1b - Draft Hydrogen Conex SOW.docx
DOCX document 24 KB Posted
- Attached to
- AK Hydrogen Conexes
- Solicitation number
- NWWV4100-20-000083_03_12_2020
About this file
This statement of work outlines requirements for the permitting, construction, delivery, and installation of hydrogen conexes and a generic hydrogen system design for the National Weather Service in Alaska. The contractor shall secure permits within 30 days of notice to proceed, construct seven conexes on schedules ranging from 30 to 120 days, deliver the conexes to seven sites on schedules ranging from 30 to 120 days, and install the conexes at the seven sites on schedules ranging from 30 to 120 days. The contractor must also provide a generic hydrogen system design within 30 days. Liquidated damages of $3,000 per day shall be assessed for any delays in meeting the outlined schedules. The contractor must have experience performing this type of work in Alaska and hold all required certifications and licenses.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sources Sought--Hydrogen Conex.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
NATIONAL WEATHER SERVICE
Alaska Region Permitting, Construction, Delivery, and Installation of Hydrogen Conexes (2/12/2020)
The successful offeror shall furnish personnel, material, equipment, services and facilities (except as otherwise specified) to perform this Statement of Work (SOW) in support of the National Oceanic and Atmospheric Administration/National Weather Service (NOAA/NWS) in Alaska. This SOW describes all services required for permitting, construction, delivery, and installation of new hydrogen conexes at NWS sites in Annette, Yakutat, St. Paul, King Salmon, Kotzebue, Nome, and Fairbanks Alaska. The work also includes a generic hydrogen system design. Successful offeror shall show demonstrated and documented success in the performance of this type of work in Alaska.
1.0 BACKGROUND
The National Weather Service operates automated weather balloon launching systems at various sites in Alaska. This Statement of Work is for the permitting, construction, delivery, and installation of new conexes used for housing the hydrogen generators required to operate the sites. The work also includes a generic hydrogen system design. This contract has a total period of performance of 180 calendar days. The total period of performance includes the permitting, construction, delivery, and installation of conexes at sites located in Annette, Yakutat, St. Paul, King Salmon, Kotzebue, Nome, and Fairbanks Alaska as well as the generic hydrogen system design.
2.0 SERVICES REQUIRED
The successful offeror shall furnish personnel (and provide proof of current certification and or licensing by the United States Government (USG) and/or State of Alaska (SoA) as appropriate, i.e. 30 hour OSHA Construction Safety Officer, SoA Licensed Electricians, SoA Licensed Mechanical Engineer, etc.), material, equipment, services and facilities to perform this Statement of Work. The scope of services required by the USG includes:
2.1 Permitting. Based on the provided design drawings, Government provided Alaska State Fire Marshal certificates and permits, provided site photos, information within this SOW, and discussions with the NWS, secure current site permits and certificates from the Alaska State Fire Marshal no later than (NLT) 30 days after Notice to Proceed (NTP), on behalf of the the NWS, for all of the following sites:
2.1.1 Annette
2.1.2 Yakutat
2.1.3 St Paul
2.1.4 King Salmon
2.1.5 Kotzebue
2.1.6 Nome
2.1.7 Fairbanks
2.2 Construction (Seven options consisting of four tasks, each option to be bid separately)
2.2.1 Task One - Construct the conexes in accordance with the design drawings provided by the NWS and provide daily documentation of the construction progress (photos and notes).
2.2.2 Task Two - Paint exterior and interior of conex in accordance with provided NOAA color scheme that will accommodate the 20 year design life of the conex.
2.2.3 Task Three - Provide and install vinyl composition tile (VCT) flooring that will accommodate the 20 year design life of the conex.
2.2.4 Task Four - Complete conex construction in order to meet the delivery schedule detailed in paragraph 2.3.
2.2.5 Seven conexes each of which will be constructed to the most conservative (insulation) requirements per the drawings and each of which are to be separately bid as an option.
2.2.5.1 Annette, no later than (NLT) 30 days post NTP
2.2.5.2 Yakutat, NLT 45 days post NTP
2.2.5.3 St Paul, NLT 60 days post NTP
2.2.5.4 King Salmon, NLT 75 days post NTP
2.2.5.5 Kotzebue, NLT 90 days post NTP
2.2.5.6 Nome, NLT 105 days post NTP
2.2.5.7 Fairbanks, NLT 120 days post NTP
2.3 Delivery (Seven sites each of which to be separately bid as an option).
2.3.1 Deliver completed conex to NWS site in Annette Alaska NLT 30 days post NTP
2.3.2 Deliver completed conex to NWS site in Yakutat Alaska NLT 45 days post NTP
2.3.3 Deliver completed conex to NWS site in St Paul Alaska NLT 60 days post NTP
2.3.4 Deliver completed conex to NWS site in King Salmon Alaska 75 days post NTP
2.3.5 Deliver completed conex to NWS site Kotzebue Alaska NLT 90 days post NTP
2.3.6 Deliver completed conex to NWS site in Nome Alaska NLT 105 days post NTP
2.3.7 Deliver completed conex to NWS site in Fairbanks Alaska NLT 120 days post NTP
2.4 Installation (Seven options consisting of two tasks, each option to be bid separately).
2.4.1 Task 1 - Safely crane the conex onto an existing steel platform that is elevated 3 feet above grade and behind a 6 foot high chain link fence without damaging the site or the conex. Provide locking mechanisms (twistlocks) as required and secure conexes to the frame at each site using the locking mechanisms (twistlocks).
2.4.2 Task 2 - Provide labor and materials to permanently electrically connect the conex to the existing site utilities IAW the latest edition of the NEC.
2.4.3 Seven installation sites each of which to be separately bid as an option:
2.4.3.1 Annette, NLT 30 days post NTP
2.4.3.2 Yakutat, NLT 45 days post NTP
2.4.3.3 St Paul, NLT 60 days post NTP
2.4.3.4 King Salmon, NLT 75 days post NTP
2.4.3.5 Kotzebue, NLT 90 days post NTP
2.4.3.6 Nome, NLT 105 days post NTP
2.4.3.7 Fairbanks, NLT 120 days post NTP
2.5 Generic Hydrogen Design (to be bid separately as an option)
2.5.1 Task 1 - Provide signed & sealed drawings and accompanying signed & sealed calculations, by a mechanical engineer currently licensed by the State of Alaska, for a generic hydrogen system to be located and operated within conexes permitted, constructed, delivered, and placed as part of this scope of work NLT 30 days post NTP.
2.5.2 Task 2 - Utilize government furnished drawings, specifications, materials lists, and a pressure safety data package to develop the drawings and calculations detailed in task 1.
2.5.3 Task 3 - Ensure that the design meets all current State and Federal hydrogen requirements and gain a permit for the design from the Alaska State Fire Marshal NLT 30 days after the notice to proceed.
2.5.4 Task - Provide signed & sealed as-built drawings based upon government furnished QA/QC reports NLT 120 days post NTP.
3.0 DETAILED SCOPE OF SERVICES
The offeror shall comply with the following requirements:
3.1 Task 1 – Kickoff Meeting
A meeting, herein referred to as the Kickoff Meeting, shall be held within three (3) calendar days (cd) after notification by the Contracting Officer (CO) of the Notice to Proceed (NTP). The Kickoff Meeting will be conducted by the Contracting Officer’s Representative (COR) to discuss the scope of the contract. The offeror shall present an overall project schedule, work breakdown structure, schedule of values (using master specification construction format), shipping schedule, and site specific safety plan for the project for the USG’s review and concurrence. The offeror shall identify issues requiring direction from the Government, and prepare Kickoff Meeting minutes in their own format to include participants, general discussion, decisions and action items. Any special requirements discussed and agreed upon shall be noted. The Kickoff meeting is expected to last approximately 1 hour, and may be via teleconference.
3.2 Task 2 – Secure Fire Marshal Permits by NLT 30 days post NTP The offeror shall secure current permits from the Alaska State Fire Marshal for all sitesNLT 30 days post NTP using provided design drawings, provided Fire Marshal Certificates, provided site photos, information within this SOW, and discussions with the NWS. Offeror shall meet requirements detailed in paragraph 2.1 and associated subparagraphs. Daily liquidated damages will be assessed in the amount of $3,000 per day in the event that the schedule for this task is not met.
3.3 Task 3 – Construct Conexes per the required schedule (Seven conexes each of which to be separately bid as an option) The offeror through its construction representative shall be responsible for the build of the conexes. The offeror through its construction representative shall be responsible for all engineering during build. The offeror shall be responsible to answer any questions and resolve issues that arise during build. The offeror shall be responsible to maintain a log of all issues on an Requests for Information (RFI) log.
The offeror shall provide all labor, materials, and equipment required to prepare and build the conexes for this project. The offeror shall execute the work in a clean and professional manner and keep the Government informed of their progress on, at least, a weekly basis through the use of daily reports, weekly teleconferences, two week look-ahead project schedules, submittals (daily construction photographs, specifications, cut-sheets, etc.), monthly project schedule updates, monthly schedule of value (definable features of work broken out using Construction Specifications Industry Master Format) updates, and monthly pay requests. The offeror shall comply with all local, state and federal codes and requirements in the execution of this work. Offeror shall meet the schedule and requirements detailed in paragraph 2.2 and associated subparagraphs. Daily liquidated damages will be assessed in the amount of $3,000 per day in the event that the schedule for this task is not met. The Government may elect to not exercise all options.
3.4 Task 4 - Deliver Conexes per the required schedule (Seven conexes each of which to be separately bid as an option) The offeror shall be responsible for meeting or exceeding the schedule and requirements detailed in paragraph 2.3 and associated subparagraphs. Daily liquidated damages will be assessed in the amount of $3,000 per day in the event that the schedule for this task is not met. The Government may elect to not exercise all options.
3.5 Task 5 - Install Conexes per the required schedule (Seven conexes each of which to be separately bid as an option) The offeror shall be responsible for meeting or exceeding the schedule and requirements detailed in paragraphs 2.3 and 2.4 and associated subparagraphs. Daily liquidated damages will be assessed in the amount of $3,000 per day in the event that the schedule for this task is not met. The Government may elect to not exercise all options. The Government may elect to not exercise all tasks (i.e. Task 1 and/or Task 2).
3.6 Task 6 - Generic Hydrogen System Design per the required schedule (bid as option) The offeror shall be responsible for meeting or exceeding the schedule and requirements detailed in paragraph 2.5 and associated subparagraphs. Daily liquidated damages will be assessed in the amount of $3,000 per day in the event that the schedule for this task is not met. The Government may elect to not exercise all options.
4.0 DELIVERABLES, CONFERENCES, MEETINGS
4.1 Meeting Minutes
Meeting minutes shall be provided by the offeror summarizing discussions and decisions made during conference calls and other meetings. The minutes may be provided via attachment to an email.
4.2 Completion of Submittals
The offeror shall be responsible for sending permits, daily/weekly project photos, project notes, equipment submittals, product literature, warranty information, and shop drawings to the COR via attachment to emails to expedite delivery of this project. Product submittals are expected to be minimal for this work.
At final submission, all warranties shall be executed to the benefit of the Government.
File details come from the government source that posted it. Updated .