MTY_COVER SF-30 Amendment 001 RFQ 19MX56-22-Q-0002 PUBLISHED.pdf
PDF 611 KB Posted
- Attached to
- Roof Maintenance and Repair service
- Solicitation number
- 19MX56-22-Q-0002
View the file
Other files
| File | Type | Posted |
|---|---|---|
| MTY_RFQ 19MX56-22-Q0002 QUESTIONS Published.pdf | ||
| MTY_Safety Management Plan DOC.docx | DOCX document | |
| MTY_RFQ 19MX56-22-Q-0002 SITE VISIT.pdf | ||
| RFQ 19MX56-22-Q-0002.pdf | ||
| Express Form NDAA Certification (Oct 2020) (SPANISH).docx | DOCX document | |
| Vendor Registration - MXP FORM.docx | DOCX document | |
| SF 18 COVER PAGE 19MX56-22-Q-0002.pdf | ||
| Letter to Offeror RFQ 19MX56-22-Q-0002.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
C. GENERAL DESCRIPTION/SPECIFICATIONS/WORK STATEMENT
The Contractor shall furnish and install all materials required by this contract. The contract drawings are set forth in Section C.5.
PART ONE – GENERAL
C.1.1 SUMMARY:
A. The U.S. Consulate in Monterrey, Mexico, has a requirement for a solvent-based elastomeric roof coating and roof related repairs on the existing 22,000 square foot NCC Staff Parking
Garage Roof.
The area to be coated consists of a concrete deck. The proposed roof repair coating using a local contractor includes, but is not limited to, the following:
1. Clean/Pressure wash roof areas and allow to dry.
2. Perform minor repairs where the concrete slab has been damaged or showing signs of stress cracks.
3. Begin repair work using a primer at low end around roof drains, scuppers or eave edges.
Apply primer over entire roof field and flashings.
4. After priming the entire surface, apply first grey coat (base coat) over the entire concrete surface, starting at low end around roof drains or eave edges. While first grey coat is still wet, install/roll full polyester fabric. Install fabric over the entire roof area field.
5. Apply a second grey base coat and embed the full fabric over the entire roof area field so that no white fabric shows through. Allow to dry
6. Apply white coat or finishing material and embed fabric on all base flashings (up-turns) around roof perimeter, penetrations, and terminations. Allow to dry.
7. Apply Flashing Grade at all difficult up-turns, terminations, projections, and flashings or where needed to insure proper waterproofing. Allow to dry.
8. Apply first field white topcoat over the grey coat/field of roof and allow to dry, per manufacturer requirements, prior to applying the second white coat.
9. Apply second white topcoat as final finish.
B. The following buildings / roof areas are included in their project.
1. Parking Garage CAC Roof Area (PKG) – 22,000 Square Feet/ 2,044 Square meter
2. Parapet total area is 242.4 m2 total
Total floor area is 2,022 m2 (100x20 + overhang - 8 openings). Parapet total area is 242.4 m2 and MUST BE INCLUDED two hands of TOP COAT ONLY as part of the requirement since is inside the roof structure.
I. LIST OF ATTACHMENTS
ATTACHMENT
NUMBER DESCRIPTION OF ATTACHMENT
NUMBER OF
PAGES
Attachment 1 Sample Bank Letter of Guaranty 1
Attachment 2 Breakdown of Price by Divisions of Specifications 1
Attachment 3 Quantity Survey 1
Attachment 4 Safety Management Plan 1
Attachment 5 Standard Form 25, "Performance and Guaranty Bond” 2
Enclosed link for reference https://www.acquisition.gov/far/part-52#FAR_52_228_15
ATTACHMENT #5
If you are not able to open the attached form – please follow hyperlink for reference
Performance Bond | GSA
STANDARD FROM 25, "PERFORMANCE AND GUARANTY BOND”
SF25-16d1.pdf https://www.acquisition.gov/far/part-52#FAR_52_228_15 https://www.gsa.gov/forms-library/performance-bond