1CA2979 RLP ExhB10_CIS-SF ASR-10-USCIS_BIM_Requirements.pdf_8_29_2022.pdf

PDF 159 KB Posted

Attached to
General Services Administration (GSA) seeks to lease office space in San Francisco, CA
Solicitation number
1CA2979
Issued by

About this file

This document contains the Building Information Modeling (BIM) requirements for a federal lease solicitation issued by the General Services Administration (GSA) for office space in San Francisco, CA. The key details are:

The solicitation requires the use of BIM modeling and data for the design and construction of the leased space. Specific requirements include using Autodesk Revit for the BIM model, providing IFC coordination views, conducting design reviews, and submitting final as-built BIM and CAD files. The document outlines the BIM submittal requirements at various design stages, the minimum modeling and data requirements, and definitions of key terms. The solicitation also provides details on the leased space requirements, such as size, parking, ceiling heights, and other building characteristics. Offers are due by July 31, 2024 for an anticipated occupancy in January 2026.

View the file

Other files

File Type Posted
1CA2979 RLP ExhB1_CIS-SF ASR General-v4.1_8_29_2022_Updated.pdf PDF
1CA2979 RLP ExhB2_CIS-SF ASR-02-RLP_USCIS_FSL_Attachment_August_2015.pdf_8_29_2022.pdf PDF
1CA2979 RLP ExhA_CIS-SF L100.pdf PDF
1CA2979 RLP ExhF_Form12000_FLS_PartsA-B_2018_12 CIS-SF.docx DOCX document
1CA2979 RLP ExhB11_CIS-SF ASR-11-USCIS_Minimum_Modeling_Matrix_(M3).pdf_8_29_2022.pdf PDF
1CA2979 RLP ExhI_Foreign Ownership Reps 552.270-33_Jun21.pdf PDF
1CA2979 RLP ExhD_3516 Solicitation Provisions (Oct. 2023)_CIS-SF.pdf PDF
1CA2979 RLP ExhH_FAR 52.204-24 Reps Rev 10.2020_CIS-SF.pdf PDF
1CA2979 RLP ExhB7_CIS-SF ASR-07-USCIS_Computer_and_Telephone_Room_AppendixA_8_29_2022.pdf PDF
1CA2979 RLP ExhB9A_CIS-SF ASR-09A-USCIS_Signage_Standards_8_29_2022.pdf PDF
1CA2979 RLP ExhB3_CIS-SF ASR-03-Physical Security Construction Standards.pdf PDF
1CA2979 RLP ExK_SmBizSubPlan Leasing Model - Jan 2023.docx DOCX document
1CA2979 RLP ExhB2_CIS-SF ASR-02_FSL_Attachment_20150829_Updated.pdf PDF
1CA2979 RLP SF Final 240627.pdf PDF
1CA2979 RLP ExhB5_CIS-SF ASR-05-USCIS_Structured_Cable_Plant_Standard_8_29_2022.pdf PDF
1CA2979 RLP ExhB6_CIS-SF ASR-06-USCIS_Computer_and_Telephone_Room_Standard_8_29_2022.pdf PDF
1CA2979 RLP ExhG_Seismic Offer Forms A - F with instructions CIS-SF.docx DOCX document
1CA2979 Sensitive Information.pdf PDF
1CA2979 RLP ExhJ_GSAR Clause 552.270-34_accesslimitation_Jun21.pdf PDF
1CA2979 RLP ExhB8_CIS-SF ASR-08-USCIS_AV_Standards_1APR20.pdf_8_29_2022.pdf PDF
1CA2979 RLP ExhB3Annex I_Supporting Document for Physical Security Construction Standards.xlsx XLSX spreadsheet
1CA2979 RLP ExhE_3517B General Clauses (Oct. 2023)_CIS-SF.pdf PDF
1CA2979 RLP ExhB9B_CIS-SF ASR-09B-USCIS_Family_of_Signs_180509_v9.pdf_8_29_2022.pdf PDF
1CA2979 RLP ExhC_FSL3 Requirements_CIS-SF 240423.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCIS Building Information Modeling Requirements Page 1 of 6

BUILDING INFORMATION MODELING REQUIREMENTS

1.0 Section 1 - General

1.1 Definitions. See Section 7 for definitions of terms used in this document.

1.2 Submittal Format

1.2.1 The Model shall be developed using Building Information Modeling (“BIM”) supplemented with Computer Aided Design (“CAD”) content as necessary to produce a complete set of Construction Documents. Submitted drawings shall be «FULL_SIZE» size, suitable for half-size scaled reproduction.

1.2.2 BIM submittals shall conform to the requirements of Sections 3.0 and 4.0 below.

1.2.3 For each facility included in this Project, all Models and associated Facility/Site Data shall be submitted in the latest version of Autodesk Revit. The submittals shall be fully operable, compatible, and editable within the native BIM tools.

2.0 Section 2 – BIM Requirements

2.1 Use of BIM. Lessor shall use BIM application(s) and software(s) to develop Projects consistent with the following requirements.

2.1.1 Baseline Model. The Lessor will not be provided a baseline multi-discipline BIM Project Model.

2.1.2 BIM Program Configuration Standards. A BIM Standard will not be provided; Lessor can select which Revit templates and resources to use.

2.1.3 Industry Foundation Class (IFC) Support. The Lessor’s selected BIM application(s) and software(s) must be commercially available, object oriented, collaboration software applications that comply with current industry interoperability standards between different software applications. Any deviations from or additions to the IFC property sets for any new spaces, systems, and equipment must be submitted for Government acceptance.

2.2 BIM Content Facility/Site Data. Develop the Facility/Site Data to include material definitions and attributes that are necessary for the Project facility design and construction as described in Section 4.0.

2.2.1 Model Content. The Model and Facility/Site Data shall include, at a minimum, the requirements of Section 4.0 below.

2.3 Output. Submitted Drawings (e.g., plans, elevations, sections, schedules, details, etc.) shall be derived (commonly known as extractions, views or sheets) from the Model and Facility/Site Data.

Drawings derived from the Model shall remain connected to the Model for the life of the Project.

Drawings not derived from the Model shall also be documented in a separate report with each submittal by the Lessor and agreed upon by the Government.

2.3.1 Drawings derived from the Model shall be compliant with the A/E/C CAD Standard.

2.3.2 The CAD file format specified for drawings shall not dictate which application(s) are used for development and execution of the Model and Facility/Site Data.

2.4 Quality Control Parameters. Implement quality control (“QC”) parameters for the Model, including:

USCIS Building Information Modeling Requirements Page 2 of 6

2.4.1 Model Standards Checks. Provide QC checks demonstrating that the Project Facility/Site Data set has no undefined, incorrectly defined or duplicated elements. Identify and report non-compliant elements and submit a corrective action plan. Provide the Government with detailed justification and request Government acceptance for any non-compliant element that the Lessor proposes to be allowed to remain in the Model.

2.4.2 CAD Standards Checks. Provide QC checks demonstrating that the fonts, dimensions, line styles, levels and other construction document formatting issues are followed. Identify and report non-compliant content and submit a corrective action plan.

2.4.3 Other Parameters. Develop such other QC parameters as Lessor deems appropriate for the Project and provide to the Government for acceptance.

2.5 Design and Construction Reviews. The Model and Facility/Site Data will be used to perform reviews at each submittal stage under Section 3.0 to test the Model, including Over-The-Shoulder Progress Reviews:

2.5.1 Visual Checks. Checking to demonstrate the design intent has been followed and that there are no unintended elements in the Model.

2.5.2 Interference Management Checks. Locate conflicting spatial data in the Model where two elements are occupying the same space. Log hard interferences (e.g., mechanical vs.

structural, or mechanical vs. mechanical, overlaps in the same location) and soft interferences, (e.g., conflicts regarding equipment clearance, service access, fireproofing, insulation, code space requirements) in a written report and resolve.

2.5.3 Over-The-Shoulder Progress Reviews. Periodic quality control meetings or construction progress review meetings shall include quality control reviews on the implementation and use of the Model, including interference management and design change tracking information.

2.6 Other Parameters. Develop other design and construction review parameters as the Lessor deems appropriate for the Project and provide to the Government for acceptance.

3.0 Section 3 – BIM Submittal Requirements

3.1 General Submittal Requirements.

3.1.1 Provide submittals as described below.

3.1.2 For each Submittal as set forth in Paragraphs 3.3 through 3.5, provide a Lessor-certified written report confirming that consistency checks as identified in Paragraphs 2.4 and 2.5 above have been completed. This report shall be discussed as part of the review process and shall address cross- discipline interferences, if any.

3.1.3 At each Submittal as set forth in Paragraphs 3.3 through 3.5, provide the Government with:

3.1.3.1 The Model, Facility/Site Data, Workspace and CAD Data files in the native

BIM/CAD format.

3.1.3.2 A copy of the Model in an interactive review format such as Autodesk

Navisworks, Adobe 3D PDF 7.0 (or later), Google Earth KMZ or other format.

The format for reviews can change between submittals.

3.1.3.3 A list of all submitted electronic files including a description, directory, and file name for each file submitted. For all CAD printed sheets, include a list of the sheet titles and sheet numbers. Identify which files have been produced from the Model and Facility/Site Data.

3.1.3.4 IFC Coordination View. Provide an IFC Coordination View in IFC Express format for all deliverables. Provide exported property set data for all IFC supported named building elements.

3.1.3.5 At each Review meeting, conduct a demonstration to review the BIM Model for clarification, and to verify the functionality of planned Model technology workflow and processes. If modifications are required, the Lessor shall complete the modifications.

3.1.4 The Government shall confirm acceptability of all submittals identified in Section 3.0.

USCIS Building Information Modeling Requirements Page 3 of 6

3.2 Initial Design Submittal.

3.2.1 Review the Minimum Modeling Matrix (M3) with the USCIS Project Manager(s) prior to the first Design Intent Document submission where, in addition to Paragraph 3.1.4.

3.3 Interim Design Submittals.

3.3.1 BIM and CAD Data. Submit the Model with Facility/Site Data per the requirements identified in Paragraphs 2.2 and 2.3 as applicable to the Interim Design package(s).

3.4 Final Design Submission and Design Complete Submittals.

3.4.1 BIM and CAD Data. Submit the Model with Facility/Site Data per the requirements identified in Paragraphs 2.2 and 2.3. Acceptance according to Paragraph 3.1.4 is required before commencement of construction.

3.5 Final As-Built BIM and CAD Data Submittal. Submit the final Model, Facility/Site Data, and CAD files reflecting as-built construction conditions for Government acceptance, as specified below:

3.5.1 Coordination. The method of producing the record drawings and their format will be discussed with USCIS at the beginning of the project and accepted by USCIS before issuing the construction solicitation. Upon Substantial Completion, BIM files shall be submitted to USCIS, and shall be cleaned of extraneous “scrap” or “working space” layers, stories, abandoned designs, object creation and testing places, empty layers, and other content which is typically produced in BIM production. The Lessor shall be responsible for providing USCIS consolidated as-built Model(s) for all building systems. The Model(s) shall be fully coordinated and align with the Design Model for architecture and structure; the required instructions on file/folder setup shall also be included:

3.5.1.1 Lessor – Native file formats of the final consolidated as-built Model(s) for building systems used in the multi-discipline coordination process.

3.5.1.2 Lessor – IFC file format of the consolidated building systems models.

3.5.1.3 Lessor - Ensure that the Model(s) remains current with all approved bulletins for overall scope

3.5.1.4 Lessor - Provide As-built drawings in PDF format with fully bookmarked pages.

3.5.1.5 Lessor - Produce hard copy printed set of final documents generated from the

Model

3.5.1.6 DWG format (latest current version) with bound views to each sheet.

3.5.2 Digital Deliverables

All digital deliverables are to be submitted on DVD/CD with the data clearly organized and software version(s) labeled

3.5.2.1 Changes. Show on the working, final record drawings and final Model, but not limited to, the following information:

Any changes within the building structure, elevations, or utilities if changes were made from the contract plans.

Changes in details of design or additional information obtained from working drawings specified to be prepared and/or furnished by the Lessor;

including but not limited to fabrication, erection, installation plans and placing details, pipe sizes, insulation material, dimensions of equipment foundations, etc.

Changes or modifications which result from the final inspection.

Where contract drawings or specifications present options, show only the option selected for construction on the final as-built prints and final Model.

Systems designed or enhanced by the Lessor, such as HVAC controls, fire alarm, fire sprinkler, and irrigation systems.

Modifications (include within change order price the cost to change working and final record drawings to reflect modifications).

USCIS Building Information Modeling Requirements Page 4 of 6

4.0 Section 4 – Minimum Modeling and Data Requirements

4.1 Minimum Modeling Matrix (M3)

4.1.1 Develop an M3 documenting elements included in the facility and site. The M3 describes the minimum modeling and data requirements by defining the Level of Development (“LOD”) and Element Grade. LOD will be determined during the Design Intent Document Phase.

4.1.2 Lessors shall use Attachment H: USCIS Minimum Modeling Matrix (M3).

4.2 Additional Requirements.

4.2.1 Classification. All modeled elements shall include Facility/Site Data referencing one or more classification system(s).

4.2.2 Spatial Data. The Model shall include spatial data defining actual net square footage and net volume, and holding data to develop the room finish schedule including room names and numbers. Include program information to verify design space against programmed space, using this information to validate area quantities.

4.2.3 Schedules. Schedules shall be produced from the Facility/Site Data within the Model. Any exceptions should be submitted to the USCIS for review.

4.2.4 Details and Enlarged Sections. All details and enlarged sections necessary for construction shall be derived from the Model when possible. For those details and enlarged sections not derived directly from the Model, Lessor must verify that geometry and data depicting the details and enlarged sections are consistent with Model elements. Details with significant drafted content such as 'standard' and 'typical' details shall not contradict the model and shall utilize the model as an underlay when possible for the purposes of verification and coordination. Three dimensional, isometric, and section isometric details derived from the model are preferred.

4.2.5 Legends. Model Elements shall be used to produce representations shown in the legends and shall match graphical representations shown in plans, sections, and elevations.

4.2.6 Drawing Indices. Where BIM authoring platform supports it, drawing indexes should be derived from a model-driven schedule.

4.2.7 Model Objects. Model objects shall contain IFC parameters and associated data applicable to building system requirements. These elements shall support the analytic process include size, material, location, mounting heights, and system information where applicable.

4.2.8 Construction Administration. The Lessor shall utilize model geometry and extract graphical information for generating construction administration documents from the Project BIM (RFI’s, Directives, Bulletins, and Change Orders, etc). The Lessor shall record as-built conditions in BIM as part of the final delivery to USCIS. Refer to Section 3.5.

4.2.9 Submittals: Submittal drawings, calculations and analysis shall be extracted from the coordinated BIM

4.2.10 Elements, objects and equipment shall be tagged with unique identifiers.

4.3 Types of Model Elements. Model elements shall be derived from the following sources:

4.3.1 Manufacturer’s Model Elements. Elements created by and acquired from manufacturers often have more information than is prudent to keep in the BIM model; the appropriate level of detail should be retained for the design element. However, embedded performance data shall remain for analysis and specification purposes.

4.3.2 Custom Created Model Elements. Custom model elements that are created must utilize appropriate BIM Authoring tool templates to create custom elements. Custom models components need to be assigned as a part and part of a family or group.

5.0 Section 5 - Ownership and Rights in Data

5.1 Ownership. The Government has ownership of and rights at the date of Closeout Submittal to all CAD files, BIM Model, and Facility/Site Data developed for the Project in accordance with FAR Part 27, clauses. The Government may make use of this data following any deliverable.

USCIS Building Information Modeling Requirements Page 5 of 6

6.0 Space Naming and Coding

6.1 Each space shall include the following attributes and be maintained throughout the Design, Construction, and Final As-built BIM models:

6.1.1 Building

6.1.2 Floor

6.1.3 Programs/ Program Offices/ Directorates

6.1.4 Divisions

6.1.5 Branches (Sub Division)

6.1.6 Space Name – English Name & Abbreviation

6.1.7 Room Number – USCIS Way finding Room Number

6.1.8 Room Number – Construction Document Number (used on large complex projects for builder use)

6.1.9 Space Code – Room Code

6.1.10 Unique Space Number (UID)

6.1.11 Space Type – OmniClass. All spaces, medical equipment, and building equipment and systems shall have an OmniClass code assigned. Use the OmniClass codes provided in the USCIS M3 or if not in the M3, then apply the appropriate OmniClass designation. Use OmniClass Tables 13, 14, and 23 as appropriate, or consult with the Construction Specifications Institute (CSI) for latest tables that apply.

6.1.12 Space Type – Uniformat

6.1.13 Space Measurement –

6.1.13.1 Rentable Square Footage (RSF)

6.1.13.2 Usable Square Footage (USF)

7.0 Definitions

7.1 The following definitions apply specifically to the USCIS BIM Requirements.

7.2 “Model”: A digital representation of physical and functional characteristics of a facility or a part thereof, comprised of “Model Elements” with “Facility/Site Data”.

7.3 “Model Element”: A self-contained element with a unique identification, whose behavior and properties are defined by Facility/Site Data and software processes. Model Elements can represent a physical entity, such as a pump or a concrete wall, and range from the simple to the complex.

7.4 “Facility/Site Data”: The non-graphical information attached to objects in the Model that defines various characteristics of the object. Facility/Site Data can include properties such as parametric values that drive physical sizes, material definitions and characteristics (e.g. wood, metal), manufacturer data, industry standards (e.g. AISC steel properties), and project identification numbers. Facility/Site Data can also define supplementary physical entities that are not shown graphically in the Model, such as insulation around a duct, hardware on a door, content of conduit, or transformer properties.

7.5 “Workspace”: A collection of content libraries and supporting files that define and embody a BIM standard. A workspace includes BIM libraries such as wall types, standard steel shapes, furniture, HVAC fittings, and sprinkler heads. It also contains sheet libraries such as print/plot configurations, font and text style libraries, and sheet borders and title blocks.

7.6 “IFC”: Industry Foundation Class, a standard and file format used for the exchange of BIM data; see www.iai-tech.org. Note: In the context of this attachment, IFC does not mean “Issued For Construction.”

7.7 The terms "drawings," "contract drawings," "drawing files," "working record drawings" and "final

USCIS Building Information Modeling Requirements Page 6 of 6 record drawings" refer to contract drawings and Model which are revised to be used for final record as-built conditions.

7.8 “GUID”: Globally Unique Identifiers are automatically assigned by BIM software. GUIDs must be preserved through generation and regeneration of IFC deliverables so that a given object (space, equipment, etc) can be tracked properly.

File details come from the government source that posted it. Updated .