About this file

This Statement of Work outlines requirements for parking lot sealcoat treatment and striping services at two National Weather Service (NWS) Weather Forecast Office locations in Pocatello, ID and Las Vegas, NV. The scope includes crack repair, seal coating, and re-striping of parking stalls including handicap spaces at facilities covering 14,350 ft² in Pocatello and 14,500 ft² in Las Vegas.

Key requirements include cleaning and sealing cracks between 1/8" to 2" wide, saw-cutting and repacking cracks larger than 2", surface preparation, applying commercial-grade sealer with 3+ years of proven performance, and restriping to AASHTO specifications. The contractor must begin work within 10 days of award and complete within 240 calendar days of receiving materials. Work hours are 0700-1600 Monday-Friday excluding federal holidays. The contractor must provide all labor, materials, and equipment, submit material specifications within 10 days of award, maintain safety protocols, and provide a 1-year warranty. Invoicing is through the Invoice Processing Platform (IPP) with payment terms of Net 30.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Parking Lot Sealcoat Treatment and Striping

1. BACKGROUND:

The National Weather Service (NWS), Weather Forecast Office (WFO’s) in Pocatello, ID and Las Vegas, NV have parking lots that have not been resealed in 10-15 years and are in severe need of treatment. The existing surface has deteriorated with large cracks.

2. GENERAL INTENTION:

To obtain the services of crack repair, seal coat and re-striping parking stalls to include one handicap stall with handicap symbol.

3. GENERAL REQUIREMENTS:

The contractor shall provide all supervision, labor, tools, materials and equipment necessary to perform work as stated. All work and materials supplied shall be in accordance with these instructions, manufacturer’s specification, all applicable federal, state, local, OSHA, EPA, NEC, NFPA, building and facilities codes and criteria.

The Contractor Shall:

3.1. Provide, as necessary, sufficient traffic barricades while the work is in progress to restrict access to the work area until the sealer application and re-striping work is completed. Remove the barricades only after notifying the Contracting Officer’s Representative (COR) that the work is complete and vehicle access is authorized.

3.2. Contractor shall verify all measurements stated below for WFO specifications.

Total Asphalt area for each site is listed below.

● Pocatello, ID - 14,350 ft2

● Las Vegas, NV - 14,500 ft2

3.3. The material used is within its manufacturer stated shelf life; proof of shelf life shall be provided to the

COR.

3.4. Prior to surface cleaning, clean out all cracks using compressed air, and seal all cracks between 1/8” to 2” in the pavement using an approved crack sealant. The crack sealant shall be compatible with the surface sealer being applied to the asphalt paved areas of this project.

3.5. Repair cracks that are larger than 2” in width by saw cutting. Remove 6” of old material on each side of the crack (1 foot in total). Pack removed area with new asphalt.

3.6. Before applying the sealer, all foreign material shall be removed from the surfaces to be treated including stall striping tape, loose material, dirt, clay, oil and grease spots. Oil and grease spots shall be cleaned and spot primed. After the cleaning operation and prior to application of the sealer, the

Contractor will inspect the area to be treated to determine its ability to receive the sealer.

3.7. The asphalt sealer shall be of a type that has been used commercially in the specified areas for at least the past three years. The sealer shall also have a proven record of satisfactory performance based on the ability of the material to reduce the rate of loss of fines and to retard crack propagation of the pavement.

3.8. All pavement markings which existed prior to the application of the surface sealer shall be reestablished by the contractor after the manufacturer-recommended curing period. All guidelines and templates shall be furnished by the contractor. Finished edges of all markings shall be sharply outlined. Paint colors shall be those as specified by the American Association of State Highway and Transportation Officials (AASHTO) for the intended use.

4. ATTACHMENTS

● Pocatello WFO Drawing

● Las Vegas WFO Drawing

5. SUBMITTAL REQUIREMENTS:

The contractor shall provide electronic copy of each required submittal in accordance with the below schedule:

Deliverable Objective Due Deliver To

Specification sheets describing in detail the marking paint to be used for all sites

Determine material to be used Within 10 days of awarded contract

COR

Specification sheets describing in detail the crack sealing material to be used for all sites

Determine material to be used Within 10 days of awarded contract

COR

Specification sheets describing in detail the surface sealing material to be used for all sites

Determine material to be used Within 10 days of awarded contract

COR

Work Schedule, with start and completion dates

Coordinate scheduling with

NWS

Within 3 days of awarded contract, or before work begins

COR

Designation of on-site, job-site supervisor and contact information

Provide a primary Point Of Contact (POC) to NWS

Contract Award COR

1-year Warranty Documentation Warranty parts and labor Upon acceptance of work

Contracting Officer (CO)

SDS (Safety Data Sheet)

List any hazardous material that will be used in performance of this contract.

Ref. FAR 52.223-3 and FED-

STD-313E

Within 3 days of awarded contract, or before work begins, whichever occurs first

CO/COR

6. LOCATION:

Project is to be completed on the below premises.

● Pocatello, ID - 1945 Beechcraft Ave. Pocatello, ID 83204

● Las Vegas, NV - 7851 Dean Martin Dr. Las Vegas, NV 89139

7. PERIOD OF PERFORMANCE:

Work must begin within ten (10) business days of award of the purchase order; “Work” includes ordering materials not already in stock and necessary to perform the work. On site work shall be completed within two hundred and forty (240) calendar days of receipt of all necessary materials.

8. DEFINITIONS:

Where “as shown”, “as indicated”, “as detailed”, or words of similar import are used, it shall be understood that reference to the drawings accompanying this specification is made unless stated otherwise.

Where “as directed”, “as required”, “as permitted”, “approved”, “acceptance”, or words of similar import are used, it shall be understood that the direction, requirements, permission, approval, or acceptance of the CO is intended unless stated otherwise.

As used herein, “provided” shall be understood to mean “provided complete in place”, that is “furnished and installed”.

9. REGULAR WORKING HOURS:

Regular working hours are from 0700 to 1600 Monday through Friday except Federal holidays and other days specifically designated by the designated representative. “Regular Working Hours” means hours a contractor can expect to be allowed to perform work on site, or be able to contact the office. Anything outside regular working hours must be done by permission of the COR.

Observance of Legal Holidays and Site Closure Information The Contractor shall observe any federal holidays if the holiday falls within the period of performance of this contract.

When any holiday falls on a Saturday, the preceding Friday is observed; when any holiday falls on a Sunday, the following Monday is observed. All personnel assigned to this contract shall limit their observation of holidays to those set forth above.

In each instance, the Contractor agrees to continue to provide sufficient personnel to perform requirements of any critical tasks already in operation or scheduled, and shall be guided by the instructions issued by the COR. In the event of a site dismissal or closure due to weather, emergency or other circumstances, the Contractor is instructed to contact the COR.

2025 Holiday Schedule

Date Holiday Wednesday, January 01 New Year’s Day

Monday, January 20 Birthday of Martin Luther King, Jr.

Monday, January 20 * Inauguration Day

Monday, February 17 ** Washington’s Birthday

Monday, May 26 Memorial Day

2025 Holiday Schedule Date Holiday

Thursday, June 19 Juneteenth National Independence Day

Friday, July 04 Independence Day

Monday, September 01 Labor Day

Monday, October 13 Columbus Day

Tuesday, November 11 Veterans Day

Thursday, November 27 Thanksgiving Day

Thursday, December 25 Christmas Day

*This holiday is designated as "Inauguration Day" in section 6103(c) of title 5 of the United States Code, which is the law that specifies holidays for Federal employees. Federal employees in the Washington, DC, area are entitled to a holiday on the day a President is inaugurated on January 20th for each fourth year after 1965.

**This holiday is designated as "Washington's Birthday" in section 6103(a) of title 5 of the United States Code, which is the law that specifies holidays for Federal employees. Though other institutions such as state and local governments and private businesses may use other names, it is our policy to always refer to holidays by the names designated in the law.

10. CONDUCT OF WORK

The contractor must ensure employees are physically able to accomplish the work specified herein. All such employees working on government premises are subject to all applicable federal rules and regulations with regard to entering and leaving the premises and building(s). Any contractor employee who is considered incompetent, careless, insubordinate, unsuitable, or otherwise objectionable or whose continued employment is contrary to the public interest by the government’s designated representative will be promptly removed from the contract work upon notification to the contractor by the Contracting Officer that such conditions(s) described above exist. Only legal US citizens and immigrants are allowed to work on federal government construction projects.

11. SAFETY REQUIREMENTS:

All work shall be conducted in a safe manner and shall comply with station regulations and Department of Labor Standards. The government will not provide safety equipment to the contractor. The contractor’s work site may be inspected during performance of the contract for OSHA and station safety violations. It will be the contractor’s responsibility to rectify any violations immediately.

The contractor shall report any accidents that occur during the performance of the contract to the CO or a designated representative, within 24-hours of an occurrence.

Provide and maintain fire extinguishers in construction areas. Flammable and Combustible Liquids: Store, dispense and use liquids in accordance with 29 CFR 1926, NFPA 241 and NFPA 30.

12. SECURITY REQUIREMENTS:

All personnel performing work under this contract shall be legal citizens or legal immigrants of the United States.

13. IDENTIFICATION OF CONTRACTOR VEHICLES:

Each Contractor provided vehicle shall show the Contractor’s name that is clearly visible and let the Administrative Assistant at the front desk know what vehicle belongs to you as the contractor. Display a valid State license plate and safety inspection sticker, if applicable. Contractor vehicles operated on Government property shall be maintained in good repair.

14. STATION REGULATIONS:

The contractor and his employees shall become acquainted with and obey all government regulations as posted, or as requested by the COR.

15. GOVERNMENT-FURNISHED EQUIPMENT, UTILITIES, AND FACILITIES:

A designated representative will, upon request, designate specific areas adjacent to the building and within the existing parking lot, specific areas for the delivery and lay-down of materials and equipment to be used by the contractor specific to this work. Utilities, such as electricity specific to this work will be supplied by the government.

16. CLEANUP:

The premises shall be kept free at all times from accumulation of waste and/or rubbish resulting from the work. Upon completion of the work, all debris, tools and surplus materials shall be removed and the entire area shall be left in a neat and clean condition. All debris, trash, waste and surplus material shall be properly disposed of off-site.

17. POINTS OF CONTACT:

TO BE PROVIDED AT TIME OF AWARD.

18. INVOICING:

Upon completion and acceptance of the work, the invoice shall be submitted via the Invoice Processing Platform (IPP). The NWS designated representative to certify for payment is Mike Kent.

Observance of Legal Holidays and Site Closure Information