Wastewater Treatment Plant PMS Solicitation No 19Z11526Q0003.pdf

PDF 1008 KB Posted

Attached to
Wastewater Treatment Plant Preventive Maintenance Services for U. S. Embassy in Harare, Zimbabwe
Solicitation number
19Z11526Q0003
Issued by

About this file

This is a Request for Quote (RFQ) for Preventive Maintenance Services for the Wastewater Treatment Plant at the U.S. Embassy in Harare, Zimbabwe. The solicitation seeks a contractor to provide comprehensive preventive maintenance services for the facility's wastewater collection and treatment systems, including sanitary sewer manholes, storm water drains, and a wastewater treatment plant. The contract will be firm-fixed price for a one-year base period with three one-year option periods, expected to commence by March 30, 2026.

Key requirements include quarterly 2-day site visits, monthly testing and monitoring of system parameters, chemical treatment, equipment maintenance, and reporting. The contractor must maintain dissolved oxygen levels, chlorine contact time, and other specified performance metrics. The equipment includes multiple blowers, pumps, motors, and aeration systems with various capacities. Pricing will be determined on a per-service basis, with separate line items for preventive maintenance work and technical analysis. The solicitation emphasizes safety, compliance with industry standards, and quality assurance, with performance evaluated based on minimal customer complaints and adherence to specified operational parameters.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Wastewater Treatment Plant PMS: Solicitation # 19Z11526Q0003

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30

1. REQUISITION NUMBER

PR15285214

2. CONTRACT NO.

3. AWARD/EFFECTIVE

DATE

4. ORDER NUMBER

5. SOLICITATION NUMBER

19Z11526Q0003

6. SOLICITATION ISSUE DATE

October 22, 2025

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME

HarareGSOProcurement@state.gov

POC: Damian Richard

b. TELEPHONE NUMBER (No collect calls)

+2638677011000

8. OFFER DUE DATE/ LOCAL

TIME

Nov 10, 2025 at 5pm

9. ISSUED BY CODE 10. THIS ACQUISITION IS UNRESTRICTED OR SET ASIDE: ____ % FOR:

United States Embassy Harare

SMALL BUSINESS WOMEN-OWNED SMALL BUSINESS

2 Lorraine Drive, Bluffhill

Harare, Zimbabwe

HUBZONE SMALL

BUSINESS

(WOSB) ELLIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM NAICS:

SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

EDWOSB

8 (A) SIZE STANDARD:

11. DELIVERY FOR FOB DESTINAT-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

12. DISCOUNT TERMS 13a. THIS CONTRACT IS A

RATED ORDER UNDER

DPAS (15 CFR 700)

13b. RATING

14. METHOD OF SOLICITATION

RFQ IFB RFP

15. DELIVER TO CODE 16. ADMINISTERED BY CODE

United States Embassy, Harare

2 Lorraine Drive, Bluffhill

Harare, Zimbabwe

United States Embassy, Harare

2 Lorraine Drive, Bluffhill

Harare, Zimbabwe

17a. CONTRACTOR/

OFFERER

TELEPHONE NO.

CODE FACILITY

CODE

18a. PAYMENT WILL BE MADE BY

United States Embassy, Harare

2 Lorraine Drive, Bluffhill Harare, Zimbabwe HarareFMOInvoices@state.gov

CODE

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN

OFFER

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK

BELOW IS CHECKED SEE ADDENDUM

19.

ITEM NO.

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

AMOUNT

Solicitation for Preventive Maintenance Service for Wastewater Treatment Plants as detailed in the SOW on pages 10-25 of the Solicitation

(Use Reverse and/or Attach Additional Sheets as Necessary)

25. ACCOUNTING AND APPROPRIATION DATA

26. TOTAL AWARD AMOUNT (For Govt. Use Only)

27a.SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA ARE ARE NOT ATTACHED

27b.CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN __ONE__

COPY TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER ALL

ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY ADDITIONAL

SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED HEREIN.

29. AWARD OF CONTRACT: REF. _________________ OFFER DATED

____________. YOUR OFFER ON SOLICITATION (BLOCK 5), INCLUDING ANY

ADDITIONS OR CHANGES WHICH ARE SET FORTH HEREIN, IS ACCEPTED AS TO

ITEMS:

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)

30b. NAME AND TITLE OF SIGNER (Type or print)

30c. DATE SIGNED

31b. NAME OF CONTRACTING OFFICER (Type or print)

Damian Richard

31c. DATE SIGNED mailto:HarareGSOProcurement@state.gov mailto:HarareFMOInvoices@state.gov

19.

ITEM NO.

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

AMOUNT

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: _______________________________

32b. SIGNATURE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f. TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

33. SHIP NUMBER 34. VOUCHER NUMBER 35. AMOUNT VERIFIED

CORRECT FOR

36. PAYMENT 37. CHECK NUMBER

PARTIAL FINAL

COMPLETE PARTIAL FINAL

38. S/R ACCOUNT NO.

39. S/R VOUCHER NO. 40. PAID BY

41.a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT 42a. RECEIVED BY (Print)

41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER

41C. DATE

42b. RECEIVED AT (Location)

42c. DATE REC’D (YY/MM/DD) 42d. TOTAL CONTAINERS

TABLE OF CONTENTS

SECTION 1 - THE SCHEDULE

• SF 1449 cover sheet

• Continuation To SF-1449, RFQ Number 19Z11526Q0003, Prices, Block 23

• Continuation To SF-1449, RFQ Number 19Z11526Q0003, Schedule Of

Supplies/Services, Block 20 Description/Specifications/Work Statement

• Attachment 1 Access Clearance Form.

SECTION 2 - CONTRACT CLAUSES

• Contract Clauses

• Addendum to Contract Clauses - FAR and DOSAR Clauses not Prescribed in Part 12

SECTION 3 - SOLICITATION PROVISIONS

• Solicitation Provisions

• Addendum to Solicitation Provisions - FAR and DOSAR Provisions not Prescribed in

Part 12

SECTION 4 - EVALUATION FACTORS

• Evaluation Factors

• Addendum to Evaluation Factors - FAR and DOSAR Provisions not Prescribed in Part

SECTION 5 - REPRESENTATIONS AND CERTIFICATIONS

• Offeror Representations and Certifications

• Addendum to Offeror Representations and Certifications - FAR and DOSAR Provisions not Prescribed in Part 12

SECTION 1 - THE SCHEDULE

CONTINUATION TO SF-1449

RFQ NUMBER 19Z11526Q0003

PRICES, BLOCK 23

I. PERFORMANCE WORK STATEMENT (see detailed PWS from page 10 to 13)

A. The purpose of this firm-fixed price purchase order is to provide the preventive maintenance services of Wastewater Treatment Plant in accordance with the Work Statement.

B. The contract will be for a one-year period from the date of the contract award, with 3 one-year options and will be expected to commence no later than 03/30/2026.

QUALITY ASSURANCE AND SURVEILLANCE PLAN (QASP)

This plan provides an effective method to promote satisfactory contractor performance. The QASP provides a method for the Contracting Officer's Representative (COR) to monitor Contractor performance, advise the Contractor of unsatisfactory performance, and notify the Contracting

Officer of continued unsatisfactory performance. The Contractor, not the Government, is responsible for management and quality control to meet the terms of the contract. The role of the

Government is to monitor quality to ensure that contract standards are achieved.

Performance Objective Scope of Work

Paragraphs

Performance Threshold

Services.

Performs all preventive maintenance services of Wastewater Treatment

Plant services set forth in the scope of work.

Page 10 thru 25

All required services are performed and no more than one customer complaint is received per month.

1. SURVEILLANCE. The COR will receive and document all complaints from Government personnel regarding the services provided. If appropriate, the COR will send the complaints to the

Contractor for corrective action.

2. STANDARD. The performance standard is that the Government receives no more than one customer complaint per month. The COR shall notify the Contracting Officer of the complaints so that the Contracting Officer may take appropriate action to enforce the inspection clause (FAR

52.212.4, Contract Terms and Conditions - Commercial Products and Commercial Services (NOV

2023), if any of the services exceed the standard.

3. PROCEDURES.

(a) If any Government personnel observe unacceptable services, either incomplete work or required services not being performed they should immediately contact the COR.

(b) The COR will complete appropriate documentation to record the complaint. (c)

If the COR determines the complaint is invalid, the COR will advise the complainant. The

COR will retain the annotated copy of the written complaint for his/her files.

https://www.acquisition.gov/far/52.212-4 https://www.acquisition.gov/far/52.212-4

(d) If the COR determines the complaint is valid, the COR will inform the

Contractor and give the Contractor additional time to correct the defect, if additional time is available. The COR shall determine how much time is reasonable.

(e) The COR shall, as a minimum, orally notify the Contractor of any valid complaints.

(f) If the Contractor disagrees with the complaint after investigation of the site and challenges the validity of the complaint, the Contractor will notify the COR. The COR will review the matter to determine the validity of the complaint.

(g) The COR will consider complaints as resolved unless notified otherwise by the complainant.

(h) Repeat customer complaints are not permitted for any services. If a repeat customer complaint is received for the same deficiency during the service period, the COR will contact the Contracting Officer for appropriate action under the Inspection clause.

MINIMUM AND MAXIMUM AMOUNTS

During this contract period, the Government shall place orders totaling a minimum of one service per year. This reflects the contract minimum for this period of performance. The amount of all orders shall not exceed 1 service. This reflects the contract maximum for this period of performance.

II. PRICING

Price shall be in United States dollars. The rates below include all costs associated with providing preventive maintenance services in accordance with the attached scope of work, and the manufacturer’s warranty including materials, labor, insurance, overhead, profit and GST (if applicable).

Advance payments are not authorized under this contract. Instead, the Embassy shall issue Task

Orders for the execution of works. Payment shall be made 30 days after the Contracting Officer

Representative (COR) has confirmed that services were rendered in a satisfactory manner

1. Base Year. The Contractor shall provide the services shown below for the base period of the contract and continuing for a period of 12 months.

CLIN Description Quantity of

Equipment

Type of services

No. of service

Unit price

/ service ($)

Total per year ($)

001 Waste Water Treatment

Plant

1 PM work 1

Operator training, plant testing, technical analysis and development of technical reports

Technic al analysis

Total Base Year

2. Option Year 1. The Contractor shall provide the services shown below for Option Year 1 of the contract and continuing for a period of 12 months.

CLIN Description Quantity of

Equipment

Type of services

No. of service

Unit price

/ service ($)

Total per year ($)

101 Waste Water Treatment testing, technical analysis and development of technical reports al analysis

Total Option Year 1

3. Option Year 2. The Contractor shall provide the services shown below for Option Year 2 of the contract and continuing for a period of 12 months

CLIN Description Quantity of

Equipment

Type of services

No. of service

Unit price

/ service ($)

Total per year ($)

201 Waste Water Treatment testing, technical analysis and development of technical reports al analysis

Total Option Year 2

4. Option Year 3. The Contractor shall provide the services shown below for Option Year 3 of the contract and continuing for a period of 12 months

CLIN Description Quantity of

Equipment

Type of services

No. of service

Unit price

/ service ($)

Total per year ($)

301 Waste Water Treatment testing, technical analysis al analysis

Total Option Year 3

5. Option Year 4. The Contractor shall provide the services shown below for Option Year 4 of the contract and continuing for a period of 12 months

CLIN Description Quantity of

Equipment

Type of services

No. of service

Unit price

/ service ($)

Total per year ($)

401 Waste Water Treatment testing, technical analysis al analysis

Total Option Year 4

6. GRAND TOTAL

Base Year

Option Year 1

Option Year 2

Option Year 3

Option Year 4

Grand Total

7. Repair option. Repairs are NOT included under this agreement and are to be done outside this contract. However, we would like to have current labor rates in the event that there is an issue discovered during the preventive maintenance of the specified equipment. Please provide your current labor rates in the Repair Option fields below. Any necessary repairs or parts will be submitted for approval and then billed against a separate purchase order (PO).

The Contractor is not approved to do any additional work without approval.

Repair Labor Rates

Base Year $ /hr.

Option Year 1 $ /hr.

Option Year 2 $ /hr

Option Year 3 $ /hr

Option Year 4 $ /hr

8. Emergency Service Option. Emergency Service is NOT included under this agreement and will be billed outside this contract. However, we would like to have the rates in the event of an emergency. Emergency Service, with a four-hour response time, must be available 24-hours per day, 365 days a year. Submit cost for Emergency Services below.

9. Please indicate how the emergency service will be billed (hourly, trip charge, etc.)

Emergency Service Rates

Base Year $

Option Year 1 $

Option Year 2 $

Option Year 3 $

Option Year 4 $

III. VALUE ADDED TAX

VALUE ADDED TAX. Value Added Tax (VAT) is not included in the CLIN rates. Instead, it will be priced as a separate Line Item in the contract and on Invoices. Local law dictates the portion of the contract price that is subject to VAT; this percentage is multiplied only against that portion. It is reflected for each performance period.

CONTINUATION TO SF-1449,

RFQ NUMBER 19Z11526Q0003

SCHEDULE OF SUPPLIES/SERVICES, BLOCK 20

DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

1. GENERAL INFORMATION

The United States Embassy i n Harare requires professional services and contractor cost proposals to perform preventive maintenance services of the facility’s Waste

Water Collection and Treatment System.

I. PROJECT REQUIREMENTS:

1. The sanitary sewer collection system includes the following

• The Sanitary Sewer and Storm Water Drains below;

SS stands for sanitary sewer which represents the manholes.

SD stands for storm drain.

SS10: Located south=-east of SCap entrance gate.

SS9: Located between Warehouse and SPX.

SS8: Located by the entrance of Garden supply shop in SPX.

SS7 & SS11: Located south of vehicle maintenance bay.

SS6: Located south of SPX & north of MSGR.

SS5: Located between NOB west and SPX.

SS4: Located West of NOB west on the driveway next to Chancery entrance/exit sign post.

SS3: Located by the south-western end corner of NOB west building.

SS2: Located by the Mcap inner gate.

SD: There are 39 Storm Water Drains

1.1 The wastewater treatment and collection systems to be maintained are as follows:

• Sanitary Sewer Collection System

• Waste Water Treatment Plant

1.2 The Overseas Buildings Operations (OBO) has a requirement to obtain wastewater treatment plant maintenance services to execute this work, including logistics, customs, shipping, transportation, labor, wastewater treatment chemicals, tools, wastewater treatment testing kits/equipment, administrative and all associated management support functions. The wastewater treatment service contract includes but is not limited to combinations of physical methods, chemical methods, equipment servicing and testing to control wastewater-related issues such as flow control, blower maintenance & operation, air diffuser operation and adjustment, activated sludge aeration (Dissolved Oxygen), clarifier cleaning and operation, weir cleaning and adjustment, air-lift pumps operation and adjustment, filtration cleaning and operation (if applicable), disinfection control, effluent testing and adjustment. All work shall comply with the requirements described in the following, as a minimum:

• AWWA Standards (American Water Works Association)

• ANSI Standards

• SDS Regulations

• ASTM D NFPA Codes UL Standards IEEE Standards

• NEMA Standards

• OSHA Standards

• And all applicable manufacturer O&M and installation instructions/requirements.

2. OBJECTIVES

2.1 The purpose of this scope of work is to define the requirements for the preventive maintenance of the wastewater collection and treatment systems located at the US Embassy

Compound. All work shall be executed in accordance with this SOW, approved wastewater treatment plant practices and shall be compliant with all applicable local and federal safety, equipment and building codes and standards. The intent of this service contract is as follows:

Sanitary Sewer Collection System: to optimize the performance of the collection system, and reduce (or eliminate) the frequency of overflows, basement back-ups, sewer pipe failures, lift station failures and peak flows.

Wastewater Treatment Plant: to adjust the wastewater treatment plant based on plant operating parameters, descale and adjust plant operations, prevent/monitor/ plant corrosion, verify local operating procedures within the manufacture’s guidelines, and familiarize operators on wastewater treatment plant operations and regulations.

3. GENERAL REQUIREMENTS

3.1 This statement of work (SOW) describes the preventive maintenance and testing services and deliverables to be performed by the contractor at the NEC Compound, U.S.

Embassy Harare, Zimbabwe.

3.2 The assigned Contracting Officer and Contracting Officer's Representative are the sole points of contact for all technical and contractual discussions or issues regarding the scope of work and its intent and execution. The contractor shall take no direction verbal or otherwise from personnel other than the Contracting Officer or Contract Officer's Representative.

3.3 This Statement of Work requires the Contractor to provide site assessment and survey services, project management, professional wastewater treatment services, wastewater treatment logistics and material procurement services, preventive maintenance and testing services, cost estimating and scheduling services, and general support services for this wastewater treatment maintenance contract.

3.4 The contractor’s proposed and U. S. Government (USG) accepted maintenance contract cost proposal and maintenance schedule, including completion dates shall be incorporated into the task order. Additionally, the task order shall be a firm fixed price task order.

3.5 This statement of work and applicable deliverables and documents developed by the contractor and accepted by the USG shall serve as the basis for describing and delineating the scope of the required services and work limits for service contract to be furnished and executed by the contractor.

3.6 All deliverables, documents, proposals, etc. submitted by the contractor under this statement of work shall remain the property of the USG. All USG documents and data provided to the contractor shall remain the property of the USG. The contractor shall limit duplication and dissemination of all USG documents and contractor developed documents under this statement of work to/within the contractor’s execution team. Duplication or distribution of project documents outside the contractor’s team is strictly prohibited without the express written approval and authorization of the Contracting Officer. Upon completion of each service visit all documents, electronic media, photos, etc. shall be submitted to the USG, including all documents and data that the USG provided to the contractor. All service contract documents and media shall be submitted to the USG along with the contractor’s service report.

3.7 The Contractor shall schedule, coordinate and arrange all work so as to cause the least interference with the normal occurrence of post operations. In those cases where some interference is unavoidable, the Contractor shall make every effort to minimize the impact of the interference and its effects on the occupants or users. All detailed work schedules required by this statement of work shall be electronically documented and updated and made available to the

Contracting Officer's Representative (COR) upon request, oral or written. If the COR determines that the Contractor’s schedule conflicts with critical post operations, the Contractor shall modify the schedule as required.

3.8 The contractor shall ensure that all Embassy/Post facilities, equipment and systems recommended for and maintained or installed by the contractor are done so with the highest quality and cost effective materials, finishes, fixtures, equipment and system that provide for sustained operational reliability, dependability and durability. The contractor shall assure that any equipment/wastewater treatment chemicals furnished and installed are maintainable and equipment/parts can be readily replaced with locally available supplies and services, as practical taking into consideration local economy and resources. The contractor shall utilize reliability-centered maintenance (RCM) principles and methodologies during and for all project activities and tasks. Uniformity of parts and components shall be taken into consideration to maximize part interchangeability with other existing Post systems. Except as otherwise directed by the contracting officer all parts, materials, components, equipment, systems, etc. furnished by the contractor shall be new – not used or manufactured by third party entities. Except as otherwise directed by the contracting officer, all replacement or warranty parts shall be new and equal to or better than manufacturer recommended replacements.

3.9 After review of the USG Statement of Work and provided technical data by the contractor, any discrepancies, errors, conflicts, etc. that are discovered by the contractor, the contractor shall forward those items to the CO via written correspondence. Submittal of this written correspondence shall be completed, within 3 days upon receipt of the US Government Statement of Work.

3.9.1 The contractor shall provide 3 customer references of similar scope of work and its US dollar value.

3.9.2 The Contractor will not use any method or substances that may cause damage to the equipment or systems. Any damage or loss through negligence and/or maintenance practices by the

Contractor, sub-contractor, or Contractor's staff shall be the whole responsibility of the

Contractor. The U.S. Embassy, Harare, Zimbabwe will require the Contractor to repair/replace any damaged systems or pay for the cost of rectification.

3.9.3 The Contractor must, for the duration of the contracted Services, continue to maintain a quality control process that has been agreed to by the U.S. Embassy, Harare, Zimbabwe COR and the Contractor.

3.9.4 The Contractor shall provide the technician’s resume and training documentations within twenty (20) calendar days of the notice to proceed.

3.10 No work on any portion of the collection system or the wastewater treatment plant shall be permitted on the last regular work day of the week. All work under this contract must be scheduled to assure that the day following the work is a normal working day for the US

Embassy. Further, the contractor must certify availability to return immediately to the US

Embassy compound to correct any operating issues that may arise following contractor work.

4. CONTRACTING OFFICER REPRESENTIVE and POST CONTROL OFFICER

4.1 All technical questions concerning the scope and requirements of the U.S. Embassy, Harare, Zimbabwe wastewater treatment service contract shall be directed to the Contracting

Officer’s Representative (COR):

COR

Farai Gutu - Supervisory Mechanical Engineer

4.2 The Post Control Officer (PCO) will be the contractor’s point of contact at the U.S.

Embassy, Harare, Zimbabwe. All questions concerning coordination of w a s t e w a t e r treatment service activities while at post shall be directed to the Post Control Officer, with weekly reporting to the COR:

5. PERFORMANCE CRITERIA

5.1 Performance Objective

The objective of this Agreement is to provide, within the Term of this Contract, a professional level of service, which provides:

• US Embassy satisfaction in respect to the maintenance of wastewater collection and treatment system; prompt reaction to any change in arrangements or operational requirements of the US Embassy;

• compliance with the statutory and regulatory provisions of the laws of the jurisdiction;

• best in class practices within the industry;

• risk reduction for the US Embassy;

• preservation of asset value; and

• reduction in operating costs.

The Contractor agrees that its performance under the Contract shall be measured against performance criteria specified in this document or otherwise agreed at the time of commencement.

5.2 Performance Benchmarks

The Contractor must for the duration of the contracted Services continue to maintain a quality control process, which has been agreed by the US Embassy and the Contractor.

The Contractor must allow the US Embassy access to the quality control system as well as the relevant quality systems of its subcontractors to enable monitoring and quality auditing of the maintenance service.

The US Embassy may reject any aspect of the Services that fails to comply with the requirements of the Contract, or its quality system, at any time.

5.3 Performance Monitoring and Reporting

The Contractor shall monitor its own performance against the criteria and benchmarks identified in this document and shall provide reports when reasonably required by the US

Embassy.

6. WASTEWATER TREATMENT AND COLLECTION SYSTEM SPECIFICATIONS

6.1 All equipment, chemicals, and testing procedures and kits shall be approved by the COR prior to use in the service contract.

6.2 The contractor will be responsible for submitting the manufacture specifications; MSDS sheets and equipment cut sheets for all equipment, chemicals (including chemical composition), and testing procedures in both English and Shona languages.

6.3 The Contractor shall test the wastewater treatment system for proper operating conditions through field-testing and shall adjust the plant to bring it into compliance with the required operating parameters as specified in Exhibit A Statement of Work

6.4 The Contractor will be responsible for the sewer collection system cleaning, inspection and maintenance as specified in Exhibit A Statement of Work.

7. SAFETY HEALTH AND ENVIROMENTAL MANAGEMENT (SHEM)

7.1 The Contractor shall take all reasonable and proper safety precautions to prevent death or injury to any person or damage to any property at the US Embassy NEC Compound and in particular all equipment used by the Contractor shall be used in such a manner and maintained so as to minimize the danger of accident, death, injury, loss or damage arising from the use of such equipment. In addition to relevant statutory requirements, standards and other provisions of this Contract, the Contractor shall have the following requirements:

7.1.1 The Contractor’s personnel shall be knowledgeable with and adhere to all relevant occupational health and safety rules, regulations, standards, and SDS sheets.

7.1.2 All electrical equipment and associated materials for the Services Contract comply with

UL requirements.

7.1.3 Follow all NFPA guidelines against fire, production of smoke or the venting of any noxious substances

7.1.4 Ensure that the Contractor’s personnel comply with all safety procedures and requirements

7.1.5 Ensure that the Contractor’s personnel are adequately trained and instructed in the safe and correct usage, handling and operation of materials and equipment relevant to the Services and provide reasonable proof of such to the US Embassy Harare on request.

7.1.6 Ensure the Contractor’s personnel are certified as having completed occupational health and safety training and have been issued all the necessary Personal Protection Equipment (PPE) required for safe implementation of this contract;

7.1.7 Training program(s) shall be presented and must satisfy the US Embassy Harare during the submittal process.

8. MAINTENANCE SPECIFICATION DETAILS

8.1 Precedence of Specifications. If and to the extent that there is an inconsistency between this maintenance specification and any Manufacture’s maintenance specification, the Manufacture’s maintenance specification shall prevail.

8.2 Hours of Work. The Contractor shall schedule all preventive maintenance during normal working hour which are defined as 0730-1700 hrs (Monday to Thursday) and 0730-1230 (Friday), inclusive of periodic maintenance that may be required on Saturdays, with the exception of any regular or special public holidays on which the US Embassy Compound is not open, or as agreed with the US Embassy prior to commencement of the contract.

9. SCOPE OF WORK

9.1 The Contractor shall provide both the required maintenance parts (air/oil filters, belts, chart paper, etc.) and necessary products and services to perform the required system maintenance, and report the results. The wastewater collection and treatment system service contract shall clean and preserve the collection system, wastewater treatment plant, and plant discharge effluent conveyance system. The contract shall also establish a cost effective wastewater treatment program to meet all effluent discharge goals with cost-effective, safe, and environmentally acceptable processes.

9.2 The sanitary sewer collection and wastewater treatment maintenance contractor shall provide a “support service wastewater collection and treatment” contract. The support service wastewater treatment contract shall involve joint responsibilities between the US

Embassy Facility Management staff and the wastewater system collection and treatment

Contractor.

9.3 The Service program shall consist of the US Embassy Facility Management staff conducting routine (daily/weekly) operator testing of the wastewater collection and treatment systems and monthly e-mailing the results to the wastewater treatment contractor, with copy to

OBO/FAC (water_testing_group@state.gov). The contractor will then be responsible for conducting a technical analysis of the routine wastewater treatment testing results from the embassy. The contractor will then respond to the embassy within 24 hours to direct the embassy facility management staff to make any changes to the collection system and/or treatment plant operations to reestablish effective and efficient wastewater treatment to meet discharge standards.

9.4 The Contractor shall visit the US Embassy quarterly (4 times a year – every 3 months) for

2-day consecutive intervals (agreed to between the COR, Facility Manager, and the Contractor).

The contractor shall be responsible for all logistics including but not limited to transportation and hotel reservations for their staff.

9.5 The Contractor shall provide documented chemicals that have a storage life expectance of at least 1 year.

9.6 The Contractor shall determine the dosage levels of chemicals and stay within the operating parameters specified under Exhibit A Statement of Work.

9.7 The Contractor shall p r o v i d e 48 hours of instruction annually in English to familiarize operators in necessary water treatment tests, the control ranges for each treatment chemical, safe handling of equipment and chemicals, and new water treatment procedures/technologies.

9.8 During each site visit to the plant, the Contractor shall review the plant operator daily operating logs to verify safe and effective operation of the plant. The Contractor will highlight all areas where plant-operating conditions are outside of acceptable operating range and shall provide instruction on how to correct the deficiency.

9.9 The Contractor shall review the routine wastewater treatment testing results from the US

Embassy monthly and respond to the facility management staff at the US Embassy within 24 hours if changes to the collection system and/or treatment plant operations are recommended to reestablish effective and efficient wastewater treatment to meet discharge standards. This contract shall also discuss the wastewater treatment plant conditions and the water quality of the effluent with the COR, Facility Manager and operating engineers and follow up with a written service report within ten (10) business days after each visit. The report shall be in

English and contain the results of wastewater treatment contractor’s on-site tests, comments on the status of each system, and specific recommendations for action if necessary.

9.10.1 The Contractor shall perform the required services as described in Exhibit A – Wastewater

Collection and Treatment System.

10 ACCESS TO GOVERNMENT BUILDINGS AND STANDARDS OF CONDUCT

10.10 The Contractor shall designate a representative who shall supervise the Contractor’s technicians and be the Contractor's liaison with the U.S. Embassy Harare. The Contractor's employees shall be on-site only for contractual duties and not for any other business or purposes.

Contractor employees shall have access to the systems dedicated rooms with or without security escorts, only with specific permission by the Facility Manager, Contracting Officer, or the COR.

10.11 Personnel Security: The US Embassy reserves the right to deny access to U.S owned and U.S.-operated facilities to any individual. The Contractor shall provide the names, biographic data and police clearance on all Contractor personnel, who shall be used on this contract prior to their utilization on this contract.

10.12 Standards of Conduct.

10.12.1General: The Contractor shall maintain satisfactory standards of employee competency, conduct, cleanliness, appearance, and integrity and shall be responsible for taking such disciplinary action with respect to employees as necessary. Each Contractor employee shall adhere to standards of conduct that reflect credit on themselves, their employer, and the

United States Government. The US Embassy reserves the right to direct the Contractor to remove an employee from the worksite for failure to comply with the standards of conduct.

The Contractor shall immediately replace such an employee to maintain continuity of services at no additional cost to the Government.

10.12.2 Uniforms and Personal Equipment. The Contractor's employees shall wear clean, neat and complete uniforms when on duty. The Contractor shall provide, to each employee and supervisor, uniforms and personal equipment. The Contractor shall be responsible for the cost of purchasing, cleaning, pressing, and repair of the uniforms.

10.12.3 Neglect of Duties. Neglect of duties shall not be condoned. This includes sleeping the integrity unreasonable delays or failures to carry out assigned tasks, conducting personal affairs during duty hours and refusing to render assistance or cooperate in upholding the integrity of the worksite security.

10.12.4 Intoxicants and Narcotics. The Contractor shall not allow its employees while on duty to possess, sell, consume, or be under the influence of intoxicants, drugs or substances which produce similar effects.

11 The wastewater treatment equipment details and plant elements are as follows:

1 Mfr. Make Model Specifications S/No. P/N Capacity Quantity

Equalisation Chamber gallons

Blower Howden 33 U-RAI 1605933001 6510502L 1

Pump 1 Goulds WS0529BF 1/2HP, 220V,3 phase,50Hz, 1450RPM, 7.8Amps

CEL4M15 1

Pump 2 Goulds WS0529BF 1/2HP, 220V,3 phase, 50 Hz

1450RPM,

7.8Amps

CEL4M15 1

Pry. Sludge Effluent

Pump 1 Goulds WS0529BF 1/2HP, 220V, 3 phase, 50 Hz, 1450RPM, 7.8Amps

CEL4M15 1

Pump 2 Goulds WS0529BF 1/2HP, 220V, 3 phase, 50 Hz

1450RPM,

7.8Amps

CEL4M15 1

Aeration Chambers

Blowers

MBBR 1

Howden 33 U-RAI 1605933000 6510502L 1

MBBR 2 Howden 45 U-RAI 1512926105 6510902L 15750 gallons

Motor 1 Baldor M3558T-57 2HP, 50Hz, 3 phase, 1445RPM

Motor 2 Baldor M3611T-57 3HP, 50Hz, 3 phase, 1445RPM

Pumps

No. 1 Goulds WE1046HH 1HP, 380V, 2900RPM, 2.6

Amps

G1637355 1

No. 2 Goulds WE1046HH 1HP, 380V, 2900RPM, 2.6

Amps

G1637354 1

Clarifier 3180

Air lift pumps

Sludge Digester (Lift station) gallons

Blower 1 Howden 45 U-RAI 1601927963 6510902L 1

Blower 2 Howden 45 U-RAI 1604931466 6510202L 1

Pumps Goulds WS0529BF 1/2HP, 220V, 3 phase, 50 Hz

1450RPM,

7.8Amps

Sanitary sewer Manhole

The petrol interceptor is between SD34 and SS11.

Storm Drain 39

Grease Trap In the cafeteria. 1

II. GENERAL REQUIREMENTS:

The Contractor SOW shall provide all labor, tools, and materials required to carry out all preventive maintenance as outlined in this SOW. US Embassy staff may have service manuals for all equipment included in this SOW. If they do not, the Contractor shall assist Embassy Staff in obtaining the manuals.

III. SCOPE OF WORK - PREVENTIVE MAINTENANCE

Contractor shall provide all materials, supervision, labor, tools and equipment to perform preventive maintenance. All personnel working in the vicinity shall wear and /or use appropriate safety protection while all work is performed. Any questions or injuries shall be brought to the attention of the Post Occupation Safety and Health Officer (POSHO) immediately. Safety Data

Sheets (SDS) shall be provided by the Contractor for all HAZMAT materials. Copies shall be submitted to the COR for approval.

At a minimum, the following work must be done:

Waste Water Collection and Treatment Plant Preventive Maintenance:

1. MAINTENANCE DESCRIPTION:

The maintenance tasks and procedures provided below describe the checks, tests, analysis and tasks required to perform annual, semi-annual and quarterly preventive maintenance for the wastewater collection system and treatment plant.

2. SAFETY & SPECIAL INSTRUCTIONS:

1. Follow procedures in the O&M Manuals for specific equipment.

2. Follow site safety procedures and your supervisor’s instructions.

3. Record and report any equipment damage or deficiencies.

4. Record maintenance information.

5. Maintenance personnel shall be trained on the health hazards of working near sewage plant operations.

6. Maintenance personnel shall be trained, certified, have appropriate equipment and safety plans before and Post approval prior to confined space entry.

7. Follow the manufacturer’s instructions.

8. Wear proper protective equipment.

9. DO NOT ENTER THE SEPTIC TANK. Hazards exist in a septic system. All precautions must be followed when inspecting the system. Keep tank openings covered at all times. Only authorized service personnel should service a septic system. Lethal gases, high voltage electricity, and other deadly hazards associated with the system. Only qualified service staff should open access ports and/or covers. Infectious organisms exist in a septic tank. If any contact with wastewater, immediately wash and disinfect all exposed areas and contact personal physician. Failure to do so could result in severe sickness or death. DO NOT use flame or spark near a septic tank access points. Gases emanating from septic tanks can explode if ignited or deadly if inhaled.

3. MAINTENANCE PROCEDURES:

Listed below are preventive maintenance procedures of a typical wastewater collection system and package treatment plant. The PM frequencies should be evaluated by the Post and adjusted based on local conditions and manufacturer’s recommendations.

Wastewater Collection System

Sludge Digester/ Sewage Lift Station

Semi-Annually:

3.1 Inspect each lift station in the sanitary collection system and assure that all pumps are operational, that all pump control systems are operating correctly, that on-off floats and high-level alarm floats are operating correctly, and that pump lead-lag controls are operating correctly.

3.2 Check lift station lighting, power systems for proper operation.

3.3 Check for leaks on suction and discharge piping, seals, packing glands, etc., make minor adjustments as required.

3.4 Disconnect the lift station pumps discharge pipe from the inlet bar screen of equalization tank, and then connect it to the existing by-pass system.

3.5 Drain the wastewater from all the tanks.

3.6 Remove all the sludge and deposits from the tanks.

3.7 Wire brush, clean and power wash the lift station.

3.8 Remove the pumps, check and clean.

3.9 Check the air diffuser and clean.

3.10 Paint all rusted metal.

3.11 Connect the lift station pumps discharge pipe back to the inlet bar screen.

3.12 Clean-up area and return to normal service.

3.13 Inspect electrical wiring for damage.

3.14 Check V-belts for proper tension and wear. Replace when, necessary

Sewage Collection System

Semi-Annually:

1. Storm Drain Manholes. Remove cover, remove mud and debris, examine interior, clean storm outfalls and sediment ponds, clean work area and remove all debris.

2. Sanitary Sewage Manholes. Remove cover, observe flow through manhole, remove mud

3. and debris, examine interior, thoroughly ventilate manhole if cleaning is required, clean work area and remove all debris.

4. Oil/Water Separators. Clean out separator, inspect for clogging, scale and improper positioned or missing baffles, and tighten loose parts as necessary, dispose of waste properly.

Wastewater Treatment Plant

Equalization Tank, Primary Settling Tanks and Irrigation Tank

1. Inspect the tanks and remove any accumulated solids from the bottom. Inspect the submersible pumps in the tanks and assure that all pumps are operational, that all pump control systems are operating correctly, that on-off floats and high-level alarm floats are operating correctly, and that pump lead-lag controls are operating correctly.

2. Check level sensor for proper operation and level settings.

3. Check pump valves for proper setting on flow to splitter box and feed–back.

4. Clean any grease and floating solids from walls and water surface of equalization tank.

5. Measure the discharge rate from the tanks to the succeeding tank or station. Adjust the return weir to assure the lowest transfer rate into the aeration tank possible within the limitations of the equalization tank volume and ability to equalize post maximum daily flow rates.

6. Fill out maintenance checklist and report deficiencies.

Monthly:

1. Inspect the tank for evidence of proper rolling of mixed liquor suspended solids

(MLSS), fine bubble production from the air diffuser heads, and even diffusion along the length of the aeration tank.

2. Measure the dissolved oxygen in the aeration tank and adjust the blower run intervals accordingly to maintain an average of 1-2 mg/L DO.

3. Conduct a mixed liquor suspended solids (MLSS) settling test of one sample from the aeration basin and one from the effluent from the settling tank. Take readings at five, thirty, and sixty minutes.

4. Inspect the blowers for proper operation. Replace the air filters if dirty, but no less frequently than once every 6-months.

5. Visually check aeration system for even air distribution, with no dead spots.

6. Check oil level in mechanical aerator gear cases. Add or remove as necessary per manufacturer’s instructions.

7. Check oil level in blower gear cases. Add or remove as necessary per manufacturer’s instructions.

8. Check and fix air leaks around base and fitting of blower

9. Check and inspect blower belts for wear and tension.

10. Check bolts and tighten if necessary: foundation, cylinder head, belt guard, etc.

11. Check tension, condition, and alignment of V-belts on blower; adjust or replace as necessary.

12. Check the blower to make sure that belts and drives are free of obstruction and all electrical connection are complete including thermal protection if applicable.

13. Check that effluent weir trough and weir is level and set to the correct elevation and adjust if necessary.

14. Check blowers at a minimum speed and listen for unusual noises.

15. Check the airlift pumps operate continuously and the total pumping rate should be approximately equal to the incoming raw sewage average flow rate.

16. Inspect the sludge digester (also known as the holding tank) where applicable. Pump and clean the tank if settled sludge exceeds 75% of the depth of the tank. Check the airflow in the digester for proper operation.

17. Scrape walls and hoppers of settling tank.

18. Fill out maintenance checklist and report deficiencies.

Blowers:

1. Change blower / mechanical aerator oil

Clarification

1. Inspect the clarifier for cleanliness and clean if required. Inspect the overflow weir cleanliness and uniformity of overflow along the weir. Clean the weir with a brush if required.

2. Inspect the Return Activated Sludge (RAS) airlift pump for proper operation and flow.

3. Inspect the clarifier skimmer airlift pump for proper operation and flow. Clean and adjust the pump as required.

4. Clean clarifier drive and surrounding area.

5. Fill out maintenance checklist and report deficiencies

6. Check unit for rust and corrosion; scape, wire brush and paint as required.

7. Drain and refill gearbox oil reservoir. Disinfection

UV Disinfection

1. Check that surfaces between the UV radiation and the target organisms are clean, and the ballasts, lamps, and reactor are functioning at peak efficiency.

2. Check cleanliness of quartz sleeves or Teflon tubes. These may be cleaned by mechanical wipers, ultrasonic, or chemicals such as citric acid. Other cleaning agents include mild vinegar solutions and sodium hydrosulfite.

3. Clean noncontact reactor systems with sodium hydrosulfite.

4. UV disinfection system should be pilot tested prior to full-scale operation to ensure that it will meet discharge permit requirements for a particular site.

5. Check that ballast is compatible with the lamps and adequately ventilated to protect it from excessive heating.

6. Check the UV lamp runtime and replace before 9,000 hours of use. Ensure that the quartz tube around the UV lamp is clean and free of grease.

7. Fill out maintenance checklist and report deficiencies

Chlorination

1. Inspect the disinfection chamber and tablet chlorinator for proper operation and chlorine contact time.

2. Clean chlorinator and check for leaks

3. Check water trap for proper level and bleed air.

4. Check and clean water strainers

5. Grease fittings

6. Test and calibrate equipment as recommended by the equipment manufacturer.

7. Fill out maintenance checklist and report deficiencies

8. Disassemble and clean the various components of the system, such as meters and floats.

9. Inspect and clean valves and springs

10. All tanks, boxes and basins, should be drained, inspected for scale buildup, rust, corrosion, and cleaned as necessary. Any painted surfaces should be inspected for rust and corrosion, cleaned and re-painted if necessary

Wastewater Testing and Operating Parameters

The performing contractor should test all the parameters below and ensure the plant is well within the Goal range

Dissolved Oxygen (DO) Goal: DO = 1.0 – 2.0 mg/L

Turn blowers off, and wait 5 – 10 minutes. Take sample from aeration basin and test immediately after sampling. If over the course of several tests during the 2-day maintenance visit, the DO is consistently too low, increase the amount of time that blowers are running. If the

DO is consistently too high, decrease the amount of time that blowers are running. The wastewater treatment plant contractor will decrease/increase blower run times by small intervals not to exceed 15-minute increments.

Free and Total Chlorine Goal Free Chlorine = 0.5 – 1.5 mg/L

If the plant has a chlorine contact tank, test the effluent being discharged from the plant. If free chlorine residuals do not meet the goals, the wastewater treatment plant contractor will adjust the chlorination rate. If free chlorine readings are consistently above the goal, reduce the amount of chlorination. If the readings are consistently below the goal, increase the amount of chlorination.

Chlorine Contact Time Goal CT = 20 mg/L-minutes

The wastewater treatment plant maintenance contractor will measure the flow rate of the effluent discharged from the plant at peak hour flows and will calculate the disinfection contact time of the plant (time between injection of chlorine and the discharge of the effluent from the plant).

The CT is calculated by multiplying the free chlorine residual (in mg/L) by the contact time. The wastewater treatment plant maintenance contractor will notify the Facility Manager if the CT is significantly less than the goal.

Chemical Oxygen Demand (COD) Goal = 50 mg/L

The wastewater treatment plant contractor will sample the plant effluent for Chemical Oxygen

Demand (COD). If the COD significantly exceeds the goal, the cleanliness of the plant and the effectiveness of the clarifier weirs will be checked and corrected by the contractor.

Total Suspended Solids (TSS) Goal = 30 mg/L

The wastewater treatment plant contractor will sample the plant effluent for Total Suspended

Solids. If the TSS readings consistently exceeds the goal, the contractor will increase the frequency of scraping the clarifier and scrubbing the overflow weirs. The contractor will check for proper operation of the clarifier skimmer.

Preventive Maintenance Services for Wastewater Treatment Plant: RFQ # 19Z11526Q0003

List of Equipment in the Wastewater Treatment Plant

END OF STATEMENT OF WORK

1 Mfr. Make Model Specifications S/No. P/N Capacity Quantity

Equalisation Chamber

Blower Howden 33 U-RAI 1605933001 6510502L 1

Pump 1 Goulds WS0529BF 1/2HP, 220V,3 phase,50Hz, 1450RPM, 7.8Amps

CEL4M15 1

Pump 2 Goulds WS0529BF 1/2HP, 220V,3 phase, 50 Hz

1450RPM,

7.8Amps

CEL4M15 1

Pry. Sludge

Pump 1 Goulds WS0529BF 1/2HP, 220V, 3 phase, 50 Hz, 1450RPM, 7.8Amps

CEL4M15 1

Pump 2 Goulds WS0529BF 1/2HP, 220V, 3 phase, 50 Hz

1450RPM,

7.8Amps

CEL4M15 1

Chambers

Blowers

MBBR 1

Howden 33 U-RAI 1605933000 6510502L 1

MBBR 2 Howden 45 U-RAI 1512926105 6510902L 15750 gallons

Motor 1 Baldor M3558T-57 2HP, 50Hz, 3 phase, 1445RPM

Motor 2 Baldor M3611T-57 3HP, 50Hz, 3 phase, 1445RPM

Pumps

No. 1 Goulds WE1046HH 1HP, 380V, 2900RPM, 2.6

Amps

G1637355 1

No. 2 Goulds WE1046HH 1HP, 380V, 2900RPM, 2.6

Amps

G1637354 1

Clarifier 3180

Air lift pumps

Sludge Digester (Lift station) gallons

Blower 1 Howden 45 U-RAI 1601927963 6510902L 1

Blower 2 Howden 45 U-RAI 1604931466 6510202L 1

Pumps Goulds WS0529BF 1/2HP, 220V, 3 phase, 50 Hz

1450RPM,

7.8Amps

SECTION 2 - CONTRACT CLAUSES

52.212-4 CONTRACT TERMS AND CONDITIONS – COMMERCIAL ITEMS

(NOV 2023) IS INCORPORATED BY REFERENCE. (SEE SF-1449,

BLOCK 27A)

Instructions for 52.212-5

FAR 52.212-5 Contract Terms and Conditions Required to Implement Statutes or Executive

Orders—Commercial Products and Commercial Services (JAN 2025)

(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or

Executive orders applicable to acquisitions of commercial products and commercial services:

(1) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or

Statements (Jan 2017) (section 743 of Division E, Title VII, of the Consolidated and Further

Continuing Appropriations Act, 2015 (Pub. L. 113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).

(2) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or

Provided by Kaspersky Lab Covered Entities (Dec 2023) (Section 1634 of Pub. L. 115-91).

(3) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video

Surveillance Services or Equipment. (Nov 2021) (Section 889(a)(1)(A) of Pub. L. 115-232).