This document is a Scope of Work (SOW) for the replacement and conversion of the boiler system at the U.S. Consulate General in Marseille, France. The key details are:
The project involves replacing the existing oil-fired boiler with two new condensing gas boilers, renovating the boiler room equipment, and updating the hydraulic distribution system. The work must be completed on an occupied and secured site, with the contractor responsible for providing all labor, materials, and equipment necessary. The contractor must submit an execution dossier for approval, adhere to a project schedule, and conduct testing and commissioning prior to acceptance. The contract will be a fixed-price agreement, and the contractor must provide a one-year maintenance period after acceptance. The solicitation is being issued by the U.S. Embassy Paris on behalf of the Department of State, and responses must be submitted electronically.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ 19FR6324Q0050 final.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT #3
SPECIFICATIONS ‐ SCOPE OF
WORK / RFQ#19FR6324Q0050
REPLACEMENT OF FURNACE AND BOILER CONVERSION
CONSULATE GENERAL ‐ MARSEILLE
ATTACHMENT #3 SPECIFICATIONS ‐ SCOPE OF WORK / RFQ#19FR6324Q0050 REPLACEMENT OF FURNACE AND
BOILER CONVERSION at Consulate General in MARSEILLE 1
Contents
1. GENERAL INFORMATION
1.1. INTRODUCTION
1.2. SCOPE OF WORK
1.3. LIST OF PROVIDED DOCUMENTS
1.4. SITE ACCESS
1.5. SITE ASSESSMENT
1.6. STANDARDS AND REGULATIONS
1.7. SAFETY OF THIRD PARTIES
1.8. SCHEDULE
1.8.1. Within the solicita on offer
1.8.2. During the service provision
1.9. SUBCONTRACTOR DECLARATION
1.10. EXECUTION AND CONSTRUCTION DOCUMENTS
1.11. VALIDATION AND APPROVAL PROCEDURES ARE AS FOLLOWS:
1.12. PROGRESS OF THE WORKSITE
1.13. MODIFICATION OF CONTRACTUAL PROVISIONS
1.14. FIRMNESS OF PRICE
1.15. AS‐BUILT DOCUMENTATION (D.O.E)
1.16. ACCEPTANCE
1.17. TESTS
1.17.1. Leak Tests
1.17.2. Temperature Rise Tests
1.17.3. Regula on Tests
1.18. COMMISSIONING
1.19. WORKS AND SUPPLIES AT THE EXPENSE OF THE CONTRACTOR
1.20. PROTECTION AND CLEANING OF STRUCTURES
1.20.1. Protec on of Structures
1.20.2. Cleaning
1.21. TRAINING OF PERSONNEL
BOILER CONVERSION at Consulate General in MARSEILLE 2
1.22. LABELING AND IDENTIFICATION
1.23. QUALIFICATION
1.24. NORMS AND REGULATIONS
1.25. ENERGY SAVINGS CERTIFICATE (CERTIFICAT D’ECONOMIE D’ENERGIE)
1.26. EXTENDED MAINTENANCE
1.27. HANDLING OF EQUIPMENT AND ROAD BLOCKING
1.28. SITE FACILITIES
2. CALCULATION BASIS
2.1. SITE CONDITIONS
2.2. INDOOR CONDITIONS
2.3. DESIGN ASSUMPTIONS AND POWER BALANCE
3. GENERAL TECHNICAL SPECIFICATIONS
3.1. CHOICE OF MATERIALS AND PRODUCTS
3.1.1. General informa on
3.1.2. Equipment Selec on
3.1.3. Corrosion Protec on:
3.2. ACOUSTIC REQUIREMENTS
3.3. PIPES
3.3.1. Steel Pipes
3.3.2. Copper Pipework
3.3.3. Mul layer Pipes
3.3.4. Other Pipework
3.4. VALVES
3.4.1. General
3.4.2. Use of Faucets
3.4.3. Strainer Filters
3.4.4. Non‐return valves
3.4.5. Controllable non‐return valve of EA type
3.5. CONTROL DEVICES
3.5.1. Thermometers
3.5.2. Pressure Gauges
BOILER CONVERSION at Consulate General in MARSEILLE 3
3.5.3. Drains
3.5.4. Air Vents
3.6. PIPE INSULATION AND ACCESSORIES
3.6.1. General
3.6.2. Hot water pipelines inside buildings or in technical rooms:
3.6.3. Hot water pipelines outside (in trenches, exposed, etc.):
3.6.4. Special protec on:
3.6.5. Insula on of accessories:
3.7. ELECTRIC PUMP GROUPS:
3.8. MARKING ‐ CONVENTIONAL COLORS
3.8.1. Device Labeling
3.8.2. Labeling of Hydraulic & Air Ducts
3.8.3. Valve Labeling
3.9. ELECTRICAL EQUIPMENT
3.9.1. Electrical Cabinets
3.9.2. Linking Pipework
3.9.3. Electric Motors
3.9.4. Grounding
3.10. CONTROL
3.10.1. Sensors
3.10.2. Regula on Valves
3.10.3. Controllers, Automa on
3.11. TESTING ‐ ACCEPTANCE ‐ WARRANTIES
3.11.1. Func oning a esta ons from the QAC
3.11.2. Technical Inspec on
3.11.3. Controls ‐ Self‐Controls
3.11.4. Consuel
3.11.5. Gas Compliance Cer ficates
3.11.6. Compliance Check
3.11.7. Circula on and Expansion Tests
3.11.8. Func onal and Power Tests: Hea ng
BOILER CONVERSION at Consulate General in MARSEILLE 4
3.11.9. Energy for Tests
3.11.10. Hea ng during the Construc on Period
3.11.11. Acous c Tests
4. DESCRIPTION OF HEATING WORKS
4.4.2. Exhaust of Combus on Gases
4.4.3. Boiler Room Ven la on ‐ Firefighter Duct
4.4.4. City Water Supply ‐ Hea ng System Filling Network
4.4.5. Water So ener
4.4.6. Air Separator
4.4.7. Expansion
4.4.8. Hydraulic Safety
4.4.9. Water Shortage Safety
4.4.11. Balancing
4.5. NETWORK DEPARTURES
4.5.1. Principle
4.5.2. Circula on Pumps for Networks
4.6. INTERNAL BUILDING NETWORKS
4.6.1. Pipework
4.6.2. Insula on
4.6.3. Draining, Purging, and Filters
4.6.4. Isola on and Adjustment
4.7. REGULATION ‐ PROGRAMMING ‐ DISPLAY
4.7.1. Principles
4.7.2. Equipment in the boiler room:
4.8. ELECTRICITY
4.8.1. General informa on
4.8.2. Electrical cabinets
4.8.3. Electrical Connec ons
4.8.4. Switching Elements Outside the Cabinet
4.8.5. Ligh ng
4.9. EXISTING DIESEL TANK REMOVAL
BOILER CONVERSION at Consulate General in MARSEILLE 5
4.10. TESTING ‐ ACCEPTANCE ‐ AS‐BUILT DOCUMENTATION
BOILER CONVERSION at Consulate General in MARSEILLE 6
1. GENERAL INFORMATION
1.1. INTRODUCTION
As part of its asset management and maintenance efforts, the U.S Government is solici ng proposals for the conversion and replacement of the boiler at the Consulate General of the United States of America in
Marseille. This project is part of a broader ini a ve aimed at enhancing thermal condi ons and preserving the func onal and modern characteris cs of the facility, while ensuring op mal comfort for users.
This Scope of work (SOW) outlined herein aims to specify the requirements and work associated with replacing the consulate's oil hea ng system with gas produc on system, as well as ensuring compliance of the heat produc on installa on. This is to guarantee func onal and consistent hea ng produc on and distribu on throughout the facility.
The service entails mul ple stages, as outlined below, and must strictly adhere to the Scope of Work, specifica ons, and general contract. This project necessitates the engagement of an experienced contractor.
The contractor is responsible for furnishing all labor, materials, tools, equipment, supervision, and any other necessary items to carry out the work in accordance with the defines scope of work and specifica ons.
Contractors are strongly encouraged to conduct on‐site visits to verify the exis ng site condi ons before developing their proposals. This firsthand assessment is crucial for ensuring accuracy and completeness in the proposal development process.
1.2. SCOPE OF WORK
This SOW includes the following works:
Emptying, neutraliza on and removal of the oil tank and exis ng boiler
Replacement of the oil boiler in the boiler room with 2 condensing gas boilers
Renova on of boiler room equipment (expansion, cold water supply...)
Replacement of the hydraulic distribu on system in the boiler room
All electrical connec ons
Tes ng, adjustment, balancing, and controls
Restora on of the exis ng fuel oil tank's room to a usable condi on
Prepara on of as‐built documenta on
BOILER CONVERSION at Consulate General in MARSEILLE 7
The works will be carried out on an occupied and secured site. The personnel involved will not be affected by the maintenance of hea ng opera on during their interven on but should consider the security constraints of the Consulate General of Marseille in their planning and daily opera on.
1.3. LIST OF PROVIDED DOCUMENTS
The documents provided during this consulta on are:
This Scope of work (SOW)
Bill of Quan es and Lump Sum Prices
Graphical element: Hydraulic principal diagram of the project
1.4. SITE ACCESS
The Consulate General of the United States of America in Marseille is situated at 12 Bd Paul Peytral, within the 6th arrondissement of Marseille.
The basement of the building accommodates technical installa ons including the oil boiler to be replaced.
The project’s area encompasses two adjacent rooms, with one housing the oil boiler and the other accommoda ng the oil tank.
Access to the consulate site is subject to regula on, necessita ng adherence to the following s pula ons by the contrac ng company and any poten al subcontractors:
The contractor is required to submit access requests to the project’s Contract Officer
Representa ve (COR) to secure the requisite authoriza ons for personnel and equipment access to the work sites, for preliminary visits, and throughout the dura on of the project.
Access request must be submi ed a minimum of 48 hours prior to the intended access date.
Access authoriza ons remain valid only for the dura on of the interven on and may be revoked by the competent authority without prior no ce.
Only individuals affiliated with the construc on sites and possessing authoriza on are permi ed entry.
The contractor and their personnel must u lize the most direct access routes, confine themselves to designated loca ons and premises allocated for work execu on, and refrain from entering or traversing other areas of the site.
Escort services will be provided to the contractor and their personnel throughout the dura on of the project.
BOILER CONVERSION at Consulate General in MARSEILLE 8
1.5. SITE ASSESSMENT
The contractor is deemed to have visited the premises (exis ng buildings and surroundings) and to have adequately assessed issues related to phasing, temporary installa ons, execu on, procurement, handling, and site installa on.
Failure to acknowledge these issues during the project cannot be used to jus fy delays or addi onal expenses.
1.6. STANDARDS AND REGULATIONS
The materials, components, and tradi onal assemblies selected must adhere to all current French and
European regulatory standards, as well as the specifica ons outlined in unified technical documents, specifica ons, and guides.
Equipment and appliances must bear the N.F. or CE label. The quali es, characteris cs, types, tes ng methods, marking, control, and acceptance of materials and prefabricated products, as well as the implementa on methods, will conform to approved standards legally enforced at the me of contract signing.
It is presumed that the contractor is acquainted with these standards. In instances where standards are absent, revoked, or jus fiably exempted, par cularly due to technical advancements, the contractor must seek approval from the Project’s Contrac ng Officer Representa ve (COR) for their own albums and catalogs, or those of their suppliers.
Each company, within its respec ve domain, is obligated to adhere to the following standards pertaining to both material quality and implementa on. These standards, considered minimum requirements by the companies, will always be subject to the provisions of this document. If the document mandates higher quality or more me culous implementa on, the la er shall take precedence.
1.7. SAFETY OF THIRD PARTIES
Throughout the construc on period, companies are required to implement all necessary measures to prevent any damage to exis ng and adjacent premises and structures. In the event of damage, companies will be held solely responsible and must assume the resul ng consequences.
BOILER CONVERSION at Consulate General in MARSEILLE 9
Likewise, every effort must be made to uphold the living and tranquility condi ons of consulate personnel by minimizing disturbances inherent in the construc on site’s progress. This includes the u liza on of soundproof equipment, adjustments to working hours, and any other measures deemed necessary.
1.8. SCHEDULE
1.8.1. Within the solicita on offer.
For the bid submission, the company must include a comprehensive work schedule detailing the following:
Deadlines for studies.
Delivery deadlines for various materials.
Implementa on deadlines for installa on works.
Tes ng schedules.
Addi onally, the bid should specify the number of hours allocated for the following ac vi es:
Conduc ng studies.
Site supervision, including par cipa on in mee ngs and overall site management.
Personnel assigned to execute the works.
Test implementa on.
Comple on of the as‐built documenta on.
1.8.2. During the service provision
During the provision of services, the following procedures will be observed:
A schedule for document submission will be dra ed by the awarded company and disseminated to all project stakeholders within 10 days following the no fica on date.
A preliminary schedule outlining precise work phases will be submi ed no later than 15 days a er the contract no fica on date for valida on by the project’s Contrac ng Officer Representa ve
(COR). The company must adhere to this schedule as a minimum requirement. This schedule will be comprehensive and dated from either the owner's order execu on date or the contract no fica on date.
The contractor will liaise with other awarded companies, at their discre on, to ensure seamless integra on of their interven ons into the schedule.
BOILER CONVERSION at Consulate General in MARSEILLE 10
Upon commencement of the construc on site, an inventory will be conducted by the company and the establishment's representa ve. Any damages iden fied will be rec fied at the company's expense.
Delivery of materials and supplies to the site will be coordinated and planned. The company must no fy the establishment prior to deliveries and be present during them. It bears responsibility for materials and supplies on‐site during the construc on period and cannot seek compensa on for loss or the .
1.9. SUBCONTRACTOR DECLARATION
Companies are required to declare any subcontractors and comply with L.3 Qualifica ons of Offerors of the solicita on document when sub‐contrac ng all or a por on of the works under the contract. The acceptance of each subcontractor will be subject to approval as described in detail in L.3.(8) The Offeror
Subcontrac ng Plan.
1.10. EXECUTION AND CONSTRUCTION DOCUMENTS
During the prepara on period, the company is required to submit a comprehensive execu on dossier for approval by the project’s COR and the eventual technical controllers. This dossier must include, at a minimum, the following documents:
Shop drawings – including the Boiler‐room layout / coordina on sketch and showing new layout, piping, equipment loca ons & measurements.
EXE plans featuring all hydraulic networks drawn to scale, in two‐way, with labels indica ng powers, flows, diameters, etc., for each element.
Sec ons at specific points as requested by the Project’s COR or the Contrac ng Authority.
Schema c diagrams of the installa on, detailing powers, diameters, flows, temperatures, pressure drops, equipment references, etc. including the ven ng system’s details (Flue/ven ng and OA feed)
Electrical diagrams of cabinets and boxes.
All suppor ng calcula on notes.
Detailed technical specifica ons of the proposed equipment and products.
Start‐up process, flashing process, water treatment plan, etc.
Regula on diagram of the installa ons.
Any addi onal execu on plans not provided in the tender documents.
Moreover, the contractor must consider the following constraints in their offer (non‐exhaus ve list):
Comple on of all administra ve procedures.
Coordina on of all material deliveries with the owner.
BOILER CONVERSION at Consulate General in MARSEILLE 11
Prohibi on on storing materials outside the construc on site.
The works will be carried out on an occupied site, and all associated constraints must be duly considered.
1.11. VALIDATION AND APPROVAL PROCEDURES ARE AS FOLLOWS:
All documents produced by the contractor are subject to valida on by the Project’s Contrac ng Officer
Representa ve (COR).
Documents must be clearly legible, properly iden fied, and signed by their authors to ensure traceability.
Failure to adhere to these requirements will result in the rejec on of the respec ve documents.
The Project Management and the Contrac ng Authority hold full authority and decision‐making power to reject any proposed material or equipment that they determine does not meet the minimum characteris c defini ons required.
No company has the right to contest these decisions, especially on financial grounds. The company is obligated to comply with the selected choice and provide the materials or equipment specified within the scope of its contract.
However, if a specific brand or type is indicated without qualifiers such as "or similar," "or equivalent," etc., it implies the absence of corresponding models in other supplies or the Project Management's selec on of a par cular model or supply for aesthe c or technical reasons.
The company may propose equipment it considers "equivalent," but such proposals may be rejected for aesthe c or technical reasons.
1.12. PROGRESS OF THE WORKSITE
The progress of the worksite will adhere to the following guidelines:
Due to the works being conducted on an occupied site, the company must formulate a precise interven on schedule, delinea ng each phase. This schedule enables the occupants to an cipate any necessary adjustments in site circula on.
Special a en on must be given to monitoring cooling produc on, par cularly in the process area.
Proposed solu ons and scheduling details must be outlined in the bid.
The contractor is responsible for verifying the compa bility of equipment provided by the owner with the planned supplies.
BOILER CONVERSION at Consulate General in MARSEILLE 12
Any interven on not approved by the COR cannot proceed. In the event of observed inconveniences, the company will be held accountable for any resultant damages and will be obligated to provide necessary repairs.
1.13. MODIFICATION OF CONTRACTUAL PROVISIONS
The contractor is not authorized to unilaterally amend any contractual provisions without the wri en consent of the designated project COR.
Requests for modifica on must be submi ed in wri ng to the COR, accompanied by an economic assessment detailing the impact on the relevant work's cost.
Generally, modifica ons for the sake of execu on convenience should not exceed the cost of the originally planned work.
If the contractor iden fies errors, omissions, or inconsistencies, they are obligated to report them in wri ng to the project COR.
Upon acceptance of modifica ons, all exis ng documents, whether referenced or not, must be promptly amended at the contractor's expense and validated for compliance before implementa on.
In the absence of technical advice or specifica ons endorsed by an accredited body, companies responsible for execu ng these works must bear all associated costs, including fees charged by the repor ng organiza on and any tests requested by the Expert Commi ee and the CSTB. It is emphasized that the company must obtain a favorable assessment from the expert commission.
1.14. FIRMNESS OF PRICE
The SOW and series of plans provided in the tender documents outline the characteris cs and principles of the works to be executed for perfect comple on and finishing.
In cases of uncertainty, omissions, or errors in the aforemen oned documents, contractors are required to seek clarifica on from the project COR, and complete and supplement any missing informa on.
Accordingly, the price agreed upon in the commitment agreement corresponds to installa ons delivered in perfect working condi on.
It is explicitly stated that the lump‐sum price encompasses all necessary works for the proper and complete execu on of the project, ensuring that its comple on, as per the condi ons specified in the plans and SOW, does not incur addi onal costs.
BOILER CONVERSION at Consulate General in MARSEILLE 13
Any works essen al for the en re and perfect comple on of the project, within the framework of the subscribed plans and SOW, will not be deemed as "addi onal works." Hence, they will not result in work orders or accounts. Consequently, the contractor cannot claim addi onal payment based on any incompleteness, contradic ons, or obvious omissions found in the designa ons outlined in the plans and
SOW.
1.15. AS‐BUILT DOCUMENTATION (D.O.E)
Upon comple on of the works and prior to acceptance, the company is required to submit an as‐built documenta on, indexed as "D.O.E," containing all modifica ons implemented during the construc on phase. This documenta on is essen al for future interven ons by the owner.
The minimum contents of this dossier include:
All updated plans, encompassing networks and essen al informa on for comprehending the installa on.
As‐builts
Calcula on notes.
Fluid and electrical schema c diagrams.
Documenta on and technical specifica ons for all installed equipment.
Regula on scheme for the equipment.
Opera on instruc ons for the installa on.
Comprehensive opera ng manual for the installa on, accessible to non‐specialized personnel, detailing startup, and shutdown procedures.
Commissioning reports, measurements, and readings conducted by the company and equipment manufacturers.
O&M ‐ Maintenance and servicing instruc ons for various equipment, including a detailed interven on schedule (D.I.U.O).
Safety opera ng instruc ons.
Network component se ng parameters.
DESP dossier comprising an inspec on plan and ini al boiler inspec on report.
Warran es, Spare Parts, training documenta on, close out
A esta on from personnel responsible for opera ng the equipment.
1 year maintenance contract and schedule
A copy of the installa on diagram will be laminated and displayed on the wall of the boiler room.
The company will compile a comprehensive dossier for valida on by the COR. Upon valida on, three copies will be produced:
BOILER CONVERSION at Consulate General in MARSEILLE 14
One for the Owner.
One for the technical controller.
One for the engineering firm.
The company will provide a digital dossier containing all documents in their na ve format.
1.16. ACCEPTANCE
Acceptance will be determined by the project COR once the tests outlined in sec on 1.17 have been conducted and completed.
Verifica on will ensure that the installa on is fully completed and that all components adhere to the tender documents and subsequent work orders.
In the event of defects, the Contractor must rec fy them by replacing any faulty parts, covering all associated labor costs, at their own expense.
Acceptance will be documented in a report, along with any reserva ons noted during the inspec on conducted for this purpose, in the presence of the various contrac ng par es.
Reserva ons may be li ed provided that:
No issues persist regarding the proper func oning of the installa ons.
The installa ons and their characteris cs remain consistent and comply with those recorded during measurements and tests.
Acceptance will be granted when all works are deemed completed, conforming to the execu on plans, in good working order, and mee ng the required standards.
1.17. TESTS
Upon comple on of the works, the company will conduct tests, which must be documented with respec ve reports prepared in accordance with the following specifica ons.
The company is required to no fy the project COR and the technical controller of the date on which these tests will be conducted.
Opera on cer ficates will serve as acceptance tests unless an unfavorable opinion is expressed. In such cases, addi onal tests deemed necessary may be conducted, upon the recommenda on of the project
COR and the technical controller.
These verifica ons encompass:
BOILER CONVERSION at Consulate General in MARSEILLE 15
The quality of the equipment and apparatus
The contractor must ensure compliance with the regula ons and specifica ons outlined in this document.
All necessary equipment for thermal, air, hydraulic, acous c, and electrical tests must be provided by the contractor.
The tests will encompass:
Leak tests
Temperature rise tests
Tests of safety and alarm devices
Tests of mechanical, electromagne c, and electrical devices
Opera on tests of the en re installa on
1.17.1. Leak Tests
These tests will occur on a day chosen by the Contractor. The networks will be pressurized with water for
24 hours. Upon successful comple on of the tests, the network will be drained, flushed, and refilled with water. A cer ficate of opera on will be issued by the contractor confirming the proper sealing of the installa on.
1.17.2. Temperature Rise Tests
These tests will be conducted at the contractor's request, on a date specified by the project COR. The objec ve of these tests is to demonstrate the proper opera on of the installa on. External weather condi ons will be necessary to validate these tests. If condi ons do not permit valida on, the installa on will be accepted pending test valida on during the required period.
1.17.3. Regula on Tests
These tests will be carried out at the contractor's request, on a date determined by the project COR. They are intended to verify the proper opera on of the equipment's regula on.
1.18. COMMISSIONING
In general, commissioning will be conducted by the manufacturer in the presence of the installer.
BOILER CONVERSION at Consulate General in MARSEILLE 16
The company must inform the project management of the scheduled date for these commissioning ac vi es.
1.19. WORKS AND SUPPLIES AT THE EXPENSE OF THE CONTRACTOR
The SOW provides as accurately as possible the nature, quality, and characteris cs of the works, as well as their loca ons and posi ons.
However, it should be noted that the documents in the tender dossier are not exhaus ve, and contractors cannot claim addi onal payment for essen al works not described or defined in the SOW.
Therefore, in addi on to the works described within this normal scope, the following services must be provided:
Supply, transporta on, and implementa on of all materials necessary for the realiza on of the installa on proposed in the technical plans.
Provision, establishment, and removal of all machinery and scaffolding necessary for the comple on of the works.
Comple on of all installa ons in perfect working order in accordance with the schedule.
Procedures with the Control Organiza on for conformity cer ficates, including associated costs.
Provision of all documents facilita ng the progress of the works within the deadlines set for their implementa on.
Consequences of over me, night hours, etc., necessary to meet the execu on deadlines.
Condensate drainage systems.
Connec on to fluids (refrigerants, drainage, etc.).
Electrical connec ons.
The removal of the diesel from the exis ng tank, as well as the tank itself, and the restora on of that room to make it useable
The companies will assume all consequences of administra ve regula ons, par cularly those stemming from current or future policy regula ons, which pertain specifically to the closure of the site, site surveillance, and traffic safety.
They will install all necessary warning signs and undertake all necessary measures to inform users of the poten al dangers posed in the vicinity of the construc on site due to their ac vi es.
1.20. PROTECTION AND CLEANING OF STRUCTURES
1.20.1. Protec on of Structures
BOILER CONVERSION at Consulate General in MARSEILLE 17
The contractor is responsible for safeguarding its structures using any means it deems appropriate, including protec on against adverse weather condi ons, damage from falling objects, the , etc. It is also accountable for maintaining these protec ve measures throughout the construc on period. The company must replace any damaged or missing materials at its own expense during the construc on period. This replacement may occur upon commissioning of the installa on.
1.20.2. Site Cleaning
The contractor must manage waste removal as construc on progresses and regularly clean the work areas. The contractor must conduct cleaning of all structures in phases before the acceptance of the works. The company awarded the contract must:
Clean all structures 24 hours prior to Provisional Acceptance (O.P.R.).
Clean all structures 24 hours prior to delivery.
The contractor is responsible for ensuring the thoroughness of these cleanings. If the Master of Works deems the cleaning unsa sfactory, they reserve the right to have it redone by a third‐party company at the expense of the company awarded the contract.
1.21. TRAINING OF PERSONNEL
Prior to acceptance, the contractor will conduct training sessions for personnel designated by the COR on the en re installa on. This training will be led by a qualified technicians (manufacturer’s representa ve or equivalent for the boiler and the contractor for ancillary systems use, opera ons and maintenance) and will have a total dura on of 1 day. Upon request from the COR, this day may be divided into 2 half‐days.
The dates for this training must be agreed upon by the Master of Works and the Contractor.
At the conclusion of this training, the COR will receive a support document summarizing the main tasks related to opera ng and maintaining the technical installa ons. Addi onally, a training cer ficate will be issued.
Note: Agenda and related material are to be supplied in advance by the contractor.
1.22. LABELING AND IDENTIFICATION
All networks will be iden fied by a color band symbolizing the nature of the fluid and the direc on of circula on. Conven onal colors will be selected in accordance with the AFNOR NF X 08.100 standard.
BOILER CONVERSION at Consulate General in MARSEILLE 18
Equipment will be labeled with engraved labels indica ng its func on. All symbols will adhere to the relevant standards and will be included in the plans, diagrams, and maintenance manuals.
1.23. QUALIFICATION
All employed personnel must possess the necessary qualifica ons and authoriza ons for the tasks outlined in this contract. Addi onally, the company itself must hold an official qualifica on for the works it commits to carry out.
1.24. NORMS AND REGULATIONS
The holder of this contract is obligated to adhere to all standards, regulatory texts, and calcula on rules per nent to their work, effec ve as of the date of signing this contract. This includes compliance with the following French standards:
N.F.P 49.115: Steel tubes ‐ Threadable seamless tubes (dimensions ‐ technical delivery condi ons)
N.F.P 49.111: Steel tubes ‐ Seamless tubes with smooth ends for general‐purpose medium‐ pressure applica ons
N.F.P 49.145: Steel tubes ‐ Threadable welded tubes
N.F.P 41.203: Spacing of pipeline supports
N.F.X 08.100: Conven onal color for piping
Direc ve 2006/42/EC on machinery
Direc ve 97/23/EC on pressure equipment
NFC 15.100: Low‐voltage installa ons
Addi onally, compliance with the following regula ons is mandatory:
Ministerial and inter‐ministerial orders
CSTB (Scien fic and Technical Center for Building) requirements
Ordinance No. 70.15134 of 16.02.70: Fixing safety measures to be observed during welding and cu ng opera ons by thermal apparatus
Materials or equipment used must be CSTB approved or, in absence of such approval, must be endorsed in wri ng by a Control Office
Departmental sanitary regula ons
Rules of the Trade
Furthermore, all other regula ons applicable at the me of acceptance of the works must be strictly followed.
BOILER CONVERSION at Consulate General in MARSEILLE 19
1.25. ENERGY SAVINGS CERTIFICATE (CERTIFICAT D’ECONOMIE D’ENERGIE)
As part of the works specified in this document, Energy Savings Cer ficates (Cer ficats d’Economie d’Energie, CEE) can be obtained from the relevant stakeholders.
These CEEs will be managed by the contractor. In their bid, the contractor must provide:
The relevant CEE forms.
The total number of cumula ve energy savings in kilowa ‐hours (kWh cumac) considered.
The price per kilowa ‐hour (kWh cumac) considered.
1.26. EXTENDED MAINTENANCE
The contractor is required to include one year of maintenance in their offer, which will be part of this contract. The maintenance period will commence from the date of acceptance.
1.27. HANDLING OF EQUIPMENT AND ROAD BLOCKING
All works under this contract are situated within the consulate premises. However, before any interven on affec ng the road in front of the consulate, the contractor must submit an interven on plan and a schedule for valida on by the Project Management and the Client.
1.28. SITE FACILITIES
The contractor must coordinate with the consulate regarding the feasibility of establishing a site facility for the project's dura on. Due to the secure nature of the site, it's possible that no interior space within the building can be allocated.
Materials and equipment must be stored directly in the basement of the building in a designated and protected area, to be defined in collabora on with the COR. The contractor will provide a space of suitable size and specify it in their bid.
The contractor will bear sole responsibility for the equipment stored onsite, and it is incumbent upon them to provide the necessary measures to ensure its security.
2. CALCULATION BASIS
BOILER CONVERSION at Consulate General in MARSEILLE 20
2.1. SITE CONDITIONS
Winter
City Marseille
Clima c zone H3
Al tude From 0 to 200m
Outdoor temperature ‐5°C
2.2. INDOOR CONDITIONS
Winter
Indoor temperature 19 °C
Humidity Uncontrolled
2.3. DESIGN ASSUMPTIONS AND POWER BALANCE
The power balance of the premises is as follows:
Hea ng
Es mated needs 140 kW*
*Indica ve data, to be confirmed by studies
(Overcapacity of 10% included)
3. GENERAL TECHNICAL SPECIFICATIONS
BOILER CONVERSION at Consulate General in MARSEILLE 21
3.1. CHOICE OF MATERIALS AND PRODUCTS
3.1.1. General informa on
All materials u lized must adhere to French standards (AFNOR) and possess either the "CE marking" or
"NF marking" if they lack a European standard or a valid technical opinion. The use of materials must comply with prevailing regula ons and standards. If, for any reason, a material or construc on process isn't covered by a standard or technical opinion, the Project COR, guided by their Control Office's advice, holds sole authority to determine its use. In all instances, materials employed must be of top quality.
The selec on of equipment and materials must consider:
The nature of the distributed fluid and its seasonal varia ons, The environnement (terrain type, premises traversed, etc.), Service and opera onal condi ons (pressure, temperature, etc.).
Prior to any procurement and implementa on, the contractor must seek prior approval from the Project
COR for:
The list of materials they intend to u lize, Detailed informa on regarding the origin, physical, chemical, and mechanical proper es of each material, validated by a laboratory, enabling verifica on of their conformity to standards.
To mi gate maintenance and upkeep issues, special a en on will be paid to the geographical origin when selec ng materials or equipment.
All materials and equipment used must comply with various decrees and orders concerning the classifica on of materials based on their fire behavior. Their selec on will also consider the fire hazard associated with the elements or parts of the construc on in which they are u lized.
Note: The use of asbestos‐based materials is strictly prohibited. It is emphasized explicitly that no excep ons will be granted on the construc on site.
If the contractor proposes materials from brands other than those men oned as examples in the
"Descrip on of Works" chapter, these alterna ve materials must match in quality, technical characteris cs, aesthe cs, and dimensions, and must be approved by the Project COR.
If the Project COR do not agree to the proposed alterna ve materials, the contractor shall:
Install the equipment and materials specified in the original project.
At their own expense, modify any necessary works resul ng from modifica ons made by the contractor.
The installa ons must be delivered with all specified accessories, even if they are not explicitly listed in the es mate or in the schedule. The installa ons must comply with all regula ons in force at the date of the
BOILER CONVERSION at Consulate General in MARSEILLE 22 offer. If new regula ons are published between the dates of the offer and execu on, the contractor must immediately provide cost es mates and propose implementa on of the new provisions according to the modali es of their applica on.
3.1.2. Equipment Selec on
The characteris cs to be achieved must adhere to the tolerances established by regula ons, standards, professional guidelines, or manufacturers.
The opera on of the installa on must remain consistent under regula on control and must simultaneously maintain, within the limits of thermal loads compa ble with equipment capaci es, temperatures within plus or minus one degree of the set value, and flow rates within plus or minus 5%.
These tolerances apply unless addi onal specifica ons are provided elsewhere in this document.
It is clarified that the admi ed tolerances apply solely to defining the stability of the installa on's opera on and must not be used in calcula ng minimum characteris cs.
The calorific powers represent useful powers that must be effec vely supplied by each heat exchanger to the treated fluid.
The losses specific to each heat exchanger, not transmi ed to the treated fluid, must also be considered addi onally for defining the net power and determining the device.
The same principles apply to losses due to transmission in pipelines or ducts, as well as to air leaks through the walls of ducts and elements of the installa on.
The installed equipment must strictly adhere to the minimum specified characteris cs, as well as to the brands, types, and characteris cs of the defined equipment.
3.1.3. Corrosion Protec on:
All components of the installa on made of non‐galvanized ferrous metals, including clamps, ducts, hea ng bodies, and various casings, must undergo an ‐rust treatment either at the manufacturer's premises or on‐site before or immediately a er installa on (two coats of an ‐rust paint), regardless of whether they are insulated or not.
Elements of the installa on placed outside the building will be designed and fixed for permanent opera on outdoors and must comply with the latest edi on of the rules defining the effects of snow and wind on construc ons.
BOILER CONVERSION at Consulate General in MARSEILLE 23
They will be made of stainless materials such as stainless steel, zinc, etc., or will have received effec ve metallurgical treatment against corrosion. The fastening elements for these various parts ‐ screws, bolts, nuts, etc. ‐ must also allow for disassembly for possible repair.
3.2. ACOUSTIC REQUIREMENTS
The installa ons must be designed to limit noise levels generated by equipment, especially burners, fans, and pumps.
Before commencing any work, the installer must provide the acous c characteris cs of all noise‐ genera ng equipment and specify the measures they intend to take to achieve the sound levels required by regula ons and in the "Calcula on Basis" sec on within the following limits:
The indicated sound levels apply only to the equipment of this lot; therefore, measurements will be taken when the area is unoccupied and equipment not pertaining to this lot is not in opera on.
The increase in sound intensity produced by equipment of this lot must not exceed the minimum value of the ambient noise by more than:
o 5 dB (A): during the day (7 am to 10 pm) o 3 dB(A): during the night (10 pm to 7 am)
Addi onally, the following provisions must be taken into account:
Technical equipment capable of genera ng and transmi ng vibra ons will be placed on floa ng mounts.
Bases, seats, or support frames will be isolated from the building structure using an ‐vibra on mounts.
Pipes and ducts will be decoupled from structures, especially when passing through walls and floors (using sleeves). Those prone to transmi ng vibra ons will be equipped with elas c sleeves and fixed using an ‐vibra on clamps or special elas c supports.
Fixing clamps will be of the an ‐vibra on type.
The selected plumbing fixtures must have received CSTB (Scien fic and Technical Centre for
Building) classifica on from an acous c perspec ve.
Furthermore, all measures will be taken to eliminate the transmission of airborne noise between rooms through pipes and ducts in par cular. If material selec on alone is insufficient to meet these condi ons, the selected equipment must be equipped with acous c silencers or soundproofing devices.
The assessment of ambient noise levels must be conducted in cases where specific issues are expected to arise on‐site. No addi onal costs should result from this as the company will have examined this issue before submi ng its offer.
BOILER CONVERSION at Consulate General in MARSEILLE 24
During implementa on, the company must provide all informa on and detailed calcula ons demonstra ng that a enua on elements have been calculated to achieve the required condi ons. Any a enua on device must be selected to minimize pressure drop.
The company must have an acous c measuring device capable of octave band spectral analysis and, a er adjustments and commissioning of the ven la on installa ons, conduct a control campaign in all rooms.
These measurements will be recorded before the acceptance of the installa ons.
In case of issues, the company will rec fy the problems at its own expense.
3.3. PIPES
The routes of the pipes will be designed to preserve the aesthe cs of the rooms where they are visible.
All pipe routes and layouts will be subject to approval by the Project Management before implementa on.
All pipes, regardless of their type (fall pipes, main supplies, distribu on feeds, whether made of cast iron, steel, PVC, or copper), must be sufficiently spaced from the walls to allow for pain ng work around their perimeter and their removal and replacement without damage. All necessary precau ons will be taken at expansion joints to prevent deforma on or rupture of the pipes.
It is clarified that pipes passing through false ceilings or enclosed in ducts must have undergone all pressure tests before pain ng them and installing insula on.
The quality of these pipes must correspond to the specific requirements of their routes.
3.3.1. Steel Pipes
Quality:
For the transport of hot hea ng water or chilled water, the pipes used will belong to either:
the series known as "welded steel pipe, threadable" (formerly commonly referred to as tariffs 1 and 2) conforming to standard NF A 49.145 and NF EN 10255 W type L for diameters up to diam.
40/49 inclusive and for temperatures ranging from ‐10°C to 110°C.
the series known as "seamless steel pipe" (commonly referred to as tariff 10) conforming to standard NF A 49‐112 for any diameter and for temperatures ranging from ‐10°C to 200°C.
For the transport of gas, non‐buried pipes will belong to:
BOILER CONVERSION at Consulate General in MARSEILLE 25 the series known as "seamless steel pipe" conforming to standard NF A 49.115 (commonly referred to as tariff 3).
Implementa on Precau ons:
The pipes will be:
Installed with sufficient spacing for insula on removal, Non‐obstruc ve to doors and openings, Sloped sufficiently to allow for air purging and complete draining, Without sagging or reverse slope, With free expansion, either by layout or by expansion loops, without abnormal fa gue and noise, Designed for a good balance of circuits with water flow without noise or water hammer, Posi oned with aesthe c concern, parallel and plumb, whenever technical condi ons do not hinder it.
All high points will be equipped with isolable automa c air vents, supplemented with manual vents with capped valves brought to human height.
All low points will be equipped with capped drain valves.
Assembly:
Hot water for hea ng:
PN DN Assembly
< 10 bars < DN 50 By screw union fi ngs in cast iron or welding
< 10 bars > DN 50 By flanged connec ons welded or by welding
> 10 bars All DN By welded flanged connec ons or by welding
Each cut or sec on of pipe will be carefully deburred and chamfered before connec on. When two sec ons are welded end to end, the ends will be chamfered. Removable assemblies will preferably be made by flanged connec ons. Removable threaded assemblies will be below DN50 and made using tapered threaded connec ons (union fi ngs). The sealing of threaded connec ons will be done using hemp fiber with paste. Teflon tape will only be tolerated for the assembly of accessories other than piping elements, valves, pumps, and any component affec ng the transport network. Any threaded joint must be easily accessible. Flange assemblies will be made using flanges conforming to French standards and will be of the type with socket‐welded collars. The flanges must be of the tongue‐and‐groove type. Removable connec ons will be used on valves, on equipment such as coils, etc., and wherever components that may need to be inspected or replaced require removable fi ngs.
BOILER CONVERSION at Consulate General in MARSEILLE 26
Gas:
The type of fi ngs will be specified before interven on: mechanical or welding; the welding method will be specified. All work carried out on gas installa ons will be performed by personnel holding the appropriate qualifica on.
Cold water:
The pipes serving the makeup or filling of the hea ng systems and located downstream of the pressure reducing zone with controlled reduced pressure will be made of steel and will comply with the same execu on constraints as the hea ng network. Upstream, they will comply with the specifica ons of the
"Plumbing" lot.
Branch fi ngs:
Up to DN 40 and for temperatures < 110°C, the pipes may be bent.
Beyond DN 40 or temperatures > 110°C, special welding elbows conforming to standard NF A
49.186 will be used.
Types of supports:
There will be three types of supports:
Fixed point supports capable of withstanding lateral forces and able to ensure:
o Holding a collector in a neutral posi on capable of expanding on both sides of the support, o Immobiliza on of pipes subject to a ground effect (an vibra on sleeves);
Guide supports allowing the collector to expand while maintaining its lateral posi on. This type of support will be located in straight sec ons; it maintains alignment.
Bearing supports allowing the collector to move laterally and longitudinally while providing support.
These supports will be located near bends and will absorb deforma ons due to expansions caused by temperature varia ons of the transported fluid.
The supports will be painted with rust inhibitor (2 coats) and coated with two coats of glycerophthalic paint: safety yellow color.
Arrangement of supports:
BOILER CONVERSION at Consulate General in MARSEILLE 27
Nominal diameter Horizontal spacing Ver cal spacing
10 mm Every 1,00 m Every 1,50 m
12 to 15 mm Every 1,20 m Every 1,80 m
20 to 25 mm Every 1,80 m Every 2,50 m
32 to 100 Every 2,50 m Every 2,50 m
These spacings must be reduced:
Near elbows, Near devices such as valves.
All support devices must allow free expansion and con nuity of any thermal insula on while respec ng acous c criteria.
Insula ng rings will be placed between the tubes, supports, and clamps.
The MUPRO type fixing system will be accepted, with a two‐part screw clamp, welded nut, threaded rod, insula on shells in con nuity with the pipe insula on, with galvanized distribu on plate between the clamp and the insulator for guide supports.
Compensa on Devices:
The company must provide the necessary devices for the free expansion of the pipes (compensators, loops, guides, fixed points), without joint fa gue and noise.
Compensators should be avoided as much as possible. In all cases, loops and expansion bends should be preferred over compensators.
Compensators, in addi on to their proper func oning, must ensure perfect ghtness and can only be used for low‐temperature (< 110°C), low‐pressure (P < 4 bars) hot water. Beyond that, only loops and expansion bends will be used.
The company will be required to provide a wri en guarantee of the ghtness of the provided devices.
The shaping of the waves should not cause any cracks.
The Supervising Engineer reserves the right to subject the compensators to radiographic examina on.
Before installa on, the contractor will submit to the approval of the Supervising Engineer the selected compensa on devices as well as the layout plans and corresponding calcula ons.
Conduits:
BOILER CONVERSION at Consulate General in MARSEILLE 28
All pipes passing through walls, par ons, or floors must be protected by rigid plas c tube conduits of appropriate dimensions.
Through an expansion joint, the conduits must be separate on each side of the joint and have a sufficient sec on to allow for pipe movement perpendicular to their axis.
The conduits must not be destroyed or deformed by temperature, or the loads applied by the pipes.
The conduits must allow for the free expansion of the pipes either parallel or perpendicular. They must not be obstructed by plaster or cement. The conduits between rooms or between rooms and technical sha s must be acous cally insulated and must not allow air infiltra on or compromise the air permeability of the buildings. For this purpose, they must be durably packed with a material preven ng sound and air transmission.
Thus, at each passage through a floor or ceiling, the conduit will be filled with bituminous felt or a resilient foam strip and/or supplemented by injec on of single‐component, low‐expansion polyurethane foam. The openings or incorpora ons will be filled with concrete, resin, or cement mortar.
Wall or par on penetra ons, especially for entries into technical sha s, will be treated in the same manner.
Inside the wall penetra on, apply a plasto‐elas c acrylic sealant joint extruded on a toric or rectangular seal in closed‐cell expanded polyethylene foam.
On the outside of the wall penetra on, apply an extruded PU or silicone sealant joint on a toric or rectangular seal in closed‐cell expanded polyethylene foam.
In horizontal penetra ons, they are flush with the wall surface. In ver cal penetra ons, they are flush with the ceiling and extend about 10 cm above the floor level (finished level).
Equipoten al Bonding:
Steel pipes must be connected to the main protec ve conductor. Equipoten al bonding will be ensured along the en re length of the installa on.
In the presence of electrical equipment on a sec on, this equipment must comply with standard NF C
15.100.
Flow Rates:
Flow rates must be determined so as not to generate fluid circula on noise. The linear pressure drop coefficient J shall not exceed that specified in the "Calcula on Basis" sec on.
BOILER CONVERSION at Consulate General in MARSEILLE 29
Pain ng:
All black steel pipes, supports, and accessories will be completely covered with two coats of an ‐rust paint. Each coat will be of a dis nct color. Pipes, accessories not insulated, and supports will then receive two coats of glycerophthalic finishing paint in conven onal shades.
The treated surfaces will be brushed and degreased beforehand.
Cleaning and Flushing of the Installa on:
During the construc on, temporarily open pipes will be protected by temporary plugs to prevent the introduc on of foreign bodies.
Before star ng up the installa on, hydraulic circuits will be cleaned and flushed.
All low points will have been operated and flushed.
A er flushing, the sieve filters will be rinsed, cleaned, and reassembled.
The final filling with water and air purging will be carried out systema cally. The pressure integrity of the network and the make‐up will be closely monitored.
3.3.2. Copper Pipework
The tubes used shall conform to the NF EN 1057 and NF EN 13349 standards, rigid, annealed, and supplied in bars.
They shall have a thickness of 1 mm up to and including diameter 52, and 1.6 mm above that.
Installa on precau ons:
Pipework shall be:
Posi oned with sufficient spacing for the removal of the insula on, Not obstruc ve to…