RFQ 19AS2025Q0023 Car Park Retaining Wall Construction.pdf

PDF 538 KB Posted

Attached to
U. S. Embassy Canberra, Car Park Retaining Wall Construction Federal contract opportunity
Solicitation number
19AS2025Q0023
Issued by
Department of State US Embassy Canberra

About this file

This document is a Request for Quotes (RFQ) for a Car Park Retaining Wall construction project at the U.S. Embassy in Canberra, Australia. The solicitation seeks a contractor to complete the project within 75 calendar days, with a contract value estimated between $100,000 and $250,000 USD. A pre-quotation conference is scheduled for July 3rd, 2025, at 10:00 AM AEST, and interested contractors must submit their quotations electronically by 5:00 PM AEST on July 25th, 2025.

Contractors must be technically qualified and meet specific requirements, including SAM registration, English language proficiency, established business presence in Australia, and ability to obtain necessary licenses and insurance. The award will be made to the lowest-priced, acceptable, and responsible quoter. Submissions must include Standard Form 1442, a pricing breakdown, representations and certifications, and proof of SAM registration. The project involves excavation, backfilling, drainage, and construction of a retaining wall at the embassy compound, with strict safety, environmental, and performance standards.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. Embassy Canberra, Australia Date: June 11th, 2025

Dear Prospective Offeror:

Subject: Request for Quotes 19AS2025Q0023 Car Park Retaining Wall

Enclosed is a Request for Quotes (RFQ) for Car Park Retaining Wall. If you would like to submit a quotation, follow the instructions in Section J of the solicitation, complete the required portions of the attached document, and submit it to the address shown on the Standard Form that follows this letter.

The U.S. Government intends to award a contract/purchase order to the responsible company submitting an acceptable offer at the lowest price. We intend to award a contract/purchase order based on initial proposals, without holding discussions, although we may hold discussions with companies in the competitive range if there is a need to do so.

The Embassy will hold a Pre-Quotation Conference at the site on July 3rd, 2025, at 10:00 AM AEST at the U.S. Embassy in Canberra. Prospective offerors/quoters should contact CNBGSOProcurement@state.gov by July 1st, 2025, at 4:00 PM for additional information or to arrange entry to the building site.

Quotations are due by 5:00 pm AEST July 25th, 2025. No quotations will be accepted after this time. Quotations must be in English and incomplete quotations will not be accepted.

Your quotation must be submitted electronically to cnbgsoprocurement@state.gov It is important to make sure the submission is made in specific size and format; in MS-Word 2007/2010 or MS-Excel 2007/2010 or Adobe Acrobat (pdf) file format. The file size must not exceed 30MB. If the file size should exceed 30MB, the submission must be made in separate files and attached to separate emails with less than 30MB each.

In order for a quotation to be considered, you must also complete and submit the following:

1. SF-1442

2. Section A, Pricing

3. Section L Representations and Certifications

4. Additional information as required in Section J

5. Proof of SAM Registration

Offerors shall be registered in the SAM (System for Award Management) database at https://www.sam.gov prior to submittal of their offer/proposal as prescribed under FAR

4.1102. Failure to be registered at the time of proposal submission may deem the offeror’s proposal to be considered non-responsible and no further consideration will be given.

Therefore, offerors are highly encouraged to register immediately if they are interested in submitting a response to this requirement.

Sincerely, Terry Alston Contracting Officer

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR

INFORMATION CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NUMBER

CODE

6. PROJECT NUMBER

8. ADDRESS OFFER TO

4. CONTRACT NUMBER

7. ISSUED BY

11. The contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

STANDARD FORM 1442 (REV. 12/2022)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

REQUEST FOR

QUOTATION (RFQ)

NEGOTIATED (RFP)

REQUEST FOR PROPOSAL

3. DATE ISSUED PAGE OF PAGES

19AS2025Q0023

U.S. Embassy Canberra GSO Procurement 21 Moonah Place Yarralumla ACT 2600 Australia

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

The U.S. Embassy in Canberra has a requirement build a Car Park Retaining Wall at the U.S. Embassy Compound Canberra, Australia.

Refer to Section B for the Statement of Work.

Your quotation must be submitted electronically to:

cnbgsoprocurement@state.gov

5. REQUISITION/PURCHASE REQUEST NUMBER

PR15378548

Kate Costan +61 2 6214 5934

6 0

06/11/2025

a. Quotation in original and 1 local time 7/25/2025

5:00pm

AWARD (To be completed by Government)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 12/2022) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES

CODE AT

27. PAYMENT WILL BE MADE BY

10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )

20b. SIGNATURE 20c. OFFER DATE

RFQ NUMBER: 19AS2025Q0023

TABLE OF CONTENTS

SF-1442 COVER SHEET

A. PRICING

B. STATEMENT OF WORK

C. PACKAGING AND MARKING

D. INSPECTION AND ACCEPTANCE

E. DELIVERIES AND PERFORMANCE

F. CONTRACT ADMINISTRATION DATA

G. SPECIAL TERMS AND CONDITIONS

H. CLAUSES

I. LIST OF ATTACHMENTS

Attachment 1: Breakdown of Price by Divisions of Specifications Attachment 2: Drawings

J. INSTRUCTIONS ON HOW TO SUBMIT A QUOTATION

K. EVALUATION CRITERIA

L. REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS

SECTION A - PRICING

A. PRICE

The Contractor shall complete all work, including furnishing all labor, material, equipment, and services required under this purchase order for the following firm fixed price and within the time specified. This price shall include all labor, materials, all insurance, overhead and profit.

Total Price (including all labor, materials, overhead and profit)

Goods and Service Tax (GST)

Grand Total (Total Price + GST)

A.1 GOODS & SERVICES TAX (GST)

The Contractor shall show Goods and Services Tax (GST) as a separate item on invoices submitted for payment.

SECTION B - STATEMENT OF WORK

The character and scope of the work are set forth in the contract. The Contractor shall furnish and install all materials required by this contract.

In case of differences between small and large-scale drawings, the latter will govern. Where a portion of the work is drawn in detail and the remainder of the work is indicated in outline, the parts drawn in detail shall apply also to all other portions of the work.

B.1. GENERAL SUMMARY

A. Section Includes:

1. Excavating and filling for rough grading the Site.

2. Preparing subgrades for a reinforced concrete slab

3. Excavating and backfilling for buildings and structures.

4. Drainage course for floor slabs.

5. Subbase course for concrete a reinforced concrete slab.

6. Subsurface drainage backfills for a retaining wall

7. Excavating and backfilling for Dincel wall with reinforced concrete retaining walls.

B. Related Requirements:

1. Section 311000 "Site Clearing" for site stripping, grubbing, stripping and stockpiling topsoil, and removal of above- and below-grade improvements and utilities.

2. Section 315000 "Excavation Support and Protection" for shoring, bracing, and sheet piling of excavations.

B.2. DEFINITIONS

A. Backfill: Soil material or controlled low-strength material used to fill an excavation.

1. Initial Backfill: Backfill placed beside and over pipe in a trench, including haunches to support sides of pipe.

2. Final Backfill: Backfill placed over initial backfill to fill a trench.

B. Base Course: Course placed between the subgrade and pavements or walks.

C. Bedding Course: Aggregate layer placed over the excavated subgrade in a trench before laying pipe.

D. Borrow Soil: Satisfactory soil imported from off-site for use as fill or backfill.

E. Drainage Course: Aggregate layer supporting the slab that also minimizes upward capillary flow of pore water.

F. Filter Material: Drainage fill material to be used in subsurface drainage applications for site retaining walls and building foundations. G. Excavation: Removal of material encountered above subgrade elevations and to lines and dimensions indicated.

1. Authorized Additional Excavation: Excavation below subgrade elevations or beyond indicated lines and dimensions as directed by Project Director/COR.

Authorized additional excavation and replacement material will be paid for according to Contract provisions for changes in the Work.

2. Bulk Excavation: Excavation more than 3 m in width and more than 9 m in length.

3. Unauthorized Excavation: Excavation below subgrade elevations or beyond indicated lines and dimensions without direction by Project Director/COR.

Unauthorized excavation, as well as remedial work directed by Project Director/COR, shall be without additional compensation.

G. Fill: Soil materials used to raise existing grades.

H. Rock: Rock material in beds, ledges, unstratified masses, conglomerate deposits, and boulders of rock material that exceed 0.76 cu. m for bulk excavation or 0.57 cu. m for footing, trench, and pit excavation that cannot be removed by rock-excavating equipment equivalent to the following in size and performance ratings, without systematic drilling, ram hammering, ripping, or blasting, when permitted:

1. Equipment for Footing, Trench, and Pit Excavation: Late-model, track-mounted hydraulic excavator; equipped with a 1065-mm maximum-width, short-tip-radius rock bucket; rated at not less than 103-kW flywheel power with bucket-curling force of not less than 128 kN and stick-crowd force of not less than 82 kN with extra-long reach boom.

2. Equipment for Bulk Excavation: Late-model, track-mounted loader; rated at not less than 172-kW flywheel power and developing a minimum of 213.3-kN breakout force with a general-purpose bare bucket.

I. Structures: Buildings, footings, foundations, retaining walls, slabs, tanks, curbs, mechanical and electrical appurtenances, or other man-made stationary features constructed above or below the ground surface.

J. Subgrade: Uppermost surface of an excavation or the top surface of a fill or backfill immediately below base, drainage fill, drainage course, or topsoil materials.

K. Utilities: On-site underground pipes, conduits, ducts, and cables as well as underground services within buildings.

B.3. PREINSTALLATION MEETINGS

A. Preinstallation Conference: Conduct pre-excavation conference at GSO car park affected area.

1. Review methods and procedures related to earthmoving, including, but not limited to, the following:

o Personnel and equipment needed to make progress and avoid delays.

o Coordination of Work with utility locator service.

o Coordination of Work and equipment movement with the locations of tree-and plant-protection zones.

o Extent of trenching by hand or with air spade.

o Field quality control.

o Discussion of safety protocols and emergency procedures.

o Review of environmental impact considerations.

o Establishment of communication channels and reporting structure.

o Q&A session to address any concerns from participants.

B.4. SUBMITTALS

A. Product Data: For each type of the following manufactured products required:

1. Geotextiles.

2. Controlled low-strength material, including design mixture.

3. Geofoam.

4. Dincel wall.

5. Drainage material.

6. Waterproofing.

B. Qualification Data: For qualified testing agency.

C. Material Test Reports: For each on-site and borrow soil material proposed for fill and backfill as follows:

1. Classification according to ASTM D2487.

2. Laboratory compaction curve according to [ASTM D698] [ASTM D1557].

3. California Bearing Ratio (CBR) according to ASTM D 1883 of each soil material proposed to support pavement sections.

4. Corrosion testing (pH, resistivity, sulfate content, and chloride content) to demonstrate that imported soils are not more corrosive to buried concrete or steel than the on-site soils or the corrosion protection measures can accommodate. Corrosion testing of at least four representative samples of each import fill material shall include:

a. pH according to ASTM G51

b. Soil resistivity according to American Association of State Highway Officials

(AASHTO) T288

c. Water-soluble chloride ion content in soil according to AASHTO T291

d. Water-soluble sulfate content in soil (Method A – Gravimetric) according to

AASHTO T290.

D. Blasting plan approved by Project Director/COR and authorities having jurisdiction.

E. Pre-excavation Photographs or Videotape: Show existing conditions of adjoining construction and site improvements, including finish surfaces that might be misconstrued as damage caused by earthwork operations. Submit before earthwork begins.

F. Health and Safety Plan

B.5. QUALITY ASSURANCE

A. Blasting: Comply with applicable requirements in NFPA 495, "Explosive Materials Code," and prepare a blasting plan reporting the following:

1. Types of explosive and sizes of charge to be used in each area of rock removal, types of blasting mats, sequence of blasting operations, and procedures that will prevent damage to site improvements and structures on Project site and adjacent properties.

2. Seismographic monitoring during blasting operations.

B. Geotechnical Testing Agency Qualifications: A qualified independent testing agency approved by the Geotechnical Engineer of Record and Project Director/COR to conduct soil materials testing, as documented according to ASTM D3740 and ASTM E329.

C. Conform to grading, excavation, and other earth moving requirements of the OBO Zoning Code.

D. Pre-Excavation Conference: Conduct conference at Project site to comply with requirements in Division 01 Section, "Contractor’s Quality Control” and Preinstallation Meeting.

B.6. PROJECT CONDITIONS

A. Traffic: Minimize interference with adjoining roads, streets, walks, and other adjacent occupied or used facilities during earth-moving operations.

1. Do not close or obstruct streets, walks, or other adjacent occupied or used facilities without permission from Project Director/COR and authorities having jurisdiction.

2. Provide alternate routes around closed or obstructed traffic ways if required by Project Director/COR or authorities having jurisdiction.

B. Existing Utilities: Do not interrupt utilities serving facilities occupied by Government or others unless permitted in writing by Project Director//COR and then only after arranging to provide temporary utility services according to requirements indicated.

1. Notify Project Director//COR not less than two days in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without Project Director/COR’s written permission.

3. Contact utility-locator service for area where Project is located before excavating.

C. Do not commence earth-moving operations until temporary site fencing and erosion- and sedimentation-control measures specified in Section 015000 "Temporary Facilities and Controls" and Section 311000 "Site Clearing" are in place.

D. Do not commence earth-moving operations until plant-protection measures specified in Section 015639 "Temporary Tree and Plant Protection" are in place.

E. The following practices are prohibited within protection zones:

1. Storage of construction materials, debris, or excavated material.

2. Parking vehicles or equipment.

3. Foot traffic.

4. Erection of sheds or structures.

5. Impoundment of water.

6. Excavation or other digging unless otherwise indicated.

7. Attachment of signs to or wrapping materials around trees or plants unless otherwise indicated.

F. Do not direct vehicle or equipment exhaust towards protection zones.

G. Prohibit heat sources, flames, ignition sources, and smoking within or near protection zones.

H. Demolish and completely remove from site existing underground utilities indicated to be removed. Coordinate with utility companies to shut off services if lines are active.

I. Demolish and completely remove existing shallow foundation, floor slabs, grade beams, and utilities below all pavement, floor slab, foundations, pile caps, or other structural elements. Replace with satisfactory soil.

J. Refer to the Geotechnical Engineering Report prepared and associated boring and test data for information pertaining to the general subsurface conditions within the project site.

B.7. PRODUCTS SOIL MATERIALS

A. General: Provide borrow soil materials when sufficient satisfactory soil materials are not available from excavations.

B. Satisfactory Soils: Soil Classification Groups GW, GP, GM, SW, SP, and SM according to ASTM D2487 or a combination of these groups; free of rock or gravel larger than 75 mm in any dimension, debris, waste, frozen materials, vegetation, potentially corrosive materials, and other deleterious matter. These materials should exhibit a Liquid Limit and Plasticity Index of less than 40 and 15, respectively.

C. Unsatisfactory Soils: Soil Classification Groups GC, SC, CL, ML, OL, CH, MH, OH, and PT according to ASTM D2487, or a combination of these groups.

1. Unsatisfactory soils also include satisfactory soils not maintained within 2 percent of optimum moisture content at time of compaction and potentially corrosive imported soils.

D. Base Course: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D2940/D2940M; with at least 100 percent passing a 50 mm sieve, 80 to 95 percent passing the 25 mm sieve, 50 to 70 percent passing the 9.5 mm sieve, 9 to 20 percent passing the 0.425 mm sieve, and not more than 8 percent passing a

0.075 mm sieve.

E. Engineered Fill: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D2940/D2940M; with at least 90 percent passing a 37.5-mm sieve and not more than 12 percent passing a 0.075-mm sieve.

F. Bedding Course: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D2940/D2940M; except with 100 percent passing a 25-mm sieve and not more than 8 percent passing a 0.075-mm sieve.

G. Drainage Course: Narrowly graded mixture of washed crushed stone or crushed or uncrushed gravel; ASTM D448; coarse-aggregate grading Size 57; with 100 percent passing a 37.5-mm sieve and zero to 5 percent passing a 2.36-mm sieve.

H. Filter Material: Narrowly graded mixture of natural or crushed gravel, or crushed stone and natural sand; ASTM D448; coarse-aggregate grading Size 67; with 100 percent passing a 25-mm sieve and zero to 5 percent passing a 4.75-mm sieve.

I. Sand: ASTM C33/C33M; fine aggregate.

J. Impervious Fill: Soil classification groups CH, MH, CL, ML according to ASTM D 2487 or a combination of these groups.

B.8. GEOTEXTILES

A. Subsurface Drainage Geotextile: Nonwoven needle-punched geotextile, manufactured for subsurface drainage applications, made from polyolefins or polyesters; with elongation greater than 50 percent; complying with AASHTO M 288 and the following, measured per test methods referenced:

1. Survivability: As follows:

o Grab Tensile Strength: 700 N; ASTM D4632.

o Sewn Seam Strength: 630 N; ASTM D4632.

o Tear Strength: 250 N; ASTM D4533.

o Puncture Strength: 250 N; ASTM D4833.

2. Apparent Opening Size: [0.425-mm] [0.250-mm] [0.212-mm] sieve, maximum;

ASTM D4751.

3. Permittivity: [0.5] [0.2] [0.1] per second, minimum; ASTM D4491.

4. UV Stability: 50 percent after 500 hours' exposure; ASTM D4355.

B. Separation Geotextile: Woven geotextile fabric, manufactured for separation applications, made from polyolefins or polyesters; with elongation less than 50 percent; complying with AASHTO M 288 and the following, measured per test methods referenced:

1. Survivability: As follows:

o Grab Tensile Strength: 1100 N; ASTM D4632.

o Sewn Seam Strength: 990 N; ASTM D4632.

o Tear Strength: 400 N; ASTM D4533.

o Puncture Strength: 400 N; ASTM D4833.

2. Apparent Opening Size: 0.250-mm sieve, maximum; ASTM D4751.

3. Permittivity: 0.02 per second, minimum; ASTM D4491.

4. UV Stability: 50 percent after 500 hours' exposure; ASTM D4355.

B.9. CONTROLLED LOW-STRENGTH MATERIAL

A. Controlled Low-Strength Material: Self-compacting, flowable concrete material produced from the following:

1. Portland Cement: ASTM C150/C150M, Type II] or Type III.

2. Fly Ash: ASTM C618, Class C or F.

3. Normal-Weight Aggregate: ASTM C33/C33M, 10-mm +- 2 size.

4. Water: ASTM C94/C94M.

B. Produce conventional-weight controlled low-strength material with 550-kPa compressive strength when tested according to ASTM C495/C495M.

B.10. DRAINAGE PANEL

A. Drainage Panel: MiraDRAIN 6000, Hydroduct 220 with Hydroduct Coil 600 Drainage Composite, or approved equivalent consisting of a 3-dimensional dimpled core and geotextile fabric for use over waterproofing membranes, lagging and retaining wall applications.

B.11. GEOFOAM

A. Extruded-Polystyrene Board Insulation: ASTM C578, [Type IV, 25-kg/cu. m density, 173-kPa compressive strength] [Type X, 21-kg/cu. m density, 104-kPa compressive strength] [Type VI, 29-kg/cu. m density, 276-kPa compressive strength] [Type VII, 35-kg/cu. m density, 414-kPa compressive strength] [Type V, 48-kg/cu. m density, 690-kPa compressive strength].

B.12. EXECUTION PREPARATION

A. Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards created by earthwork operations.

B. Preparation of subgrade for earthwork operations including removal of vegetation, topsoil, debris, obstructions, and deleterious materials from ground surface within [x] feet beyond the limit of construction area as specified in Division 31 Section “Site Clearing.”

C. After stripping and prior to placing fill, proof-roll subgrade below [the building slabs], [new fill], [foundations], [and] [pavements] with a heavy pneumatic-tired equipment to identify soft pockets and areas of excess yielding not encountered in the test borings.

D. Protect and maintain erosion and sedimentation controls, which are specified in Division 31 Section “Site Clearing,” during earthwork operations.

E. Stockpile on-site materials anticipated for re-use after screening. Care shall be taken to avoid blending with the deleterious materials.

B.13. DEWATERING

F. Provide dewatering system of sufficient scope, size, and capacity to control hydrostatic pressures and to lower, control, remove, and dispose of ground water and permit excavation and construction to proceed on dry, stable subgrades.

G. Prevent surface water and ground water from entering excavations, from ponding on prepared subgrades, and from flooding Project site and surrounding area.

H. Protect subgrades from softening, undermining, washout, and damage by rain or water accumulation.

1. Reroute surface water runoff away from excavated areas. Do not allow water to accumulate in excavations. Do not use excavated trenches as temporary drainage ditches.

2. Install a dewatering system as indicated in Division 31 Section “Dewatering” as required to keep subgrades dry and convey groundwater away from excavations.

Groundwater levels should be maintained a minimum of 0.6m (2 ft) below subgrade level. Maintain until dewatering is no longer required.

I. Dispose of all dewatering effluent in strict accordance with the project environmental requirements, US Federal regulations, and local requirements. The Project Director must review and approve dewatering disposal method.

B.14. EXCAVATION, GENERAL

A. Unclassified Excavation: Excavate to subgrade elevations regardless of the character of surface and subsurface conditions encountered. Unclassified excavated materials may include rock, soil materials, and obstructions. No changes in the Contract Sum or the Contract Time will be authorized for rock excavation or removal of obstructions.

1. If excavated materials intended for fill and backfill include unsatisfactory soil materials and rock, replace with satisfactory soil materials.

2. Remove rock to lines and grades indicated to permit installation of permanent construction without exceeding the following dimensions:

o 600 mm outside of concrete forms other than at footings.

o 300 mm outside of concrete forms at footings.

o 150 mm outside of minimum required dimensions of concrete cast against grade.

o Outside dimensions of concrete walls indicated to be cast against rock without forms or exterior waterproofing treatments.

o 150 mm beneath bottom of concrete slabs-on-grade.

o 150 mm beneath pipe in trenches and the greater of 600 mm wider than pipe or 1065 mm wide.

B.15. EXCAVATION FOR STRUCTURES

A. Excavate to indicated elevations and dimensions within a tolerance of plus or minus 25

mm. If applicable, extend excavations a sufficient distance from structures for placing and removing concrete formwork, for installing services and other construction, and for inspections.

1. Excavations for Footings and Foundations: Do not disturb bottom of excavation.

Excavate by hand to final grade just before placing concrete reinforcement. Trim bottoms to required lines and grades to leave solid base to receive other work.

2. Foundations shall be constructed on suitable natural soils, new compacted fill, or lean concrete. Do not disturb bottom of excavation. Excavate by hand to final grade just before placing concrete reinforcement. Trim bottoms to required lines and grades to leave solid base to receive other work.

3. Foundation subgrades shall be observed by a qualified local Geotechnical Engineer to evaluate whether the soils are suitable for the recommended bearing pressures and to verify that subgrades have not become excessively disturbed

B.16. SUBGRADE INSPECTION

A. Notify Project Director and Geotechnical Testing Agency when excavations have reached required subgrade.

B. If Project Director or Geotechnical Testing Agency determine that unsatisfactory soil is present, continue excavation and replace with compacted backfill or fill material as directed.

C. Proof-roll subgrade below [the building slabs], [new fill], [foundations], [and] [pavements] with a heavy pneumatic-tired equipment to identify soft pockets and areas of excess yielding.

Do not proof-roll wet or saturated subgrades.

1. Completely proof-roll subgrade in one direction, repeating proof-rolling in direction perpendicular to first direction. Limit vehicle speed to 5 km/h.

2. Proof-roll with a loaded dump truck or other suitable weight rubber-tired construction equipment weighing not less than 14 tons. Alternate equipment must be approved by Project Director.

3. Excavate soft spots, unsatisfactory soils, and areas of excessive pumping or rutting, as determined by Project Director and Geotechnical Testing Agency, and replace with compacted backfill or fill as directed.

D. In confined areas where proof-rolling with heavy pneumatic-tired equipment is not feasible, the subgrade should be evaluated using other methods to determine the suitability of subgrade soils before fill placement. Other methods include the use of a dynamic cone penetrometer (DCP), geostick penetrometer or similar methods.

E. Subgrades beneath structural slab areas shall be sufficient strength to support construction activities and machinery without excessive damage.

F. Authorized additional excavation and replacement material will be paid for according to Contract provisions for changes in the Work.

G. Reconstruct subgrades damaged by freezing temperatures, frost, rain, accumulated water, or construction activities, as directed by the Geotechnical Testing Agency and Project Director/COR, without additional compensation.

B.17. STORAGE OF SOIL MATERIALS

A. Stockpile borrow soil materials and excavated satisfactory soil materials without intermixing. Place, grade, and shape stockpiles to drain surface water. Cover to protect from rain and to prevent windblown dust.

1. Stockpile soil materials away from edge of excavations. Do not store within drip line of remaining trees.

2. Contractor shall be solely responsible for the stability of stockpiles and the areas where stockpiles are placed. Contractor shall stockpile materials in a manner so as to not compromise the stability or cause loss of support to existing structures and surfaces.

B.18. BACKFILL

A. Place and compact backfill in excavations promptly, but not before completing the following:

1. Construction below finish grade including, where applicable, subdrainage, damp proofing, waterproofing, vapor barrier installation, and perimeter insulation.

2. Surveying locations of underground utilities for Record Documents.

3. Testing and inspecting underground utilities.

4. Removing concrete formwork.

5. Removing trash and debris.

6. Removing temporary shoring, bracing, and sheeting.

7. Installing permanent or temporary horizontal bracing on horizontally supported walls.

B. Place backfill on subgrades free of debris, water, mud, frost, snow, or ice that are not loose or contain deleterious materials.

B.19. SOIL FILL

A. Plow, scarify, bench, or break up sloped surfaces steeper than 1 vertical to 4 horizontal so fill material will bond with existing material.

B. Place and compact fill material in layers to required elevations as follows:

1. Under grass and planted areas, use satisfactory soil material.

2. Under walks and pavements, use satisfactory soil or engineered fill material.

3. Under steps and ramps, use engineered fill.

4. Under building slabs, use engineered fill.

5. Under footings and foundations, use engineered fill.

C. Place soil fill on subgrades free of mud, water, frost, snow, or ice and that are not loose or contain deleterious materials.

B.20. COMPACTION OF SOIL BACKFILLS AND FILLS

A. Place backfill and fill soil materials in layers not more than 200 mm in loose depth for material compacted by heavy compaction equipment and not more than 100 mm in loose depth for material compacted by hand-operated tampers.

B. Place backfill and fill soil materials evenly on all sides of structures to required elevations and uniformly along the full length of each structure.

C. Compact soil materials to not less than the following percentages of maximum dry unit weight according to [ASTM D698] [ASTM D1557]:

1. Under structures, building slabs, steps, and pavements, scarify and recompact top 300 mm of existing subgrade and each layer of backfill or fill soil material at 95 percent.

2. Under walkways, scarify and recompact top 150 mm below subgrade and compact each layer of backfill or fill soil material at 95 percent.

3. Under turf or unpaved areas, scarify and recompact top 150 mm below subgrade and compact each layer of backfill or fill soil material at 92 percent.

4. For utility trenches, compact each layer of initial and final backfill soil material at 95 percent.

B.21. SUBSURFACE DRAINAGE

A. Subsurface Drain: Place subsurface drainage geotextile around perimeter of subdrainage trench. Place a 150-mm course of filter material on subsurface drainage geotextile to support subdrainage pipe. Encase subdrainage pipe in a minimum of 300 mm of filter material, placed in compacted layers 150 mm thick, and wrap in subsurface drainage geotextile, overlapping sides and ends at least 150 mm.

1. Compact each filter material layer with a minimum of two passes of a plate-type vibratory compactor.

B. Drainage Backfill: Place and compact filter material over subsurface drain, in width indicated, to within 300 mm of final subgrade, in compacted layers 150 mm thick. Overlay drainage backfills with one layer of subsurface drainage geotextile, overlapping sides and ends at least 150 mm.

1. Compact each filter material layer with a minimum of two passes of a plate-type vibratory compactor.

2. Place and compact impervious fill over drainage backfill in 150-mm thick compacted layers to final subgrade.

B.22. FIELD QUALITY CONTROL

A. Geotechnical Testing Agency: The Contractor will engage a qualified geotechnical engineering testing agency to perform field quality-control testing. Geotechnical Testing Agency must be from independent from Contractor and Contractor’s firm unless approved by the Project Director/COR.

B. Allow geotechnical testing agency to inspect and test subgrades and each fill or backfill layer. Proceed with subsequent earth moving only after test results for previously completed work comply with requirements.

C. Foundation Subgrade: At foundation subgrades, at least one test of each soil stratum will be performed to verify design bearing capacities. Subsequent verification and approval by the Geotechnical Testing Agency of other footing subgrades may be based on a visual comparison of subgrade with tested subgrade when approved by Project Director/COR.

D. Testing agency will test compaction of soils in place according to ASTM D1556, ASTM D2167, ASTM D2922, ASTM D2937, and ASTM D6938, as applicable. Note that if Contractor request approval to use an electromagnetic density gauge (EDG) according to ASTM D 7830 to assess soil compaction, prior approval should be received from Project Director/COR and a minimum of one sand cone (ASTM D 1556), or drive-cylinder (ASTM D 2937) compaction test shall be performed for every 20 EDG tests. Tests will be performed at the following locations and frequencies:

1. Paved and Building Footprint Areas: At subgrade and at each compacted fill and backfill layer, at least one test for every 186 sq. m or less of paved area or building footprint but in no case fewer than three tests.

2. Foundation Wall Backfill: At each compacted backfill layer, at least one test for every 30 m or less of wall length but no fewer than two tests.

3. Trench Backfill: At each compacted initial and final backfill layer, at least one test for every 46 m or less of trench length but no fewer than two tests.

E. When testing agency reports that subgrades, fills, or backfills have not achieved degree of compaction specified, scarify and moisten or aerate, or remove and replace soil materials to depth required; recompact and retest until specified compaction is obtained.

B.23. PROTECTION

A. Protecting Graded Areas: Protect newly graded areas from traffic, freezing, and erosion.

Keep free of trash and debris.

B. Repair and reestablish grades to specified tolerances where completed or partially completed surfaces become eroded, rutted, settled, or where they lose compaction due to subsequent construction operations or weather conditions.

1. Scarify or remove and replace soil material to depth as directed by Project Director/COR; reshape and recompact.

C. Where settling occurs before Project correction period elapses, remove finished surfacing, backfill with additional soil material, compact, and reconstruct surfacing.

2. Restore appearance, quality, and condition of finished surfacing to match adjacent work, and eliminate evidence of restoration to greatest extent possible.

B.24. DISPOSAL OF SURPLUS AND WASTE MATERIALS

A. Remove surplus satisfactory soil and waste materials, including unsatisfactory soil, trash, and debris, and legally dispose of them off Government's property.

SECTION C - PACKAGING AND MARKING

Mark materials delivered to the site as follows:

[ RESERVED ]

SECTION D - INSPECTION AND ACCEPTANCE

The COR, or his/her authorized representatives, will inspect from time to time the services being performed and the supplies furnished to determine whether work is being performed in a satisfactory manner, and that all supplies are of acceptable quality and standards.

The Contractor shall be responsible for any countermeasures or corrective action, within the scope of this contract, which may be required by the Contracting Officer as a result of such inspection.

D.1 SUBSTANTIAL COMPLETION

(a) "Substantial Completion" means the stage in the progress of the work as determined and certified by the Contracting Officer in writing to the Contractor, on which the work (or a portion designated by the Government) is sufficiently complete and satisfactory. Substantial completion means that the property may be occupied or used for the purpose for which it is intended, and only minor items such as touch-up, adjustments, and minor replacements or installations remain to be completed or corrected which:

(1) do not interfere with the intended occupancy or utilization of the work, and

(2) can be completed or corrected within the time period required for final completion.

(b) The "date of substantial completion" means the date determined by the Contracting Officer or authorized Government representative as of which substantial completion of the work has been achieved.

Use and Possession upon Substantial Completion - The Government shall have the right to take possession of and use the work upon substantial completion. Upon notice by the Contractor that the work is substantially complete (a Request for Substantial Completion) and an inspection by the Contracting Officer or an authorized Government representative (including any required tests), the Contracting Officer shall furnish the Contractor a Certificate of Substantial Completion. The certificate will be accompanied by a Schedule of Defects listing items of work remaining to be performed, completed, or corrected before final completion and acceptance. Failure of the Contracting Officer to list any item of work shall not relieve the Contractor of responsibility for complying with the terms of the contract. The Government's possession or use upon substantial completion shall not be deemed an acceptance of any work under the contract.

D.2 FINAL COMPLETION AND ACCEPTANCE

D.2.1 "Final completion and acceptance" means the stage in the progress of the work as determined by the Contracting Officer and confirmed in writing to the Contractor, at which all work required under the contract has been completed in a satisfactory manner, subject to the discovery of defects after final completion, and except for items specifically excluded in the notice of final acceptance.

D.2.2 The "date of final completion and acceptance" means the date determined by the Contracting Officer when final completion of the work has been achieved, as indicated by written notice to the Contractor.

D.2.3 FINAL INSPECTION AND TESTS. The Contractor shall give the Contracting Officer at least five (5) days advance written notice of the date when the work will be fully completed and ready for final inspection and tests. Final inspection and tests will be started not later than the date specified in the notice unless the Contracting Officer determines that the work is not ready for final inspection and so informs the Contractor.

D.2.4 FINAL ACCEPTANCE. If the Contracting Officer is satisfied that the work under the contract is complete (with the exception of continuing obligations), the Contracting Officer shall issue to the Contractor a notice of final acceptance and make final payment upon:

Satisfactory completion of all required tests, A final inspection that all items by the Contracting Officer listed in the Schedule of Defects have been completed or corrected and that the work is finally complete (subject to the discovery of defects after final completion), and

Submittal by the Contractor of all documents and other items required upon completion of the work, including a final request for payment (Request for Final Acceptance).

SECTION E - DELIVERIES AND PERFORMANCE

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

(APR 1984)

The Contractor shall be required to:

(a) commence work under this contract within ten (10) calendar days after the date the Contractor receives the notice to proceed,

(b) prosecute the work diligently, and,

(c) complete the entire work ready for use not later than seventy-five (75) calendar days.

The time stated for completion shall include final cleanup of the premises.

52.211-12 LIQUIDATED DAMAGES - CONSTRUCTION (SEPT 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, or any extension, the Contractor shall pay liquidated damages to the Government in the amount of $250.00 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor’s right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Default clause.

CONTRACTOR'S SUBMISSION OF CONSTRUCTION SCHEDULES

(a) The time for submission of the schedules referenced in FAR 52.236-15, "Schedules for Construction Contracts", paragraph (a), is hereby modified to reflect the due date for submission as five (5) calendar days after receipt of an executed contract".

(b) These schedules shall include the time by which shop drawings, product data, samples and other submittals required by the contract will be submitted for approval.

(c) The Contractor shall revise such schedules (1) to account for the actual progress of the work, (2) to reflect approved adjustments in the performance schedule, and

(3) as required by the Contracting Officer to achieve coordination with work by the Government and any separate contractors used by the Government. The Contractor shall submit a schedule, which sequences work so as to minimize disruption at the job site.

(d) All deliverables shall be in the English language and any system of dimensions (English or metric) shown shall be consistent with that used in the contract. No extension of time shall be allowed due to delay by the Government in approving such deliverables if the Contractor has failed to act promptly and responsively in submitting its deliverables. The Contractor shall identify each deliverable as required by the contract.

(e) Acceptance of Schedule: When the Government has accepted any time schedule; it shall be binding upon the Contractor. The completion date is fixed and may be extended only by a written contract modification signed by the Contracting Officer.

Acceptance or approval of any schedule or revision thereof by the Government shall not:

(1) Extend the completion date or obligate the Government to do so,

(2) Constitute acceptance or approval of any delay, or

(3) Excuse the Contractor from or relieve the Contractor of its obligation to maintain the progress of the work and achieve final completion by the established completion date.

NOTICE OF DELAY

If the Contractor receives a notice of any change in the work, or if any other conditions arise which are likely to cause or are actually causing delays which the Contractor believes may result in late completion of the project, the Contractor shall notify the Contracting Officer.

The Contractor’s notice shall state the effect, if any, of such change or other conditions upon the approved schedule, and shall state in what respects, if any, the relevant schedule, or the completion date should be revised. The Contractor shall give such notice promptly, not more than ten (10) days after the first event giving rise to the delay or prospective delay. Only the Contracting Officer may revise the approved time schedule.

NOTICE TO PROCEED

(a) After receiving and accepting any bonds or evidence of insurance, the Contracting Officer will provide the Contractor with a Notice to Proceed. The Contractor must then prosecute the work, commencing and completing performance not later than the time period established in the contract.

(b) It is possible that the Contracting Officer may elect to issue the Notice to Proceed before receipt and acceptance of any bonds or evidence of insurance. Issuance of a Notice to Proceed by the Government before receipt of the required bonds or insurance certificates or policies shall not be a waiver of the requirement to furnish these documents.

WORKING HOURS

All work shall be performed from 0700 to 1800 Monday through Friday. Other hours, if requested by the Contractor, may be approved by the Contracting Officer's Representative (COR). The Contractor shall give 24 hours in advance to COR who will consider any deviation from the hours identified above. Changes in work hours, initiated by the Contractor, will not be a cause for a price increase.

PRECONSTRUCTION CONFERENCE

A preconstruction conference will be held 10 days after contract award at the U.S. Embassy Canberra to discuss the schedule, submittals, notice to proceed, mobilization and other important issues that effect construction progress. See FAR 52.236-26, Preconstruction Conference.

DELIVERABLES - The following items shall be delivered under this contract:

Description Quantity Deliver Date Deliver To

Section G. Securities/Insurance 1 10 days after award CO

Section E. Construction Schedule 1 10 days after award COR

Section E. Preconstruction Conference 1 10 days after award COR

Section G. Personnel Biographies 1 10 days after award COR

Section F. Payment Request 1 Last calendar day of each month COR

Section D. Request for Substantial Completion 1

15 days before inspection COR

Section D. Request for Final Acceptance 1 5 days before inspection COR

SECTION F – CONTRACT ADMINISTRATION DATA

652.242-70 CONTRACTING OFFICER'S REPRESENTATIVE (COR) (AUG 1999)

(a) The Contracting Officer may designate in writing one or more Government employees, by name or position title, to take action for the Contracting Officer under this contract. Each designee shall be identified as a Contracting Officer’s Representative (COR).

Such designation(s) shall specify the scope and limitations of the authority so delegated;

provided that the designee shall not change the terms or conditions of the contract, unless the COR is a warranted Contracting Officer, and this authority is delegated in the designation.

(b) The COR for this contract is: FM Projects Coordinator

Payment: The Contractor's attention is directed to Section H, 52.232-5, "Payments Under Fixed-Price Construction Contracts". The following elaborates on the information contained in that clause.

Requests for payment may be made no more frequently than monthly. Payment requests shall cover the value of labor and materials completed and in place, including a prorated portion of overhead and profit.

After receipt of the Contractor's request for payment, and on the basis of an inspection of the work, the Contracting Officer shall make a determination as to the amount, which is then due.

If the Contracting Officer does not approve payment of the full amount applied for, less the retainage allowed by in 52.232-5, the Contracting Officer shall advise the Contractor as to the reasons.

Under the authority of 52.232-27(a), the 14-day period identified in FAR 52.232- 27(a)(1)(i)(A) is hereby changed to 30 days.

U.S. Embassy Canberra Attn: Canberra Accounts Payable cnbcustservice@state.gov

The Contractor shall show Goods and Services Tax (GST) as a separate item on invoices submitted for payment.

SECTION G - SPECIAL TERMS AND CONDITIONS

G.1.0 INSURANCE - The Contractor is required by FAR 52.228-5, "Insurance - Work on a Government Installation" to provide whatever insurance is legally necessary. The Contractor shall at its own expense provide and maintain during the entire performance period the following insurance amounts:

G.1.1 GENERAL LIABILITY (includes premises/operations, collapse hazard, products, completed operations, contractual, independent contractors, broad form property damage, personal injury):

(1) BODILY INJURY, ON OR OFF THE SITE, IN U.S. DOLLARS

Per Occurrence $10,000,000 AUD or USD Equivalent

Cumulative $10,000,000 AUD or USD Equivalent

(2) PROPERTY DAMAGE, ON OR OFF THE SITE, IN U.S. DOLLARS

Per Occurrence $10,000,000 AUD or USD Equivalent

Cumulative $10,000,000 AUD or USD Equivalent

G.1.2 The foregoing types and amounts of insurance are the minimums required. The Contractor shall obtain any other types of insurance required by local law or that are ordinarily or customarily obtained in the location of the work. The limit of such insurance shall be provided by law or sufficient to meet normal and customary claims.

G.1.3 The Contractor agrees that the Government shall not be responsible for personal injuries or for damages to any property of the Contractor, its officers, agents, servants, and employees, or any other person, arising from…

This is the start of the file's text. The full file is on GovTribe.