This solicitation requests proposals for warehouse support services at the U.S. Embassy in Seoul, South Korea. The services include warehouse operations, house make-ready services, programmatic event setup, airport logistics, and laundry/ironing. Standard services are priced as a fixed monthly rate, while additional services are priced hourly. The base period of performance is 12 months with four optional 12-month extensions. Proposals are due by January 22, 2024. The award will be a fixed-price contract made to the responsible offeror with the lowest price meeting standards. The contract value includes warehouse support, additional services up to 4,000 hours annually, and materials reimbursement up to $3 million per year. The contractor must comply with all Department of State security, conduct, insurance, and safety requirements detailed in the solicitation.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation Notice_19KS7024R0001_Warehouse Support Services-Seoul.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1Embassy of the United States of America
Seoul, Republic of Korea General Services Office
Tel. 82-2-397-4754 Fax: 82-2-397-4744
December 19, 2023 Dear Prospective Offerors:
Subject: Solicitation Number 19KS7024R0001, Warehouse Support Services
Enclosed is a Request for Proposal (RFP) for Warehouse Support Services.
If you would like to submit a proposal, follow the instructions in Section L of the solicitation, complete the required portions of the attached document, and submit it in electronic format to the Contracting Office as shown on the block 8 of the Standard Form 33 that follows this letter.
The U.S. Embassy Seoul intends to award a contract to the responsible company submitting an acceptable proposal at the lowest price. We intend to award a contract based on initial offers, without holding discussions, although we may hold discussions with companies in the competitive range if there is a need to do so.
The Embassy intends to conduct a pre-proposal conference on January 4, 2024 at 13:00 pm, Korea Standard Time at the General Services Office (GSO) Green Room at #10, Namyoung-dong, Yongsan-gu, Seoul, Korea. Site visit will be done right after the pre-proposal conference.
If you intend to participate in the pre-proposal conference/site visit, please contact Ahn, Dong Ho (Tel. 82-2-397-4755, Fax: 82-2-397-4744, email: AhnDH@state.gov) to make necessary arrangement for access to GSO no later than January 3, 2024 at 16:00 hours p.m. Korea Standard Time. Offerors are requested to limit the number of participants to two persons per company. Please be sure to bring the solicitation document with you to the conference. No extra copies will be available at the conference.
Any questions concerning the solicitation should be submitted in writing by January 8, 2024 at 17:00 hours, Korea Standard Time via email.
Proposals are due by January 22, 2024 at 17:00 pm Korea Standard Time. No proposals will be accepted after this time. Proposals must be in English and incomplete proposals will not be accepted.
Your proposal must be submitted electronically to SeoulProposals@state.gov. It is important to make sure the submission is made in specific size and format; in MS-Word 2007/2010 or MS-Excel 2007/2010 or Adobe Acrobat (pdf) file format. The file size must not exceed 30MB. If the file size should exceed the 30MB, the submission must be made in separate files and attached to separate emails with less than 30MB each.
For a proposal to be considered, you must also complete and submit the following:
As required in Section L, the offers shall be submitted in 2 separate packages as in the following:
A. Price Offer: With Prices
1. Signed SF33,
2. Section B, Pricing schedule,
3. Section K, Representations and Certifications
4. IRS Form W-14
The Offeror should submit a completed IRS Form W-14, found at www.irs.gov/w14 to ensure compliance with FAR 52.229-11.
5. Proof of SAM Registration with UEI Number
B. Technical Offer: Without Prices
1. Technical proposals required in Section L.1.1.2 and L.1.2 below.
Offerors shall be registered in the SAM (System for Award Management) database https://www.sam.gov prior to submittal of their offer/proposal as prescribed under FAR 4.1102. Failure to be registered at time of proposal submission may deem the offeror’s proposal to be considered non-responsible and no further consideration will be given. Therefore, offerors are highly encouraged to register immediately if they are interested in submitting a response to this requirement.
Sincerely, Joshua M. Lamb
Contracting OfficerDate:
Enclosure: Solicitation 19KS7024R0001
| SOLICITATION, OFFER AND AWARD |
| 1. THIS CONTRACT IS A RATED ORDER |
UNDER DPAS (15 CFR 350)
| RATING |
| PAGE OF PAGES |
2. CONTRACT NUMBER
3. SOLICITATION NUMBER
19KS7024R0001
4. TYPE OF SOLICITATION
[ ] SEALED BID (IFB)
[x] NEGOTIATED (RFP)
5. DATE ISSUED
December 19, 2023
6. REQUISITION/PURCHASE NUMBER
7. ISSUED BY CODE
8. ADDRESS OFFER TO (If other than item 7)
U.S. Embassy Seoul
GSO-PUR
10, Namyoung-dong
Yongsan-gu, Seoul, Korea U.S. Embassy Seoul Contacting Office
(SeoulProposals@state.gov)
NOTE: In sealed bid solicitation "offer" and "offeror” mean "bid" and "bidder".
SOLICITATION
9. Electronically submitted offers will be received at the email address specified in item 8, until January 22, 2024, Not Later Than 5 p.m., Seoul time.
CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L. Provision No. 52.215-1. All offers are subject to all terms and conditions contained in this solicitation.
| 10. FOR INFORMATION CALL: |
| A. NAME |
Joshua M. lamb
| B. TELEPHONE (NO COLLECT CALLS) |
| C. E-MAIL ADDRESS |
SeoulProposals@state.gov
AREA CODE
82-2
NUMBER
EXT
11. TABLE OF CONTENTS
| (x) |
| SEC. |
| DESCRIPTION |
| PAGE(S) |
| (x) |
| SEC. |
| DESCRIPTION |
| PAGE(S) |
| PART I - THE SCHEDULE |
| PART II - CONTRACT CLAUSES |
| X |
| A |
| SOLICITATION/CONTRACT FORM |
| 3 |
| X |
| I |
| CONTRACT CLAUSES |
| 33 |
| X |
| B |
| SUPPLIES OR SERVICES AND PRICES/COSTS |
| 4 |
| PART III - LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACH. |
| X |
| C |
| DESCRIPTION/SPECS/WORK STATEMENT |
| 8 |
| X |
| J |
| LIST OF ATTACHMENTS |
| 48 |
| D |
| Deleted |
PART IV - REPRESENTATIONS AND INSTRUCTIONS
| X |
| E |
| INSPECTION AND ACCEPTANCE |
| 23 |
| X |
| K |
| REPRESENTATIONS, CERTIFICATIONS, AND |
| 55 |
| X |
| F |
| DELIVERIES OR PERFORMANCE |
| 25 |
OTHER STATEMENTS OF OFFERORS
| X |
| G |
| CONTRACT ADMINISTRATION DATA |
| 27 |
| X |
| L |
| INSTRS., COND., AND NOTICES TO OFFERORS |
| 72 |
| X |
| H |
| SPECIAL CONTRACT REQUIREMENTS |
| 28 |
| X |
| M |
| EVALUATION FACTORS FOR AWARD |
| 77 |
OFFER (Must be fully completed by offeror)
NOTE: ITEM 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.
12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (120 calendar days unless a different period is inserted by the offer) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.
13. DISCOUNT FOR PROMPT PAYMENT
(See section I, Clause No 52.232-8)
| 10 CALENDAR DAYS (%) |
| 20 CALENDAR DAYS (%) |
| 30 CALENDAR DAYS (%) |
| CALENDAR DAYS (%) |
| 14. ACKNOWLEDGMENT OF AMENDMENTS |
| AMENDMENT NO. |
| DATE |
| AMENDMENT NO. |
| DATE |
(The offeror acknowledges receipt of amendments to the solicitation and related documents ) numbered and dated:
15A.
NAME AND ADDRESS OF OFFEROR
CODE
FACILITY
16. NAME AND TITLE OF PERSON AUTHORIZED
TO SIGN OFFER (Type or print)
| 15B. TELEPHONE NO. (Include area code) |
| [ ] 15C. CHECK IF REMITTANCE ADDRESS IS DIFFERENT FROM ABOVE - ENTER SUCH ADDRESS |
| 17. SIGNATURE |
| 18. OFFER DATE |
AREA CODE
NUMBER
EXT
AWARD (To be completed by Government)
19. ACCEPTED AS TO ITEM NUMBERED
| 20. AMOUNT |
| 21. ACCOUNTING AND APPROPRIATION |
22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:
[ ] 10 U.S.C. 2304(c) [ ] 41 U.S.C. 253(c)
23. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM
24. ADMINISTRATION BY (If other than Item 7) CODE
25. PAYMENT WILL BE MADE BY CODE
26. NAME OF CONTRACTING OFFICER (Type or print) Joshua M. Lamb
27. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
28. AWARD DATE
IMPORTANT - Award will be made on this form, or on the Standard Form 26, or by other authorized official written notice.
AUTHORIZED FOR LOCAL REPRODUCTION
STANDARD FORM 33 (REV 9-97)
Previous edition is unusable
Prescribed by GSA – FAR (48 CFR) 53.214(c)
SECTION B
SUPPLIES OR SERVICES AND PRICES/COSTS
B.1
SCOPE OF SERVICES
The Contractor shall provide personnel, supplies and equipment, as identified in this solicitation, for all warehouse support services for US Embassy Seoul as described in Section C, DESCRIPTION/SPECIFICATIONS/WORK STATEMENT, of this contract and all Exhibits attached in Section J.
B.2
TYPE OF CONTRACT
This is a fixed price contract for Standard Services as defined in Section C, DESCRIPTION/SPECIFICATIONS/WORK STATEMENT. The fixed price will include all work, including furnishing all labor, materials, equipment, and services, overhead and profit, unless otherwise specified.
Indefinite delivery/indefinite quantity type contract will be awarded for additional services.
B.3
TYPES OF SERVICES
(a) Standard Services. The Contractor shall provide standard warehouse support services as specified in Section C within the buildings listed in Section J, Exhibit A.
(b) Additional Services.
The Contractor shall provide Additional Services that are temporary when requested by the Contracting Officer through a written order. These Additional Services shall be delivered in addition to the Standard Services and shall be priced at the unit price shown below. The tasks to be accomplished are additional quantities of the same tasks described in Section C.
Because Additional Services are based on indefinite delivery/indefinite quantity the minimum and maximum amounts are defined below:
Minimum: The Government shall place orders totaling a minimum of 50 hours. This reflects the contract minimum for the base year and option period.
Maximum: The amount of all orders shall not exceed 4,000 hours. This reflects the contract maximum for the base year and each option period for Additional Services.
The hourly rates for Additional Services, as defined in Section C, are fully loaded rates, including:
· All direct and indirect labor costs (including any premiums relating to overtime, holidays or night shifts, etc., and materials,
· All overhead and indirect costs, including general and administrative expenses (g&a); and Profit.
B.4
PRICING
(a) The Government will pay the Contractor a fixed price per month for Standard Services that have been satisfactorily performed. The Government will also pay the Contractor for Additional Services ordered each month by the Government for satisfactorily completed work.
(b) Offers and Payment in U.S. dollars:
U.S. firms are eligible to be paid in U.S. dollars. U.S. firms desiring to be paid in U.S. dollars should submit their offers in U.S. dollars. A U.S. firm is defined as a company which operates as a corporation incorporated under the laws of a state within the United States.
Foreign firms:
Any firm, which is not a U.S. firm, is a foreign firm. Any firm that does not meet the above definition of U.S. firm shall submit its prices and receive payment in local currency.
(c) The Contractor shall include any premium pay for services required on holidays only in the fixed prices for Standard Services. The Contractor shall include any premium pay for overtime only in the fixed rates for Additional Services.
(d) The Government will also reimburse the Contractor at the purchase price for any materials or equipment ordered by the Government for Additional Services.
(e) The cost of Workers’ Compensation War-Hazard Insurance Overseas (See Section I, FAR 52.228-4) is not reimbursable and shall be included in the Contractor’s rates.
(f) Value Added Tax. Value Added Tax (VAT) is not applicable to this contract and shall not be included in the rates for Standard Services and Additional Services.
B.5 Base Year Prices
(a) Standard Services. The fixed price for the Base Year of the contract is (starting on the date stated in the Notice to Proceed (NTP) and continuing for a period of 12 months):
| Price per Month |
| 12 months |
| Price per Year |
X 12
(b) Additional Services. The unit fixed price is:
| Price per Hour |
| Estimated Number of hours per Year |
| Total Not to Exceed Price |
800 hours
(c) Materials or Equipment. The Government will reimburse the Contractor for any materials or equipment that the Government orders to be delivered in conjunction with any order for Additional Services. All reimbursements shall be paid for the Contractor's out of pocket cost, with no overhead, profit, or other charge added.
| Material/Equipment Not to Exceed per Year |
| W3,000,000 |
Total Not to Exceed Price for Base Year (a + b + c)
B.6 Option Year 1 Prices (Option Term: Twelve (12) Months)
(a) Standard Services. The fixed price for Option Year 1 of the contract is:
| Price per Month |
| 12 months |
| Price per Year |
X 12
(b) Additional Services. The unit fixed price is:
| Price per Hour |
| Estimated Number of hours per Year |
| Total Not to Exceed Price |
800 hours
(c) Materials or Equipment. The Government will reimburse the Contractor for any materials or equipment that the Government orders to be delivered in conjunction with any order for Additional Services. All reimbursements shall be paid for the Contractor's out of pocket cost, with no overhead, profit, or other charge added.
| Material/Equipment Not to Exceed per Year |
| W3,000,000 |
Total Not to Exceed Price for Option Year 1 (a + b + c)
B.7 Option Year 2 Prices (Option Term: Twelve (12) Months)
(a) Standard Services. The fixed price for Option Year 2 of the contract is:
| Price per Month |
| 12 months |
| Price per Year |
X 12
(b) Additional Services. The unit fixed price is:
| Price per Hour |
| Estimated Number of hours per Year |
| Total Not to Exceed Price |
800 hours
(c) Materials or Equipment. The Government will reimburse the Contractor for any materials or equipment that the Government orders to be delivered in conjunction with any order for Additional Services. All reimbursements shall be paid for the Contractor's out of pocket cost, with no overhead, profit, or other charge added.
| Material/Equipment Not to Exceed per Year |
| W3,000,000 |
Total Not to Exceed Price for Option Year 2 (a + b + c)
B.8 Option Year 3 Prices (Option Term: Twelve (12) Months)
(a) Standard Services. The fixed price for Option Year 3 of the contract is:
| Price per Month |
| 12 months |
| Price per Year |
X 12
(b) Additional Services. The unit fixed price is:
| Price per Hour |
| Estimated Number of hours per Year |
| Total Not to Exceed Price |
800 hours
(c) Materials or Equipment. The Government will reimburse the Contractor for any materials or equipment that the Government orders to be delivered in conjunction with any order for Additional Services. All reimbursements shall be paid for the Contractor's out of pocket cost, with no overhead, profit, or other charge added.
| Material/Equipment Not to Exceed per Year |
| W3,000,000 |
Total Not to Exceed Price for Option Year 3 (a + b + c)
B.9 Option Year 4 Prices (Option Term: Twelve (12) Months)
(a) Standard Services. The fixed price for Option Year 4 of the contract is:
| Price per Month |
| 12 months |
| Price per Year |
X 12
(b) Additional Services. The unit fixed price is:
| Price per Hour |
| Estimated Number of hours per Year |
| Total Not to Exceed Price |
800 hours
(c) Materials or Equipment. The Government will reimburse the Contractor for any materials or equipment that the Government orders to be delivered in conjunction with any order for Additional Services. All reimbursements shall be paid for the Contractor's out of pocket cost, with no overhead, profit, or other charge added.
| Material/Equipment Not to Exceed per Year |
| W3,000,000 |
Total Not to Exceed Price for Option Year 4 (a + b + c)
B.10 6-MONTH OPTION TO EXERCISE- FAR 52.217-8
(a) Standard Services. The fixed price for Option Year 4 of the contract is:
| Price per Month |
| 6 months |
| Price per Year |
X 6
(b) Additional Services. The unit fixed price is:
| Price per Hour |
| Estimated Number of hours per Year |
| Total Not to Exceed Price |
400 hours
(c) Materials or Equipment. The Government will reimburse the Contractor for any materials or equipment that the Government orders to be delivered in conjunction with any order for Additional Services. All reimbursements shall be paid for the Contractor's out of pocket cost, with no overhead, profit, or other charge added.
| Material/Equipment Not to Exceed per 6 Month |
| W1,500,000 |
Total Not to Exceed Price for Option Year 4 (a + b + c)
B.11 Grand Total of Base plus ALL Option Years
Base Year Total
Option Year 1 Total
Option Year 2 Total
Option Year 3 Total
Option Year 4 Total
6 Month Option To Exercise -FAR 52.217-8
Grand Total of Base plus All Option Years
SECTION C
DESCRIPTION/SPECIFICATIONS/WORK STATEMENT
C.1
WORK REQUIREMENTS
C.1.1 General. The Contractor shall provide services for the U.S. Embassy, Seoul. The Contractor shall perform warehouse support services for property owned or managed by the U.S. Government in Seoul, Korea as listed in Section J, Exhibit A, “LOCATIONS FOR WAREHOUSE SUPPORT SERVICES.” The Contractor shall furnish all managerial, administrative, and direct labor personnel necessary to accomplish the work in this contract. Contractor employees shall be on site only for contractual duties and not for other business purposes.
C.1.2 Personnel. The Contractor shall provide a qualified work force meeting the contract requirements, including sufficient laborers to carry out the tasks plus a Project Manager as specified in C.3.1.1 of this contract. The workforce shall be able to provide the services identified in Section C.2.
C.1.3 General Requirements.
C.1.3.1 Definitions.
"General Instructions" mean those instructions, directives and guidelines that apply to all warehouse support service personnel.
"Chancery" means the Embassy building
“CMR” means the official residence of the ambassador.
"Daily" means 5 days per week, on each non-holiday workday.
"DCMR" means the official residence of the Deputy Chief of Mission.
“Work Order” means a task or work instructions given to the contracted laborer with a specific timeline for completion. These are issued daily and indicate the routine actions that are expected of the contractor per the contract (i.e. Deliver welcome kit to house A, provide make ready services to house C, etc.).
C.1.3.2 The Contractor shall prepare general instructions for the work force. The Contractor shall provide drafts to the Contracting Officer’s Representative (COR) for review within thirty days after award of the contract. The COR must approve these general instructions before issuance.
C.1.4 Duties and Responsibilities.
C.1.4.1
Certain areas specified in Section J, Exhibit A require an escort and can only be entered during scheduled times. The Embassy will provide escorts for these areas. The General Instructions shall emphasize security requirements so that accidental security violations do not occur.
C.1.4.2
Contractor shall schedule warehouse support services requirements to ensure that these are done in the order and time frame that are most efficient and have the least impact on normal operations. They are to be performed on a daily basis. Due to security escort requirements, programmatic needs, customer service standards, and resource constraints, the contractor must closely coordinate delivery schedules with the COR. The four hour performance standard is intended to allow the contractor enough time to perform the work and coordinate delivery schedules with the COR in a manner that meets all programmatic and logistic requirements. For an urgent request, the Contracting Officer (CO) may order services orally and with less advance notice. Such orders will be confirmed in writing the following work day.
C.1.4.3
Additional Services are services that are defined as Standard Services but are required at times other than the normal workday. These services shall support special events at the Post. The Contractor shall provide these services in addition to the scheduled services specified in paragraph C.2.1 thru C.2.5 of this contract. The Contracting Officer shall order these services as needed by issuing a written task order. This work shall be performed by trained employees of the Contractor, and shall not be subcontracted. The Contracting Officer may require the Contractor to provide additional services with 24 hour advance notice. In emergency situations the Contracting Officer may order additional services orally and with less advance notice. Such orders will be confirmed in writing within the three working days.
C.1.4.4
The Contractor shall include in its next regular invoice details of the additional services and, if applicable, materials provided and requested under additional services. The Contractor shall also include a copy of the task order requesting the additional services.
C.2
TYPES OF SERVICES
Standard Services shall include the following (C.2.1 thru C.2.5).
C.2.1 Warehouse Operations Services Warehouse operations services shall include receiving, delivery and pick up. Delivery and pick up service shall take place at locations identified in Section J, Exhibit A and any other locations as specified by the COR. Contractor shall be responsible for maintaining a clean working environment at ten (10) warehouses and six (6) storage areas on the Embassy Annex, covering a total area of 37,259 square feet.
C.2.1.1
Receiving Operations
General Services Office (GSO) is responsible for officially receiving items that are delivered to the Embassy. In performing these duties, GSO staff will prepare and file the receiving reports, keep track of items received and issued, and sign for receipt of items/supplies delivered to the Embassy. The contractor, in performing receiving operations as described in this section, shall be responsible for the physical unloading, unpacking, repacking, and placing of items received by GSO into their designated warehouse spaces.
(a) Shipping containers
(i) Unload shipping containers and crates at receiving warehouse (W1), to include the GSO warehouse and other government locations.
(ii) Dismantle and unpack shipping containers and crates.
(iii) Repack and clean opened containers and crates as needed after inspection of received items by GSO staff.
(iv) Store received items into designated warehouse/storage spaces within a maximum of 3 days after receipt by GSO staff.
(v) Performance standard: Contractor shall complete unloading, unpacking, and repacking of 20' to 40' shipping containers and crates within 4 hours after receipt of work order. Contractor shall complete placement of items into designated spaces within 3 days of work order receipt. No more than one late receiving/unloading operation per month.
(vi) Estimated work volume per year : 25 containers (175 items per 20’ or 40’container) and 20 crates (various sized and weight)
(b) Shipping boxes
(i) Unload shipping boxes at receiving warehouse (W1), to include the GSO warehouse and other government locations.
(ii) Dismantle and unpack shipping boxes.
(iii) Repack and clean opened boxes as needed after inspection of received items by GSO staff.
(iv) Store received items into designated warehouse/storage spaces.
(v) Performance standard: Contractor shall complete unloading, unpacking, and repacking of shipping boxes within 4 hours upon the receipt of work order. Contractor shall complete placement of items into designated spaces within 3 days of work order receipt. No more than one late receiving operation per month.
(vi) Estimated work volume per year: 1,500 shipping boxes. These are spread throughout the year.
C.2.1.2 Deliveries and pick up (exclusive of make-ready tasks)
(a) Expendable Supplies
(i) Collect office supplies from the warehouse for issuance.
(ii) Deliver office supplies on a regular weekly delivery schedule, plus emergency deliveries as needed.
(iii) Clean office supplies regularly and before issuance.
(iv) Performance standard: Contractor shall complete delivering office supplies within 4 hours upon the receipt of work order. No more than one late delivery per month, and no more than one customer complaint per month.
(v) Estimated work volume per year : 1,500 work orders (average 5 line items per work order)
(b) Welcome Kits (See Section J, Exhibit D)
(i) Pull welcome kit items from storage warehouses and prepare welcome kits for delivery.
(ii) Deliver, unpack, and arrange welcome kit items in houses.
(iii) Pick up welcome kit items from houses.
(iv) Clean, wash returning welcome kit items and place in correct storage locations. Iron linen items when requested.
(v) Label the loanable TV and vacuum with a house number for the correct record keeping.
(vi) Performance standard: Contractor shall complete assembling, cleaning, storing, and arranging welcome kit items within 4 hours of the designated delivery time. The contractor will be given a minimum of 4 hours between the receipt of the work order and the designated delivery time. There shall be no discrepancy between items listed in the welcome kit inventory and the actual items that are verified to be in the home during the final inspection performed by GSO. No more than one late delivery per month, no more than one incorrect assemble per month, and no more than one customer complaint per month.
(vii) Estimated work volume per year : 180 work orders (average 55 items per work order)
(c) Maintenance supplies and auto supplies
(i) Deliver supplies and auto parts from storage warehouses for issuance to the Facility Maintenance Office and Motorpool Mechanics.
(ii) Performance standard: Contractor shall complete counting and preparation of maintenance supplies and auto parts within 4 hours upon the receipt of work order. No more than one late pulling out per month, and no more than one customer complaint per month.
(iii) Estimated work volume per year : 50 work orders (average 3 items per work order )
(d) Standard Warehouse Items
(i) Prepare items for delivery.
a) Dust, and clean all furniture and furnishings, including household furniture (except for residential wood furniture), appliances, lamps, mattresses, office furniture, and office equipment no more than 4 hours prior to the delivery time. All wood furniture should be dusted and wiped clean prior to delivery (drawers included). Drawers should be repaired if not closed properly. All residential wood furniture should be polished prior to delivery.
i) Performance standard: Contractor shall complete cleaning of all furniture and equipment prior to the scheduled delivery time. All furniture and equipment in warehouse shall be free of dust, dirt, and sticky surfaces prior to issuance to the customers. No more than one late preparation per month, and no more than one customer complaint per month.
ii) Estimated work volume per year : 800 work orders (average 5 items per work order )
b) Clean and shampoo all cushioned furniture items, including sofas, loveseats, easy chairs, occasional chairs, dining chairs, and office chairs. Unfold and vacuum mattresses from sofa beds.
i) Performance standard: Contractor shall complete cleaning of all cushioned furniture items no more than 48 hours prior to delivery. All cushioned furniture shall be free of dust, dirt, stains, and sticky surfaces when delivered to the customers. No more than one late cleaning per month, and no more than one customer complaint per month.
ii) Estimated work volume per year : 70 work orders (average 3 items per work order )
iii) Dust and clean all mattresses. Shampoo mattresses if required.
iv) Performance standard: Contractor shall complete cleaning of all mattresses no more than 48 hours prior to delivery. All mattresses shall be free of dust, dirt, and stain when delivered to the customers. No more than one late cleaning per month, and no more than one customer complaint per month. Wrap mattresses that are intended for storage in the warehouse.
v) Estimated work volume per year : 100 work orders (average 1.5 items per work order )
(ii) Re-arrange and/or re-stock items after delivery to or pick up from specified locations.
a) Performance standard: Contractor shall complete rearrangement and restocking within 4 hours of the designated time on the work order. In case of pick up items, contractors shall provide a tally-in sheet listing all items for verification. No more than one late delivery or pick-up per month, and no more than one customer complaint per month.
b) Estimated work volume per year : 800 work orders (average 5 items per work order ) C.2.1.3 Maintenance and Cleaning of the Warehouse
(a) Sweep and wet mop all floor areas in the warehouses on a weekly basis (10 warehouses and 6 storage areas for a total area of 37,259 square feet - See Section J, Exhibit F).
(b) Sweep all floor areas in the warehouse whenever a large shipment or delivery has been made.
(c) Maintain a clean and neat warehouse, dusting, sweeping and mopping as needed to meet the performance standard.
(d) Performance standard: Floors and shelving shall be free of dust, mud, sand, and other debris. Corridors shall be free of any boxes, crates, packing supplies, or property items. No more than one customer complaint per month.
(e) Estimated work load per year : 70 work orders (cleaning/sweeping all warehouse spaces)
C.2.1.4 Storing / Organizing
(a) Pack and wrap furniture, equipment, and related items for storage and delivery.
(i) Items must be properly packed and wrapped to prevent damage, including the corners.
(ii) Government furnished craft wrapping paper and hard cardboard paper boxes shall be used in case of easily damaged items.
(iii) Performance standard: Contractor shall complete packing and wrapping within 4 hours of receiving the work order. No more than one unsatisfactory packing and wrapping per month, and no more than 1 customer complaint per month.
(iv) Estimated work volume per year : 50 work orders
(b) Annual inventory
(i) Assist in conduct of annual property inventory by pulling out from various warehouse locations, counting, verifying, and re-stocking all items in all warehouses and other Embassy locations in conjunction with the GSO staff.
a) All stacked furniture and equipment must be made accessible for GSO staff to scan each bar code. All items must be returned to their original position (or designated location) after verifying code.
i) Estimated work load per year: 5,000 items to be moved, counted, verified, and re-stocked during the annual property inventory exercise.
ii) Performance standard: Items shall be moved, counted, and verified according to the designated inventory schedule. No more than three incorrect counts per year. The designated inventory schedule shall be provided a minimum of 4 hours prior to the performance of inventory activities.
b) All stacked office supplies, maintenance supplies, and auto parts in warehouse bins and storage locations must be counted, verified, and documented in conjunction with the GSO staff. All items must be returned to their original position (or designated location) after verification.
c) An inventory shall be performed once annually, usually between November and February.
i) Estimated work load per year: 2,500 different stock items to be counted, verified, and re-stocked.
ii) Performance standard: All items shall be counted, verified and no more than three incorrect counts per year.
(c) Disposal Operations
(i) Moving, cleaning, preparing, and loading items for property disposal
a) Wipe, sweep, brush, or otherwise clean items in preparation for disposal.
b) Safeguard all items against damage or theft
c) Load items for delivery in trucks, vans, and other delivery vehicles.
d) Deliver loads of items to disposal sites.
e) Estimated work load per year: 2,000 non-expendable property items and 1,000 expendable property items.
f) Performance standard: Contractor shall complete preparations for disposal within 4 hours of the scheduled time. The contractor will be given at least 7 calendar days to perform all disposal sale preparation activities. No more than one customer complaint per year.
C.2.2 House Make-Ready Services
House Make-ready services shall include removing, preparing, delivering, installing, and cleaning furniture and appliances in designated residential areas identified in Section J, Exhibit A. A full make-ready consists of approximately 80 items of furniture and household appliances. An average house make-ready is comprised of removing and reissuing 30 pieces of furniture and appliances from each residence. Estimated frequency of make-ready service is 1 to 2 residences per week, with a maximum estimate of twelve (12) residences per week during the peak summer season.
C.2.2.1 Pre-Make Ready
(a) At the start of each make-ready, gather the furniture in each residence into the center of each room and cover for protection. Remove all drapes & sheers from the windows, and remove all pins.
(b) Return designated furniture and appliances to the warehouse.
(c) Performance standard: Contractor shall gather all furniture without damage and load/unload all items at the scheduled work hour. The contractor will receive no less than 8 hours advance notice to complete this task. No more than one late delivery and no more than one late completion per month.
(d) Estimated work load per year: 90 residences per year
C.2.2.2 Restocking
(a) Assist GSO staff in checking the condition of all items returning from the residences.
(b) Restock or place all items into designated warehouses and storage locations in accordance to specifications described in section C.2.1.4 Storing / Organizing.
(c) Performance standard: Complete restocking and placing items within 48 hours after the receipt of work order. No more than one late delivery and no more than one late completion per month.
(d) Estimated work load per year: 30 pieces of furniture and appliances per make-ready
C.2.2.3 Gathering, delivering, installing, and placing items from warehouses into designated residences.
(a) Assist GSO staff in selecting items for loading and delivery to make-ready residences.
(b) Load, deliver, and install items at the make-ready house.
(c) Performance standard: Complete delivery, installation, and placement of items at the scheduled work hour. The contractor will receive no less than 8 hours advance notice to complete this task. No more than one late delivery and no more than one late completion per month.
(d) Estimated work load per year: 30 pieces of furniture and appliances per make-ready C.2.2.4 Cleaning and installation of make-ready furniture and furnishings
(a) Clean furniture and furnishings per instructions in Section C.2.1.2 (d).
(b) Place all items in their designated room locations.
(c) Install drapes and sheers (including steam treatment). Contractor shall wash drapes and sheers when required.
(d) Performance standard: Contractor shall complete the cleaning and installation of furniture and furnishings in houses at the scheduled work hour. The contractor will receive no less than 48 hours advance notice to complete this task. No more than one late delivery and no more than one late completion per month.
(e) Estimated work load per year: 90 residences per year C.2.2.5 The U.S. Government reserves the right to change make-ready work orders up to three times per work order.
C.2.3 Programmatic Event Set Up Services
Programmatic event set up services include arranging tables and chairs; setting up tents; moving equipment, furnishings and appliances; delivering supplies; and providing related logistics services in support of receptions, concerts, press conferences, lectures, seminars, meetings, exhibitions, VIP visits, and other programmatic events as required. Programmatic events may be held indoors or outdoors at locations specified in Section J, Exhibit A.
C.2.3.1 Representational Events at the CMR and DCMR
(a) Set up tables and chairs for official receptions at CMR and DCMR.
(b) Remove furniture and furnishings from representational rooms to the basement, guest bedrooms, and other areas as required.
(c) Set up tables and chairs for events in accordance with programmatic requirements.
(d) Return furniture and furnishings to their original positions after the event and store tables and chairs.
(e) Iron chair covers, linens, and other items at the residences as required.
(f) Performance standard: Contractor shall complete event set-up at the CMR or DCMR within 4 hours upon the receipt of the work order. No more than one late set up and no more than one late completion per month.
(g) Estimated work load per year: 50 events (average event size: 40 guests per event)
C.2.3.2 Public Outreach Events through the Public Affairs Office & Information Resource Center
(a) Set up tables and chairs for public events held at the Public Affairs Office and Information Resource Center.
(b) Return tables and chairs to their original positions after the event.
(c) Event types will include meetings, seminars, press conferences, lectures, presentations, and parties.
(d) Performance Standard: Contractor shall set up tables and chairs within 4 hours upon the receipt of work order. No more than one late set up and no more than one late completion per month.
(e) Estimated work load per year: 100 events (average event size: 60 guests per event)
C.2.3.3 Chancery Building events
(a) Set up tables and chairs at the Chancery cafeteria, Consular waiting room, or other venues within the chancery to support official functions like conferences, training programs, official ceremonies, and parties.
(b) Return tables and chairs to their original positions after the event.
(c) Performance standard: Contractor shall set up tables and chairs within 4 hours upon the receipt of work order. No more than one late set up and no more than one late completion per month.
(d) Estimated work load per year: 40 events per year (typical event size: 40-80 guests per event)
C.2.3.4 Exhibit Locations
(a) Move furniture, equipment and supplies for various exhibits between designated Embassy offices and specified exhibit locations.
(b) Return tables and chairs to their original positions as needed after the exhibit.
(c) Performance standard: Contractor shall complete delivering items within 4 hours upon the receipt of work order. No more than one late delivery and no more than one customer complaint per month.
(d) Estimated work load per year: 30 events per year
C.2.3.5 Outdoor Tents
(a) Set up and dismantle tents, tables and chairs for official events at designated locations in Section J, Exhibit A.
(b) GSO has an inventory of different tent sizes that may be used in support of various outdoor events. Current inventory includes:
Size of Tents
Quantity Approx. Weight 6m x 6m (Mongolian)
32 ea
110kg each
4m x 4m (Mongolian)
2 ea
75kg each
3m x 3m (Mongoian)
2 ea
65kg each
3m x 6m (Zabara) 4 ea
70kg each
(c) Tents must be set up and dismantled on time and safely, ensuring our customers are satisfied with the delivery and installation.
(d) Contractor shall ensure the wearing of safety helmets and shoes to avoid any possible accidents. Contractor shall ensure US Government safety policies are followed.
(e) Performance standard: Contractor shall complete setting up tents by the designated time with no less than 8 hours advance notice. Contractor shall complete the dismantling of tents by the designated time with no less than 8 hours advance notice. No more than one late set up or dismantling per month, and no more than one customer complaint per month.
(f) Estimated work load per year: 50 events per year (average event size: 6 tents per event)
(g) USG reserves the right to change outdoor tent work orders up to three times per work order, but with no less than 2 hours advance notice.
C.2.3.6 VIP Visit Support
(a) Make deliveries, pick-ups, and setup/installation of furniture and equipment in support of VIP visits.
(b) Furniture and equipment may include copiers or shredding machine, office supplies, computer hardware, and other items from the GSO warehouses. An Embassy escort will be provided when classified items are involved.
(c) Performance standard: Contractor shall complete delivering items within 4 hours upon the receipt of work order. No more than one late delivery per month.
(d) The Contractor will assume responsibility for any liabilities associated with accidents.
(e) Estimated work load per year: 20 VIP visits per year. Moving office supplies (average 10 boxes) to/from hotels for VIP visits including setting-up and dismantling of rooms used by the Embassy as functional spaces.
C.2.4 Airport Logistics Service
Airport Logistics support consists of assisting with unloading and delivery of cargo flights and transporting baggage and equipment for visiting delegations.
C.2.4.2 Transporting baggage and equipment
(a) Transporting baggage and equipment between various airports, bus or train stations, and hotels for VIP delegations
(b) Load/unload, deliver, and count/verify baggage in conjunction with Embassy staff.
(c) Drive Embassy vehicle to/from airport and hotel with baggage and Embassy staff.
(d) Performance standard: Contractor shall complete baggage delivering within 4hours after the arrival of the luggage. No more than one late delivery per month, and no more than one customer complaints per month
(e) Estimated work load per year: 20 visits and 50 items per visit C.2.5 Laundry and Ironing Services
Laundry and ironing services include washing and ironing of drapes, sheers, welcome kit linens, table clothes, uniforms, sheets, chair covers and other fabric for the locations identified in Section J, Exhibit A.
C.2.5.1 Drapes and sheers
(a) Wash all drapes and sheers from residences. Drapes and sheers size for standard 3 bedroom house is as below;
· Living room window: 200”W x 90”H
· Dining room window: 90”W x 90”H (Less than 15 houses)
· Bedroom 1 window: 95”W x 68”H – 1ea, 95”W x 46”H – 1ea
· Bedroom 2 window: 95”W x 68”H – 1ea, 95”W x 46”H – 1ea
· Bedroom 3 window: 95”W x 68”H – 1ea
· Entry & French (Sheer only): 32”W x 82”H, 22”W x 73”H
(b) Performance standard: Contractor shall wash drapes and sheers clean without any stain by the start date of Property section’s house make ready. The contractor will receive no less than 16 hours advance notice to complete this task. No more than one late completion per month.
(c) Estimated work load per year: 90 houses per year with a maximum estimate of 12 residences per week during the peak summer season.
C.2.5.2 Table clothes
(a) Wash and iron various sized table clothes.
(b) Performance standard: Contractor shall wash and iron table clothes clean and neatly by the designated date. The contractor will receive no less than 8 hours advance notice to complete this task. No more than one late completion per month.
(c) Estimated work load per year: 300 table clothes from the American Center in Korea (ACK) and other offices per year.
C.2.5.3 Chair covers
(a) Wash and iron chair covers for the Ambassador residence.
(b) Performance standard: Contractor shall wash and iron chair covers clean and neatly by the designated date. The contractor will receive no less than 8 hours advance notice to complete this task. No more than one late completion per month.
(c) Estimated work load per year: 100 chair covers per year.
C.2.5.4 Welcome kit linens
(a) Wash and iron welcome kit linens such as bedspreads, blankets, sheets, pillow cases, and towels.
(b) Performance standard: Contractor will receive no less than 8 hours advance notice to complete this task. No more than one late completion per month.
(c) Estimated work load per year: 50 sets per year.
C.2.5.5 Fabric washing and ironing
(a) Wash and iron other fabric such as uniforms, gowns, sheets, and others.
(b) Performance standard: Contractor shall wash and iron requested fabric clean and neatly by the designated date. The contractor will receive no less than 8 hours advance notice to complete this task. No more than one late completion per month.
(c) Estimated work load per year: 50 pieces per year.
C.2.5.6. Office furniture dissembling and relocation
(a) Dismantle, relocate and re-assemble office furniture.
(b) Performance standard: Contractor shall dismantle, relocate to and/or re-assemble office furniture at designated areas. The contractor will receive no less than 8 hours advance notice to complete this task. No more than one late completion per month.
(c) Estimated work load per year: 20 times per year.
C.2.6 Additional Services and Performance Standards C.2.6.1 The Contractor shall provide Additional Services when requested by the Contracting Officer through a written task order, on an indefinite quantity basis. Work performed without such prior approval will be performed at the Contractor's risk and may be at no cost to the Government. Additional Services delivered shall be in addition to the Standard Services when they occur outside normal working hours, and shall be priced at the unit price established in the contract. The tasks to be accomplished shall be additional quantities of the same or similar tasks described above.
C.2.6.2 Control of Overtime. The Contractor shall plan individual work schedules that do not exceed 40 hours per week so that no individual works overtime as a part of the standard services requirement. If extra services are specifically ordered and confirmed in writing by the COR which results in overtime, payment for the overtime shall be at the rates for the unit price established in the contract. Monthly billings by the Contractor shall include details of any overtime so ordered by the Government.
C.2.7 Workload estimates:
Estimated workloads are described above in sections C.2.1 to C.2.6 in accordance with specific work tasks. Current estimates of inventory are provided here, according to residential or office use.
C.2.7.1 Residential: There are currently 150 Embassy residential units, concentrated at Yongsan South Post Residential Area. In addition, there are currently approximately 50 leased apartments in high-rise buildings, concentrated mostly in the Yongsan neighborhood. The CMR is located in downtown Seoul (See Section J, Exhibit A). From time to time, short-term and long-term leased houses may be added or removed from the housing inventory. The current inventory of residential appliances and equipment, furniture and furnishings residing at all residential units is as follows:
(a) Household Furniture & Furnishings 15,000 items
(b) Household Appliances & Equipment 3,000 items C.2.7.2 Office: The Chancery building is located in down town Seoul. Several U.S. Government agencies are also located in the Leema Building (146-1 Soosong-dong, Chongno-gu, Seoul, Korea) behind the Embassy Chancery. The U.S. Embassy also maintains and operates auxiliary services on the Embassy Annex, other buildings on Yongsan Garrison, and at other designated locations. The current inventory of office equipment, furniture, and items of personal property contained in all US Embassy office complexes is as follows:
(a) Office Furniture
2,500 Items
(b) Office Equipment
3,000 Items
(c) Other Equipment
500 Items
(d) Office Supplies & Custodial supplies 5,500 Boxes
(46cm x 30.5cm x 25.5cm H) C.2.7.3 Summer Peak Season: Many of the required services under this contract are concentrated during a “peak summer season.” During this peak season, we anticipate a greater frequency of make-ready services (C.2.2), welcome kit deliveries (C.2.1.2(b)), disposal sale (C.2.1.4(c)), airport logistics services (C.2.4), and VIP visit support requirements (C.2.3.6). During the peak season (June 01 – October 30), the estimated maximum workload is the following:
(a) Make-ready services 12 per week
(b) Welcome kit deliveries
12 per week
(c) Laundry and Ironing Services
5 sets per week
(d) Airport logistics services
3 per week
(e) VIP visit support
2 per week
C.2.8 Government Furnished Vehicles:
The USG will provide the Contractor with three Embassy-owned vehicles (two box trucks and a sports van) and two forklifts as listed in Exhibit C for the purpose of performing the work described in this contract. The USG will conduct all necessary maintenance on the vehicles, supply all motor fuel and standard maintenance supplies, and provide standard automobile insurance coverage. In addition to three Embassy-owned vehicles, the Contractor may use their own vehicles to perform work if necessary. Contractor-furnished vehicles might be necessary to meet the Standard Service requirements of this contract, especially during peak times. Contractor-furnished vehicles that are needed for Standard Service must be included in the contractor’s fixed price.
The Contractor shall be responsible for following all US Embassy motor pool regulations and procedures, to include keeping a daily trip log, keeping the vehicles clean, and safeguarding the vehicles from theft, vandalism, or any other form of damage.
Contractor personnel designated to drive Government provided vehicles must have valid driver’s licenses for the class of vehicle including forklift, a safe driving record, defined as having no traffic violations or accidents in the past 3 years, and medical examination per the Embassy’s motor vehicle regulations. Contractor personnel designated to the box truck should have at least one year drive experience with the same class of vehicle. Three drivers and two backup drivers are required. All drivers are also required to adhere to all relevant polices regarding motor vehicle use and safety.
All the drivers are required to participate in the mandatory SMITH safety driving training as is administered to all Embassy drivers. The training is to be renewed every two years.
C.3 Management and Supervision.
C.3.1 Contractor Management.
C.3.1.1
Supervision: The Contractor shall designate a project manager who shall be responsible for on-site supervision of the Contractor’s workforce at all times. The project manager shall be the focal point for the contractor and shall be the point of contact with the U.S. Government personnel. The project manager shall have sufficient English language skill to be able to communicate with members of the U.S. Government staff and sufficient Korean language skill to communicate with the Contractor’s workforce. The project manager shall have a minimum of three years of experience in supervision of warehouse support services.
C.3.1.2
The Contractor shall maintain schedules. The schedules shall take into consideration the hours that the staff can effectively perform their services without placing a burden on the security personnel of the Post. For those items other than routine daily services, the Contractor shall provide the COR with a detailed plan of the personnel to be used and the time frame to perform the service.
C.3.1.3
The Contractor shall be responsible for quality control. The Contractor shall perform inspection visits to the work site on a regular basis. The Contractor shall coordinate these visits with the COR. These visits shall be surprise inspections to those working on the contract.
C.3.1.4
The Contractor shall control overtime through efficient use of the work force. Individual work schedules shall not exceed 40 hours per week to preclude overtime being part of the standard services provided under the contract. Overtime may be necessary under Additional Services.
SECTION E - INSPECTION AND ACCEPTANCE
E.1
52.252‑2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .