steel pipe and boring procedure and all such drawings and computations shall bear the seal of a Registered Professional Engineer.

1.04 PRODUCT DELIVERY, STORAGE AND HANDLING

A. Transport, handle and store materials and Products specified herein in a manner recommended by the representative manufacturers of such to prevent damage and defects.

1.05 JOB CONDITIONS

A. Classification of Materials:

1.Roadway Crossing Boring: No consideration will be given to the nature of materials encountered in the boring for roadway crossings. Remove rock encountered during the boring operation except as provided in the following paragraph.
a.Where rock is encountered during the boring of an encasing conduit which is such that in the judgment of the ENGINEER the boring of the encasing conduit cannot be continued, discontinue boring. Construct the remaining portion of the sewer or water line across the roadway by open cut method meeting with the approval of the ENGINEER.
b.If the highway crossing is constructed by open cut methods, provide the same casing pipe that was required for the bored crossing.
c.CONTRACTOR shall not obstruct streets, roads and highways. Unless the Municipality or Governing Agency authorizes in writing the complete closing of the street, road or highway, employ such measures at no expense to the OWNER as may be necessary to keep the street, road or highway open and safe for traffic. Maintain a straight and continuous passageway on sidewalks and over crosswalks, at least three feet wide and free from obstructions. DO NOT OBSTRUCT FIRE HYDRANTS.

PART 2 - PRODUCTS

2.01 ENCASING CONDUIT

A. Steel Pipe: ASTM A53/A53M-20 or A139/A139M-16

1. Minimum Diameter: As determined by the size of the carrier pipe. The casing pipe shall have an inside diameter at least 2 inches greater than the outside diameter of the carrier pipe joint assembly.

2. Casing spacers shall be utilized for support between carrier pipe and liner pipe as shown in the detail drawings provided herein. Acceptable manufacturer shall be the Ford Meter Box Co., Inc. or as otherwise approved by OWNER.

PART 3 - EXECUTION

3.01INSPECTION
A.Inspect materials and products before installing in conformance with the inspection requirements of the appropriate referenced standard.
B.Remove rejected materials and products from the Project.

3.02 PERFORMANCE

A. Boring:

1. Boring shall conform to acceptable trade practices and additional requirements specified herein.

a. Install the encasing conduit by the boring method to the limits specified or such additional limits required by the ENGINEER.

b. Excavate and sheet boring pit.

c. Provide devices at the front of the pipe to prevent auger and cutting heads from leading the encasing conduit. Unsupported excavation ahead of the pipe is prohibited.

d. Over-cut by cutting head not to exceed the outside diameter of the encasing conduit by more than one-half inch.

e. The use of water or other liquids to facilitate casing placement and spoil removal is prohibited.

f. Check conduit alignment in a manner and at times required by ENGINEER.

g. Completely weld joints around the circumference between sections of steel pipe encasing.

2. Testing: After laying pipe in encasing conduit conduct line acceptance testing as specified in Section 02510 or Section 02590.

3. Should the CONTRACTOR in constructing any boring pit excavate below the subgrade for the sewer/water main, he will be required to backfill the area excavated below the subgrade with Aggregate Backfill or with concrete as required by the ENGINEER at his own expense and at no cost to the OWNER.

DIVISION 2 – SITEWORK

SECTION 02590 – PIPE, VALVES AND APPURTENANCES & INSTALLATION METHODS

PART 1 – GENERAL

1.01 SCOPE OF WORK

A. This section consists of furnishing and installing all pipe, valves, and appurtenances used in this project.

1.02 SUBMITTALS

A. Shop Drawings and Product Data. Submit completely detailed shop drawings or other data as required to provide a complete description of materials as outlined in this Section.

B. Certificates. A manufacturer’s certified statement shall be submitted certifying that the materials will be supplied in accordance with the specified reference standards when alternative materials are proposed.

PART 2 - PRODUCTS

2.01 PIPE

A. Ductile Iron Pipe:

1. Manufacture-Ductile Iron Grade 60-42 ANSI/AWWA C151/A21.51-17.

2. Wall Thickness-Class 52 for all sizes ANSI/AWWA C150/A21.50-14.

3. Cement Mortar Lining-Double Thickness ANSI/AWWA C104/A21.4-16.

4. Joints-Push on Tyton ANSI/AWWA C111/A21.11-17.

5. Nominal laying length-18 ft. or 20 ft.

6. Manufacture certification required.

7. Ductile Iron Pipe to be Griffin or Approved Equal.

B. PVC Pipe:

1. Manufacture-PVC Pressure Pipe ANSI/AWWA C-900-16.

2. Wall Thickness-DR-18 for all sizes ANSI/AWWA C-900-16 Cell Classification 12454 (ASTM…