Q&A_19FJ6018Q0002.pdf

PDF 203 KB Posted

Attached to
INSTALLATION OF GENERATORS
Solicitation number
19FJ6018Q0002
Issued by

About this file

Questions & Answers

View the file

Other files

File Type Posted
Q&A_19FJ6018Q0002.pdf PDF
Q&A_19FJ6018Q0002.pdf PDF
Fedbiz_post_Generator_Installation_2018.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

19FJ6018Q0002: GENERATOR INSTALLATION SOLICITATION QUESTIONS &

ANSWERS:

1. Provide better understanding of what the East Asian & Pacific Posts has estimated the size or magnitude of this project (in dollars) to be.

Please read the Solicitation Package

2. If this solicitation is for services (not construction), please indicate so.

Please read the Solicitation Package

3. The SOW requires an FEA electrical contracting license. Will US electrical licenses be an acceptable alternative?

The contractor is required to perform this work under the FEA [Fiji

Electricity Authority] electrical contracting license.

The project is at private residences and all its current electrical requirements conform to FEA standards and regulations.

4. Will you accept other technicians?

All bidders must provide past experiences doing installation and servicing of Cummins Generator in Fiji as part of their submitted proposal.