Form W14- Site Visit for Well Drilling Project 19MR6025Q0013 - Questions and Responses.pdf
PDF 66 KB Posted
- Attached to
- New Well Drilling and Pump Installation
- Solicitation number
- 19MR6025Q0013
- Issued by
-
Department of State
About this file
This document is a set of responses to inquiries from a site visit for a Well Drilling Project for the U.S. Embassy in Nouakchott, Mauritania (Solicitation No. 19MR6025Q0013). The responses address key technical and procedural questions about the project, including scope of work, contractor responsibilities, and project timeline. Critical details include the requirement to drill a well to 70 meters depth, install two pumps (one operational and one spare), and complete the project within specific milestones: 30 days for administrative submittals, 105 days for geophysical survey and recommendations, 150 days for well drilling mobilization, 180 days for well completion, and 240 days for final water sample and pump test results.
The document outlines payment structure with milestone-based partial payments: 15% for Pre-Drilling Phase, 30% for Drilling Phase, 20% for Evaluation Phase, 20% for Completion Phase, and 15% for Post-Drilling Phase. The Embassy will provide water and electricity, and contractors are permitted to submit proposals without attending the site visit. The contractor is responsible for demolition and restoration of structures, mud removal, disposal of drilling materials, and installing all necessary well components as specified in the Statement of Work (SOW). The project does not include salt removal filtration systems, and the contractor must conduct a survey to confirm the drilling depth prior to beginning work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation 19MR6025Q0013 Well Drilling and Pump Installation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Responses to Inquiries from July 23, 2025, Site Visit for the Well Drilling Project (Solicitation No. 19MR6025Q0013)
1. When an existent installation obstructs the movement of the project, is it possible to remove or demolish that installation? For example, the small wall The small wall will be demolished for the project and rebuilt after completion. The contractor shall be responsible for demolition and restoration of structures, as necessary, within the limits of disturbance. All structures shall be restored using materials and workmanship.
2.Removal of mud during the excavation The contractor shall be responsible for mud removal during the project. The contractor shall be responsible for disposal of all cuttings, spoiling, drilling mud, and other material, clean-up, and restoration of the site to pre-project conditions.
3. Where does the work of the contractor stop? Connect to local systems?
The contractor work for this project is to build the well, the manhole and have the pump outlet up to the manhole. The contractor shall be responsible for completing all the work described in the scope of work.
4. Does the Embassy provide water and electricity?
Yes
5. Does the contractor install salt removal filtration systems?
No, the contractor is in charge to building the well, installing the pump and the well accessories as specified in the SOW (Sampling and water analyses).
6. Clarify the pumps to be installed in the projects? What are the characteristics, capacity, and models? How many pumps?
Two pumps shall be provided; one shall be installed and the other shall be kept as a spare.
The pump specifications are well described in the SOW.
7. What are the specific accessories to be installed? Are there any other accessories not mentioned in the scope?
The accessories are specified in the SOW, but it is still the responsibility of the contractor to install all required components pertaining to a well.
8. What are surveys that the Embassy has conducted to determine that 70 meters in depth is accurate? Is a contractor allowed to stop at any depth when sufficient water is reached?
The Embassy has only used available city data. The SOW calls 70 meters, a survey shall be conducted by the contractor prior to drilling to confirm drilling depth.
9. What is the time frame to execute the project?
Contractor should provide timeframe and schedule in their offers. It should stipulate some durations such as time to provide bonds and insurance 30 days from notice of award: time to provide schedule, key personnel, worker VAR information, and other administrative submittals 30 days from notice of award. Mobilize for geophysical survey 75 days from award; geophysical survey report and final well recommendations 105 days from award;
well drilling mobilization 150 days from award, well completion 180 days; water sample results, pump test results and final report 240 days from award. You can adjust these durations as you see fit. Add additional durations for key deliverables and check to see that we have stipulated our review time frame (we usually reserve 15 calendar days to review submittals).
10. Is it permissible for a contractor to submit a proposal without having attended the site visit?
Yes, it is permissible for a contractor to submit a proposal without having attended a site visit
11. Is there a possibility to have partial payments during the execution of the project?
For construction contracts (as defined in FAR 36.102), progress payments based on percentage or stage of completion are authorized (FAR 32.102(b)).
To facilitate this process, we kindly recommend corresponding payment percentages for each milestone. Each milestone can be tied to a percentage of the total contract value, ensuring payments aligned with completed deliverables.
- Pre-Drilling Phase: 15%
- Drilling Phase: 30%
- Evaluation Phase: 20%
- Completion Phase: 20%
- Post-Drilling Phase: 15%