This is a Project Manual for the Sunset Heights Urgent Care Construction and Buildout project, prepared for Harris Health in Texas. The document provides comprehensive construction specifications and requirements for the development of an urgent care facility at the Sunset Heights location. The project encompasses site preparation, building construction, mechanical, electrical, and plumbing systems installation, and final buildout to create a fully operational urgent care center. The manual details technical specifications, construction standards, material requirements, and quality standards that contractors must meet throughout the project execution. The document serves as the governing technical reference for all construction activities and contractor performance expectations.

The Project Manual establishes the baseline requirements and standards for all construction work related to the estimated $10,481,414 project budget. It contains detailed specifications for building systems, finishes, and operational requirements necessary to create a functional urgent care facility. The manual includes provisions for compliance with applicable building codes, safety regulations, and healthcare facility standards. This document functions as a critical planning and reference tool for bidders and contractors to understand the full scope of work, technical requirements, and quality expectations that will govern the construction and buildout phase of the Sunset Heights Urgent Care facility for Harris Health.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sunset Heights Urgent Care Harris Health Houston, Texas

Project Manual

Issued For Contract Documents

Project Number: 2321.06 12.19.25

This page intentionally left blank

CONTRACT DOCUMENTS SUNSET HEIGHTS URGENT CARE

DECEMBER 19, 2025 PROJECT NO. 2321.06

SEALS PAGE 00 01 07 - 1/3

SECTION 00 01 07

SEALS PAGE

ARCHITECT OF RECORD

O'Connell Robertson 811 Barton Springs Road, Suite 900 Austin, Texas 78704

Architect of Record Date

MECHANICAL ENGINEER OF RECORD

O'Connell Robertson 811 Barton Springs Road, Suite 900

TBPE Registered Firm No. F-2708

Mechanical Engineer of Record Date

ELECTRICAL ENGINEER OF RECORD

O'Connell Robertson 811 Barton Springs Road, Suite 900

Electrical Engineer of Record Date

12/18/2025

12/18/2025

12/19/2025

SEALS PAGE 00 01 07 - 2/3

PLUMBING ENGINEER OF RECORD

O'Connell Robertson 811 Barton Springs Road, Suite 900

Plumbing Engineer of Record Date

CIVIL ENGINEER OF RECORD

Martinez-Moore Engineers 401 S. 1st Street, Suite 600 Austin, TX 78704

Civil Engineer of Record Date

STRUCTURAL ENGINEER OF RECORD

H2B Engineering 1225 North Loop West, Suite 800 Houston, TX 77008

Structural Engineer of Record Date

STRUCTURAL ENGINEER OF RECORD

H2B Engineering 1225 North Loop West, Suite 800 Houston, TX 77008

Structural Engineer of Record Date

12/19/2025

Plumbing Engineer of Record

STATE OF TEXAS

PROFESSIONA L ENGINEE

R

L ICENSED

97261

VANESSA R. McELROY

12/19/25

SEALS PAGE 00 01 07 - 3/3

DATACOM CONSULTANT OF RECORD

Combs Consulting 1022 River Road #2 Boerne, Texas 78006

Datacom Consultant of Record Date

LANDSCAPE ARCHITECT OF RECORD

Wong & Associates, Inc P.O Box 2028 Bellaire, Texas 77402

Landscape Architect of Record Date

END OF DOCUMENT

DATACOM CONSULTANT OF RECORD

Combs Consulting 1022 River Road #2 Boerne, Texas 78006

Datacom Consultant of Record Date

Anthony Vistein

LANDSCAPE ARCHITECT OF RECORD

Wong & Associates, Inc P.O Box 2028 Bellaire, Texas 77402

Landscape Architect of Record Date

Austin 811 Barton Springs Road, Suite 900, Austin, Texas 78704 p: 512.478.7286 f: 512.478.7441

San Antonio 4040 Broadway, Suite 300, San Antonio, Texas 78209 p: 210.224.6032 f: 210.224.6453

ADDENDUM

SCP ACS Sunset Heights Urgent Care Addendum No. 01 1615 N. Main Street Page 1 of 6 Houston, TX O’Connell Robertson Project No. 2321.06 Harris Health Project No. 25-3SCP00178

Addendum No. 01

Date: 01/16/26

SCP ACS Sunset Heights Urgent Care

1615 N. Main Street

Houston, Texas

O’Connell Robertson Project: 2321.06

Harris Health Project: 25-SCP00178

01/16/2026MECHANICAL

01/16/2026

01/16/2026 01/16/2026

Austin 811 Barton Springs Road, Suite 900, Austin, Texas 78704 p: 512.478.7286 f: 512.478.7441

San Antonio 4040 Broadway, Suite 300, San Antonio, Texas 78209 p: 210.224.6032 f: 210.224.6453

Notice To Bidders

A. This Addendum shall be considered part of the Construction Documents dated December

19, 2025, for the above-mentioned project, as though it had been issued at the same time and incorporated integrally therewith. Where provisions of the following supplementary data differ from those of the original Construction Documents, this Addendum shall govern and take precedence.

B. Bidders are hereby notified that they shall make necessary adjustments in their estimates on account of this Addendum. It will be construed that each bidder’s proposal is submitted with full knowledge of all modifications and supplemental data specified herein. Please staple in the back of your specification book.

SPECIFICATIONS

Sections itemized below are attached to this Addendum.

Replace previously issued sections in entirety with those issued herewith.

*Indicates new specification section

ITEM 1 Section 23 09 23 - Building Automation Systems for HVAC

A. ADDED section.

DRAWINGS

LANDSCAPE:

ITEM L1 Sheet L1.1 – LANDSCAPE PLAN

A. Due to conflict with overhead powerlines poles, trees and site furnishing have shifted to stay out of easement.

ITEM L2 Sheet L1.2 – ENLARGEMENT PLAN

A. Due to conflict with overhead powerlines poles, trees and site furnishing have shifted to stay out of easement.

STRUCTURAL:

ITEM S1 Sheet S6 – FOUNDATION SECTIONS AND DETAILS

A. MODIFIED detail 9 for clarity.

B. ADDED detail 10 for typical light pole foundation.

C. ADDED detail 11 for typical charging station pedestal footing.

D. ADDED detail 12 for HEAL lettering foundation.

Austin 811 Barton Springs Road, Suite 900, Austin, Texas 78704 p: 512.478.7286 f: 512.478.7441

San Antonio 4040 Broadway, Suite 300, San Antonio, Texas 78209 p: 210.224.6032 f: 210.224.6453

ARCHITECTURAL:

ITEM A1 Sheet A1.2 – ARCHITECTURAL SITE PLAN – AREA A

A. REVISED mobile unit charging pedestal.

B. MODIFIED keynote 175.

ITEM A2 Sheet A1.5 – ARCHITECTURAL SITE DETAILS

A. ADDED elevations, sections & detailing for charging pedestal.

ITEM A3 Sheet A3.1 – FLOOR PLAN

A. REVISED door swing for doors 1013 and 1002.

B. REVISED window tags.

ITEM A4 Sheet A4.1 – EXTERIOR ELEVATIONS

A. REVISED a curtain wall window at the North Exterior Elevation.

ITEM A5 Sheet A6.1 – EXTERIOR DETAILS

A. REVISED cement fiber panel soffit detail.

B. REVISED curtainwall at sill detail.

ITEM A6 Sheet A6.2 – EXTERIOR DETAILS

A. REVISED curtainwall details.

B. REVISED parapet plate detail.

C. REVISED light at soffit detail.

ITEM A7 Sheet A6.3 – EXTERIOR DETAILS

A. REVISED parapet EJ detail.

B. REVISED parapet detail at roof canopy.

ITEM A8 Sheet A6.4 – EXTERIOR DETAILS

A. REVISED existing canopy detail at corridor.

ITEM A9 Sheet A6.5 – PLAN DETAILS

A. REVISED detail 1.

ITEM A10 Sheet A7.4 – EXTERIOR FRAME TYPES

A. REVISED storefront frames to curtainwall.

ITEM A11 Sheet A9.1 – REFLECTED CEILING PLAN

A. REVISED ceiling grid and lighting in Cashier 1016.

B. REVISED ceiling grid and lighting in Ambulance Vestibule 1068.

C. REVISED RCP legend.

ITEM A12 Sheet A9.2 – ENLARGED REFLECTED CEILING PLAN

A. ADDED dimensions to Enlarged Ceiling Plan – Waiting.

Austin 811 Barton Springs Road, Suite 900, Austin, Texas 78704 p: 512.478.7286 f: 512.478.7441

San Antonio 4040 Broadway, Suite 300, San Antonio, Texas 78209 p: 210.224.6032 f: 210.224.6453

ITEM A13 Sheet A10.1 – ROOM FINISH PLAN

A. REVISED Room Finish Tag for METERING ROOM 1002.

B. ADDED Keynote Legend to sheet.

FIRE PROTECTION:

ITEM FP1 Sheet FP1.1 – FIRE PROTECTION NOTES, SYMBOLS AND ABBREVIATIONS

A. REVISED notes.

PLUMBING:

ITEM P1 Sheet P1.1 – PLUMBING NOTES, SYMBOLS AND ABBREVIATIONS

A. REVISED notes.

ITEM P2 Sheet P3.0 – PLUMBING UNDERFLOOR PLAN

A. ADDED pipe tags.

ITEM P3 Sheet P3.1 – PLUMBING PLAN

A. ADDED keynotes.

ITEM P4 Sheet P5.1 – PLUMBING RISER DIAGRAMS

A. ADDED sheet.

MECHANICAL:

ITEM M1 Sheet M3.1 – MECHANICAL DUCTWORK PLAN

A. ADDED Keynotes 9-11.

B. REVISED ductwork in EVS 1062 and Staff Lounge 1043.

C. REVISED ductwork in south east corner.

D. REVISED V2-09 size.

E. REVISED V2-01 thermostat location.

F. REVISED static pressure sensor locations in ductwork.

G. REVISED ductwork near Ambulance Vestibule 1068.

ITEM M2 Sheet M3.5 – MECHANICAL ROOF PLAN

A. ADDED keynote #5.

B. ADDED outside air intake clearance boundaries.

ITEM M3 Sheet M7.2 – MECHANICAL CONTROLS

A. REMOVED detector from controls diagram.

B. ADDED VAV control serving vestibule notes.

Austin 811 Barton Springs Road, Suite 900, Austin, Texas 78704 p: 512.478.7286 f: 512.478.7441

San Antonio 4040 Broadway, Suite 300, San Antonio, Texas 78209 p: 210.224.6032 f: 210.224.6453

ITEM M4 Sheet M8.1 – MECHANICAL SCHEDULES

A. ADDED ‘pre/final’ to rooftop AC schedule.

B. REVISED values in the VAV terminal schedules.

C. REVISED V2-09 unit size.

D. REVISED notes on VAV terminal schedules.

E. REVISED area served on electric unit heater.

ELECTRICAL:

ITEM E1 Sheet E1.3 – ELECTRICAL SITE PLAN

A. REVISED utility poles to be dimensional aligned with Centerpoint Energy drawings.

B. CLARIFIED lighting and relay panel circuit.

C. DELETED (2) light poles at south parking lot.

D. REVISED light pole locations at north parking lot.

E. ADDED power for monument sign.

F. ADDED keyed notes 7-10.

ITEM E2 Sheet E3.1 – ELECTRICAL POWER PLAN

A. Circuit numbers have been updated but not clouded for clarity.

B. Elec Rm 1013: ADDED lighting inverter locations.

C. Elec Rm 1030: ADDED 3rd panelboard section.

ITEM E3 Sheet E3.2 – ELECTRICAL POWER PLAN - EQUIPMENT

A. Circuit numbers have been updated but not clouded for clarity.

B. ADDED keyed note 10 for VAV controls circuit.

ITEM E4 Sheet E4.1 – LIGHTING PLAN

A. X

ITEM E5 Sheet E5.1 – SPECIAL SYSTEMS PLAN

A. Utility 1072: ADDED fire pull station.

B. AIDR 1064 & IDR 1066: ADDED smoke detector and fire pull station. REVISED to AV device.

ITEM E6 Sheet E7.1 – ELECTRICAL RISER DIAGRAM AND PANEL SCHEDULES

A. Detail 1: ADDED available fault current calculations. REVISED Panel ‘HL1’ multipoint meter to be external.

B. Panel ‘MDP2’ and ‘HL1’: CLARIFIED ‘MPM’ description.

C. Panel ‘HQ1’: ADDED available fault current calculations.

ITEM E7 Sheet E8.1 – ELECTRICAL EQUIPMENT AND LIGHTING SCHEDULES

A. REVISED Light Fixture Schedule.

Austin 811 Barton Springs Road, Suite 900, Austin, Texas 78704 p: 512.478.7286 f: 512.478.7441

San Antonio 4040 Broadway, Suite 300, San Antonio, Texas 78209 p: 210.224.6032 f: 210.224.6453

ITEM E8 Sheet E9.1 – ELECTRICAL DETAILS

A. DELETED detail 1.

TECHNOLOGY:

ITEM T1 Sheet T2.1 – TECHNOLOGY OVERALL FLOOR PLAN

A. ADDED overhead cable tray section through Consultation 1015 as requested by

Harris Health IT.

ITEM T2 Sheet T2.2 – TECHNOLOGY FLOOR PLAN

A. UPDATED Keyed Note #19. Removed “DATA CABLE FOR PRIMAX SYSTEM” and changed verbiage to “NOT USED”.

ITEM T3 Sheet T3.0 – TECHNOLOGY ENLARGED VIEWS

A. REVISED Details #1 and #2 - Moved equipment rack row 5 feet plan east closer to the entrance door and switched positions of Rack #1 and Rack #2 as requested by Harris Health IT.

END OF ADDENDUM NO. 01

ADDENDUM 001 SUNSET HEIGHTS URGENT CARE

JANUARY 16, 2026 PROJECT NO. 2321.06

TABLE OF CONTENTS 00 10 00 - 1/5

TABLE OF CONTENTS

DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS

00 01 07 Seals Page 00 10 00 Table of Contents 00 31 32 Geotechnical Data 00 31 32a Geotechnical Report

DIVISION 01 GENERAL REQUIREMENTS

01 10 00 Summary 01 23 00 Alternates 01 25 00 Substitution Procedures

Substitution Request Form-Bidding Phase Substitution Request Form-Executed Contract

01 26 00 Contract Modification Procedures 01 29 00 Payment Procedures 01 31 00 Project Management and Coordination 01 32 00 Construction Progress Documentation 01 32 33 Photographic Documentation 01 33 00 Submittal Procedures 01 40 00 Quality Requirements 01 43 39 Mockups 01 50 00 Temporary Facilities and Controls 01 50 10 Temporary Project Identification Signage 01 60 00 Product Requirements 01 73 00 Execution 01 74 19 Construction Waste Management and Disposal 01 77 00 Closeout Procedures 01 78 23 Operation and Maintenance Data 01 78 39 Project Record Documents 01 79 00 Demonstration and Training 01 91 00 Commissioning

(DIVISION 02 EXISTING CONDITIONS – NOT USED)

DIVISION 03 CONCRETE

03 30 00 Cast-in-Place Concrete

DIVISION 04 MASONRY

04 20 00 Unit Masonry

DIVISION 05 METALS

05 12 00 Structural Steel Framing 05 31 00 Steel Decking 05 40 00 Cold-Formed Metal Framing 05 50 00 Metal Fabrications

01/16/2026

TABLE OF CONTENTS 00 10 00 - 2/5

DIVISION 06 WOOD, PLASTICS, AND COMPOSITES

06 10 00 Rough Carpentry 06 16 00 Sheathing 06 40 23 Interior Architectural Woodword 06 41 16 Plastic-laminate-faced Architectural Cabinets 06 64 00` Resin Fabrications

DIVISION 07 THERMAL AND MOISTURE PREVENTION

07 14 16 Cold Fluid-applied Waterproofing 07 21 00 Thermal Insulation 07 26 00 Under Slab Vapor Barriers 07 27 26 Fluid-Applied Membrane Air Barriers 07 42 13.23 Metal Composite Material Fabrications 07 46 46 Fiber-Cement Siding 07 54 23 Thermoplastic-Polyolefin (TPO) Roofing 07 62 00 Sheet Metal Flashing and Trim 07 72 00 Roof Accessories 07 84 00 Firestopping Systems 07 84 00a Firestopping Systems Schedule 07 92 00 Joint Sealants 07 92 19 Acoustical Joint Sealants 07 95 13.13 Interior Expansion Joint Cover Assemblies

DIVISION 08 OPENINGS

08 11 13 Standard Steel Doors and Frames 08 14 12 Plastic-Laminate-Faced Flush Wood Doors 08 14 73.20 Sliding Door Assemblies 08 31 13 Access Doors and Frames 08 33 23 Overhead Coiling Doors 08 42 29 Automatic Entrances 08 44 13 Glazed Aluminum Curtain Walls 08 71 00 Door Hardware – Harris Health Standard 08 71 00 Door Hardware 08 80 00 Glazing

DIVISION 09 FINISHES

09 22 16 Non-Structural Metal Framing 09 29 00 Gypsum Board 09 30 00 Tiling 09 51 13 Acoustical Panel Ceilings 09 65 13 Resilient Base and Accessories 09 65 16 Resilient Sheet Flooring 09 68 13 Tile Carpeting 09 72 00 Wall Coverings 09 91 13 Exterior Painting 09 91 23 Interior Painting

DIVISION 10 SPECIALTIES

10 11 00 Visual Display Units 10 14 19 Dimensional Letter Signage 10 14 23 Panel Signage

TABLE OF CONTENTS 00 10 00 - 3/5

DIVISION 10 SPECIALTIES—CONTINUED

10 21 23 Cubicle Curtains and Tracks 10 26 00 Wall Protection 10 28 00 Toilet and Bath Accessories 10 44 13 Fire Protection Cabinets 10 44 16 Fire Extinguishers 10 45 00 Automated External Defibrillator Cabinets 10 51 13 Metal Lockers 10 73 43 Manufactured Aluminum Canopies 10 90 00 High Security Entry Systems

(DIVISION 11 EQUIPMENT – NOT USED)

DIVISION 12 FURNISHINGS

12 24 13 Roller Window Shades 12 36 23.13 Plastic-Laminate-Faced Countertops 12 36 61.16 Solid Surfacing Countertops

(DIVISION 13 THOUGH DIVISION 14 – NOT USED)

DIVISION 21 FIRE SUPPRESSION

21 00 01 Basic Fire Protection Requirements 21 05 00 Common Work Results for Fire Suppression 21 05 53 Identification for Fire Protection Piping and Equipment 21 13 13 Wet-Pipe Sprinkler Systems 21 13 16 Dry-Pipe Sprinkler Systems 21 13 19 Preaction Sprinkler Systems

DIVISION 22 PLUMBING

22 00 01 Basic Plumbing Requirements 22 05 29 Hangers and Supports for Plumbing Piping and Equipment 22 05 53 Identification for Plumbing Piping and Equipment 22 07 00 Plumbing Insulation 22 11 00 Facility Water Distribution 22 13 00 Facility Sanitary Sewerage 22 14 00 Facility Storm Drainage 22 33 00 Electric Domestic Water Heaters 22 40 00 Plumbing Fixtures

DIVISION 23 HEATING, VENTILATING AND AIR CONDITIONING

23 00 01 Basic HVAC Requirements 23 05 13 Common Motor Requirements for HVAC Equipment 23 05 29 Hangers and Supports for HVAC 23 05 48 Vibration Controls for HVAC Piping and Equipment 23 05 93 Testing, Adjusting and Balancing for HVAC 23 07 00 HVAC Insulation 23 09 23 Building Automation Systems for HVAC 23 31 00 HVAC Ducts and Casings 23 33 00 Air Duct Accessories 23 34 00 HVAC Fans 23 36 00 Air Terminal Units

TABLE OF CONTENTS 00 10 00 - 4/5

DIVISION 23 HEATING, VENTILATING AND AIR CONDITIONING – CONTINUED

23 37 00 Air Outlets and Inlets 23 81 03 Packaged Rooftop Air Conditioning Units Up to 25 Tons 23 81 26 Split-System Air Conditioners and Heat Pumps 23 82 19 Terminal Heat Transfer Units

(DIVISION 25 INTEGRATED AUTOMATION – NOT USED)

DIVISION 26 ELECTRICAL

26 00 01 Basic Electrical Requirements 26 05 03 Equipment Wiring Connections 26 05 05 Electrical Demolition 26 05 19 600-Volt Building Wire and Cable 26 05 26 Grounding and Bonding for Electrical Systems 26 05 29 Hangers and Supports for Electrical Systems 26 05 33 Raceway Systems 26 05 43 Underground Ducts 26 05 53 Identification for Electrical Systems 26 05 73 Short Circuit/Coordination Study and Arc Flash Hazard Study 26 09 23 Lighting Control System 26 22 13 Low-Voltage Transformers 26 24 16 Panelboards 26 27 26 Wiring Devices 26 28 13 250- & 600-Volt Fuses 26 28 16 Enclosed Switches and Circuit Breakers 26 29 16 Enclosed Contactors 26 29 23 Variable Frequency Motor Controllers 26 41 13 Facility Lightning Protection 26 43 13 Surge Protective Devices 26 51 16 Interior Lighting 26 56 16 Exterior Lighting

DIVISION 27 COMMUNICATIONS

27 05 00 Common Work Results – Harris Health Standard 27 05 00 Common Work Results – (Combs) 27 05 26 Grounding and Bonding 27 05 33 Pathways for Communications Systems 27 05 53 Identification for Communications Systems 27 11 00 Communications Equipment Room Fittings 27 13 00 Communications Backbone Cabling 27 15 00 Communications Horizontal Cabling 27 16 00 Communications Connecting Cords, Devices and Adaptors 27 20 00 Data Communications Equipment 27 40 00 Audio-Video Systems 27 51 17 Overhead Paging Systems

DIVISION 28 ELECTRONIC SAFETY AND SECURITY

28 13 00 Security and CCTV Systems – (Combs) 28 13 00 Security and CCTV Systems – Harris Health Standard 28 31 00 Fire Alarm and Smoke Detection (NEW)

TABLE OF CONTENTS 00 10 00 - 5/5

DIVISION 31 EARTHWORK

31 11 00 Cleaning and Grubbing 31 22 13 Site Grading 31 23 33 Trenching, Backfilling and Compaction 31 25 00 Erosion and Sedimentation Control 31 32 13.19 Lime Stabilization 31 41 33 Trench Safety

DIVISION 32 EXTERIOR IMPROVEMENTS

32 13 13 Concrete Pavement 32 17 23.13 Painted Pavement Markings 32 31 19 Decorative Metal Fences and Gates 32 84 00 Irrigation 32 90 00 Planting

DIVISION 33 UTILITIES

33 10 00 Water Distribution 33 30 00 Sanitary Sewer 33 40 00 Drainage

END OF DOCUMENT

BUILDING AUTOMATION SYSTEMS FOR HVAC 23 09 23 - 1/50

SECTION 23 09 23 - BUILDING AUTOMATION SYSTEMS FOR HVAC

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General Conditions and Division 01 Specification Sections, apply to this Section.

B. Refer to associated equipment specification sections as they apply to BMS interface requirements herein as they are shown in the controls sheets in the Drawings.

C. Division 01 - Submittal Procedures

D. Division 01 - Temporary Facilities and Controls

E. Division 01 - Execution and Closeout Requirements

F. Division 01 - Commissioning

G. Section 07 84 00 - Fire-stopping.

H. Section 23 05 53 - Identification for HVAC Piping and Equipment

I. Section 23 05 93 - Testing, Adjusting and Balancing for HVAC

J. Section 23 08 00 - Commissioning of HVAC

K. Section 26 00 01 - Basic Electrical Requirements.

L. Section 26 05 03 - Equipment Wiring Connections.

M. Section 26 05 19 - 600-Volt Building Wire and Cable.

N. Section 26 05 53 - Identification for Electrical Systems.

1.2 SYSTEM DESCRIPTION

A. General:

1. Building Automation Controls shall be designed, procured, installed, and commissioned by an experience Controls Installing Contractor (CIC) following these and other approved specifications.

2. The control system network of BACnet controllers, an Enterprise system server, enterprise network infrastructure, and web service user interfaces shall integrate seamlessly into the site IT infrastructure. Network shall be composed of the Multitier Model as described in this document.

B. Tier 1: Enterprise IP Network Tier. This tier includes devices directly connected to the Owner’s enterprise network, including the Enterprise server, graphical front end, data historian, SQL server, OPC Server, etc.; peripheral devices such as printers, Web-client computers, Master Operator Workstations (B-OWS), Wi-Fi enabled cellphones or tablets; network routers, and BAS controllers (B-BCs, B-CACs, B-ASCs, ) and devices that have IP connectivity. Includes IEEE

802.3, 1000BASE-X, 1000BASE-SX, 1000BASE-T.

BUILDING AUTOMATION SYSTEMS FOR HVAC 23 09 23 - 2/50

C. Tier 2: Building- or Facility-Level IP Device Network. This tier includes VLAN IP devices connected to the IP network tier via a switch dedicated to the BAS device network or to enterprise managed switches under Owner’s IT department control. In general this may include Operator Workstations (B-OWS) for sub-divisions of a master network (e.g. separate buildings on a campus system) and BAS controllers (B-CACs, B-ASCs), gateways to non-BACnet protocol and other devices that have IP connectivity. This may include equipment containing IP NIC such as chillers, VFDs, boilers, lighting control, compressors, energy meters, etc. Includes IEEE 802.3, 10BASE- T, 100BASE-T. Tier 2 network cabling costs shall be obtained from the Owner’s approved network cabling contractor for those portions of the work that require integration into the Owner’s network infrastructure.

D. Tier 3: Non-IP-Based BAS Controller Network Tier or BAS Controller Tier. This tier includes devices and actuators that are not IP based. These devices should be networked using non-IP wired networks such as BACnet MS/TP, LON TP/FT-10, Modbus, or other approved proprietary media types. This tier also includes any sensors and actuators that are directly connected to a BAS controller or are required for a BAS device, such as a boiler or chiller, which in turn is networked into the non-IP-BAS controller network. Device planned in Tier 2 that are non-IP based will be assigned to Tier 3. Other Tier 3 devices may include terminal box actuator/controllers, room thermostats, occupancy sensors, networked remote I/O, networked sensors, etc. Preferred ISO 8802-2 Type 1, EIA-485 physical layer

E. Enterprise IT Integration Requirements. CIC shall coordinate their work with the Owner’s IT department to provide a seamless integration into the Owner’s enterprise network. Integration shall be coordinated with Owner’s IT group regarding IT requirements for the following:

1. Network switches and hubs (coordinate scope of work with Owner)

2. Network routers (coordinate scope of work with Owner)

3. Gateways: In general gateways shall be avoided

4. Security firewalls

5. Network IP address allocation, VLAN and static IP blocks

6. Port blocking/unblocking/binding

7. Password/pass phrase requirements, strength, periodic changes

8. Use of antivirus, antispam, and adware blocking, and logon security

9. Server security requirements

10. Server backup and maintenance requirements

11. System gateway requirements

F. System Architecture - refer to Controls Drawings.

G. Remote accessing outside of the Owner’s enterprise network shall be prohibited if security features do not meet the Owner’s IT standards. CIC shall identify requirements for remote access in their proposal. Limited access via VPN or limited duration “guest access” may be provided.

Owner may not approve the request and no additional compensation will be provided.

H. Significant design activities will be required by the CIC to establish detailed requirements for trending, alarming, operator notification and escalation, graphics screens, etc. CIC shall provide sufficient time and resources to meet with the Owner’s team to collect necessary input to complete these design activities. CIC shall have sufficient resources to conduct on-site meetings with the Owner’s team to establish minimum requirements, submittal review of Owner feedback, and publication of a Basis of Design document covering the various aspects of the project.

I. Performance Monitoring: The BAS will provide the specified performance monitoring functionality including required monitoring points and performance metrics, improved through system accuracy, data acquisition and data management capabilities, and required graphical and data displays.

BUILDING AUTOMATION SYSTEMS FOR HVAC 23 09 23 - 3/50

J. System Performance:

1. The communication speed between the BACnet controllers, Network interface devices, Enterprise server, and operator interface devices shall be sufficient to ensure fast system response time under any loading condition. Contractor shall submit guaranteed response times with Shop Drawings including calculations to support the guarantee. In no case shall delay times between an event, request, or command initiation and its completion be greater than those listed herein:

a. 5 seconds between a Level 1 (critical) alarm occurrence and enunciation at operator workstation.

b. 10 seconds between a Level 2 alarm occurrence and enunciation at operator workstation.

c. 20 seconds between a Level 3/4 alarm occurrence and enunciation at operator workstation.

d. 10 seconds between an operator command via the operator interface to change a setpoint and the subsequent change in the controller.

e. 5 seconds between an operator command via the operator interface to start/stop a device and the subsequent command to be received at the controller.

f. 10 seconds between a change of value or state of an input and it being updated on the operator interface.

g. 10 seconds between an operator selection of a graphic and it completely painting the screen and updating at least ten (10) points.

2. Reporting Accuracy. System shall report values with minimum end-to-end accuracy listed in Table 1.

3. Control Stability and Accuracy. Control loops shall maintain measured variable at setpoint within tolerances listed in Table 1 under “Accuracy Required for Control.”

TABLE 1 Sensors, Meters, Calculated Values, and Required Accuracies

Sensor Type Range Min. Accuracy

Duct/AHU Temperature 40 - 130°F ± 0.5°F

Room Temperature 50 - 85°F ± 0.5°F

Outside Air Temperature -20 - 120°F ± 0.5°F

Humidity 0 – 100% ± 3% RH

Duct Static Pressure 0 – 3.0” w.g. ± 1% full scale per 50°F

Space Static Pressure -0.25” – 0.25” w.g. ± 1% full scale per 50°F

Current Sensor Sized for application ± 1% full scale

Power (kWh) Sized for application ± 2% full scale (at 1.0 PF)

Air Flow 700 – 4,000 fpm ± 2% full scale

CO2 Sensors 0 – 2,000 PPM ± 3% full scale

1.3 CONTROL AND POWER WIRING

A. All electrical control wiring, conduit, raceway and cable systems shall be furnished and installed under this section.

1. Wiring of interlock systems includes, but is not limited to, all fan interlocks and motorized dampers. See schedule on the drawings for motorized dampers to be interlocked.

2. Wiring of control equipment includes, but in not limited to, all necessary relays, switches and other equipment specified or required to accomplish interlocks and control sequences specified.

3. Wiring shall conform to National Electrical Code and ANSI C2.

BUILDING AUTOMATION SYSTEMS FOR HVAC 23 09 23 - 4/50

B. Low voltage wiring shall be run in EMT conduit in exposed areas, attic spaces, and in vertical risers. Low voltage wiring shall be run in Schedule 80 PVC conduit outside. Line voltage control wiring shall be run in EMT conduit.

C. All 120V power wiring required to make the control system completely functional, which is not shown on the electrical drawings shall be provided by the controls contractor in accordance with Division 26 specification requirements.

1.4 REFERENCE STANDARDS

A. The latest published edition of a reference shall be applicable to this Project unless identified by a specific edition date.

B. All reference amendments adopted prior to the effective date of this Contract shall be applicable to this Project.

C. All materials, installation and workmanship shall comply with the applicable requirements and standards addressed within the following references:

D. American Society of Heating, Refrigeration and Air Conditioning Engineers (ASHRAE).

1. ASHRAE 135: BACnet - A Data Communication Protocol for Building Automation and Control Networks (2019 edition, including all current addenda and annexes).

2. ASHRAE Guideline 13, Specifying Direct Digital Control Systems (2015 edition)

3. ASHRAE Guideline 36, High Performance Sequences of Operation for HVAC Systems

(2018 edition)

E. Electronics Industries Alliance:

1. EIA-458: Standard Optical Fiber Material Classes and Preferred Sizes.

2. EIA-485: Standard for Electrical Characteristics of Generator and Receivers for use in

Balanced Digital Multipoint Systems.

3. EIA-472: General and Sectional Specifications for Fiber Optic Cable.

4. EIA-475: Generic and Sectional Specifications for Fiber Optic Connectors and all Sectional

Specifications.

F. Underwriters Laboratories:

1. UL 916: Energy Management Systems.

2. UUKL 864: UL Supervised Smoke Control if the BAS is used for smoke control.

G. NEMA Compliance:

1. NEMA 250: Enclosure for Electrical Equipment.

2. NEMA ICS 1: General Standards for Industrial Controls.

H. NFPA Compliance:

1. NFPA 90A "Standard for the Installation of Air Conditioning and Ventilating Systems" where applicable to controls and control sequences.

2. NFPA 70 National Electrical Code (NEC).

I. Institute of Electrical and Electronics Engineers (IEEE)

BUILDING AUTOMATION SYSTEMS FOR HVAC 23 09 23 - 5/50

1. IEEE 142: Recommended Practice for Grounding of Industrial and Commercial Power Systems.

2. IEEE 802.3: CSMA/CD (Ethernet – Based) LAN.

3. IEEE 802.4: Token Bus Working Group (ARCNET – Based) LAN.

4. IEEE 519: Recommended Practices and Requirements for Harmonic Control in Electric

Power Systems.

J. Building Codes and local ordinances – refer to list on the Drawings.

1.5 SYSTEM REQUIREMENTS

A. BACnet IP Devices. Devices designed to connect directly to a BACnet network using the IP Protocol and in conformance with the requirements outlined in the BACnet Standard.

B. BACnet MS/TP devices. The use of BACnet device deployed in a master/slave network connection shall be for those systems of a non-critical nature, see network architecture. BACnet MS/TP may also be used for higher levels system but must be in a peer-to-peer on a sub LAN.

C. All BACnet devices supplied shall be BACnet Testing Laboratory (BTL) certified as required unless approved in advance. The component shall bare the BTL Mark Label.

D. Failure of single component shall not interrupt normal operation of other components. Supplier shall identify consequences of controller and device failures in the appropriate system Sequence of Operation.

E. BACnet Device Selection

1. Reference the Proposed System Architecture Drawings. The CIC shall supply a BAS that meets the intent of the propose system architecture with regards to BACnet device types.

Alternate bid may be offered though the Owner may reject any bids failing to meet the intent of the proposed system architecture.

2. Supplier shall select BACnet Devices that provide a high-performance solution with minimum latency for data handling, built-in applications, alarm and event management, trending, scheduling, device and network management, etc. BACnet Controller devices with I/O or memory limits should be selected where there is sufficient processing and memory capability to handle significant data transmission overhead associated with multiple complex control algorithms, large quantities of data, alarms, events, messages, trending and web service requests. Controller Object Capacity.

3. Suppliers who offer multiple versions of Building Controllers (B-BC) and Custom Application Controllers (B-CAC) should select these controllers such that performance is not compromised when significant amounts of trend data, alarm data, event data, etc. are being processed or communicated to other devices., In particular they should be selected to allow for sufficient data storage in the event of a loss of communication to archival or supervisory storage.

4. The selection of the various BACnet Devices shall be at the discretion of the supplier but proposed system architecture is the Owner’s preferred design. Acceptance of B-BC versus B-CAC will be contingent upon the specific features offered by each supplier. Do not supply B-ASC controllers where B-CAC controllers have been specified except as an alternate.

a. BACnet specifications for B-BC, B-CAC, B-ASC shall meet the minimum requirements for support BIBBS. If the supplier’s version of a given controller exceeds the BACnet BIBB specification this should be noted in their justification of a given controller type.

BUILDING AUTOMATION SYSTEMS FOR HVAC 23 09 23 - 6/50

5. For each BACnet Device suppliers selects they shall indicate in their bids if there are higher performance models of the same BACnet device type available and the additional cost to provide this unit in lieu of the unit they have in their base bid

F. Operator Workstations. Operator workstation software may be resident at the B-BC or B-CAC controller or in other standalone configurations. This hardware shall be loaded as needed with any operation workstation software. CIC shall support Owner with loading of software.

G. The Enterprise Server shall collect and store data from every connected site for a minimum of five years. CIC shall submit with their bid the quantity of data storage needed to meet this requirement for initial phase plus the long term Owner’s need (all campus building plus offsite building). This storage shall be supplied by the Owner and be attached to the Owner’s Tier 1 Enterprise network. Alternate bid shall allow for Tier 1 data storage provided by the CIC, or Tier 2 data storage supplied by the CIC.

H. Data trending data shall be continuous and lapses in trend data due to communication failures should be avoided. Trend data stored at a local controller shall be in non-volatile memory and loss of network communication shall not cause the loss of any trend data. All BAS objects shall be trended.

1.6 DESIGN REQUIREMENTS OF THE CONTROLS INSTALLING CONTRACTOR (CIC)

A. Drawings and Narratives – Create, update, and prepare design documents and submit for approval.

1. System Architecture Drawing. Graphical representation of the overall system configuration indicating Tier 1, 2, and 3 networks and the configuration of control cabinets.

2. Network Drawings. One-line diagram indicating schematic locations of all control units, workstations, network interface devices, gateways, etc. Update provided drawing Indicating network number, device ID, address, device instance, MAC address, IP, drawing reference number, cable and port numbers, and controller type for each control unit.

3. P&ID Drawing.

4. Loop Drawing.

5. Panel Drawing.

6. Floor Plans showing control device location

7. Analog Loop Diagrams:

a. Show all devices requiring electrical connections.

b. Identify all wire and terminal numbers.

c. Identify Controller I/O addresses.

d. Identify location of loop power supply.

e. Identify field devices, back-of-panel devices, and front-of panel devices.

f. Show tabular summary of transmitter output capability, input impedance of each receiver, total loop impedance, and reserve output capacity.

g. Reference tag number where assigned.

8. Control Panel Construction Drawings:

a. Scaled drawings of all control panels and enclosures.

b. Front panel elevation complete with nameplate legend.

c. Back panel elevation complete with schedule of devices.

9. Control Panel Power and Environmental Requirements:

a. Identify voltage and Ampacity requirements.

BUILDING AUTOMATION SYSTEMS FOR HVAC 23 09 23 - 7/50

b. Show sizing calculations for environmental controls (ventilation, heat, air conditioning).

10. Control Panel Schematic Wiring Diagrams:

a. Ladder type schematic diagrams.

b. Show all devices requiring electrical connections.

c. Identify all wire and terminal numbers.

d. Identify Controller I/O addresses.

e. Reference tag number where assigned.

f. Cross-reference all relay contacts and coils.

g. Identify switching action on all switching devices.

h. Common diagrams will not be accepted unless they are provided with list all of the units that share the diagram and what each unit serves.

i. Identify special installation procedures such as grounding.

11. Control Panel Plumbing Diagrams:

a. Show all devices requiring plumbing connections (air or liquid).

b. Show pipe/tube sizing.

c. Show all control devices (regulators, filters, etc.).

12. Interconnecting Wiring Diagrams:

a. Show all interconnections between control panels.

b. Show all interconnections between control panels and motor control centers.

c. Show all interconnections between control panels and field devices.

d. Show all interconnections between motor control centers and field devices.

e. Identify all wire and terminal numbers, including field terminal junction box terminals.

13. Control Device Installation Details

14. Sequence of Operation (SOO) shall be reviewed in conjunction with the P&IDs and legacy control schematics. Conflicts shall be noted and a resolution submitted. For applicable equipment and systems ASHRAE Guideline 36, High Performance Sequences of Operation for HVAC Systems shall be the basis SOO. The CIC’s SOO shall contain the following sections:

a. Drawing References

b. General Description of the control

c. Equipment List

d. Instrument List

e. Panel Designations

f. Failure Analysis Summary

g. Control Detail

h. Loop Descriptions

i. Control and Alarm Setpoints

j. Trending points and trend parameters

k. SCADA Interface Screen(S)

15. Instrument Location Drawings.

16. Instrumentation and Data Point Index. Contractor shall submit in table format the following information for each instrument and data point. The table is to be reviewed and approved by the Owner’s representative prior to hardware and software installation and programming.

a. Point/Variable name

BUILDING AUTOMATION SYSTEMS FOR HVAC 23 09 23 - 8/50

b. Point description: provide building designation, system type, equipment type, engineering units, and functionality; include a description of its physical location

c. BACnet Object ID(s)

d. P&ID Drawing

e. SOO Number

f. Engineering Units at 0%

g. Engineering Units at 100%

h. Setpoint BACnet Object ID

i. Variable Type

j. Point Type

1) Bound or Polled

2) Digital Input

3) Digital Output

4) Analog Input

5) Analog Output

6) Virtual Point (Calculated)

k. Integration Requirement

1) Monitored

2) Controlled

3) Logged

4) Trended

5) Data trend interval

6) Number of samples stored in local controller before transfer to host computer/server database

7) Alarmed

8) Scheduled

9) Display (Local Panel)

10) Display (Operator GUI)

11) Graphic displays associated with point

l. Alarms

1) Low Limit

2) Low Low Limit

3) High Limit

4) High High Limit

5) Notification and Escalation Path

m. Sampling Rates

n. Data Buffer Limits

B. Integration of virtual data and data from non-BACnet devices

1. CIC shall design and supply an appropriate interface to networked BACnet devices containing virtual data points, non-BACnet third party systems which may include supply and installation of a gateway or application software such as OPC (PLCs (PLCopen / IEC 61131 compliant) to BACnet software.

2. CIC shall include sufficient BACnet Object IDs and virtual I/O to capture all of the needed data contained in the integrated systems. This estimate is for reference only and does not exclude CIC from providing requirements for all I/O as documented in the P&IDs.

3. CIC shall include necessary hardware and software for complete integration.

4. Integration shall include graphics, alarms, trending of all imported I/O.

BUILDING AUTOMATION SYSTEMS FOR HVAC 23 09 23 - 9/50

C. Point naming, system points: For project with a previous point naming standard such standard will be used, else the following.

1. BACnet network numbers and Device Object IDs shall be unique throughout the network.

2. All assignment of network numbers and Device Object IDs shall be coordinated with the

Owner.

3. Each Network number shall be unique throughout all facilities including future work and shall be assigned in the following manner unless specified otherwise:

4. Point names shall match point naming shown in points list in the Drawings.

5. Point names shall follow site standard. When site standard is not available naming should follow ISA naming convention or it may use following conventions: (AAAA-BBBBB-CCC-

DD-EEE)

a. Location in building or building identifier. (AAAA).

b. System (BBBBB).

c. Component or process of system (CCC).

d. Unique identifier (DD)

e. Type of variable (EEE) (Not an exhaustive list)

1) Temperature (T).

2) Humidity (H).

3) Setpoint (SP).

4) Pressure (P).

5) Damper Actuator (DA).

6) Current (I).

D. Alarms.

1. It is the Owner’s intent to have a comprehensive alarm management system that allows for advanced alarm notification via web services and email notification. CIC shall design an alarm handling system that incorporates:

a. Notification via OWS, via Owner’s email system, paging system, and mobile devices

b. Acknowledgement via OWS, via Owner’s email system, paging system, and mobile devices

c. Owner customizable escalation to selective users

2. CIC shall include necessary design and programming to support Owner’s alarm management requirements including development of unique alarm notification path scripts and unique alarm escalation path scripts. Scripts shall be reviewed and approved by the Owner and tested during startup and commissioning.

3. There shall be 4 Alarm priority levels,

a. Level 1: Life-safety; High Risk

b. Level 2: Critical Equipment Message (i.e., equipment failure)

c. Level 3: Urgent Message (i.e., comfort critical)

d. Level 4: Normal Message (i.e., preventative maintenance)

E. Graphic User Interface (GUI).

1. The following are intended as guidelines and CIC shall conduct design sessions with the Owner’s team to developed detailed GUI requirements. The CIC’s graphic design session will cover basic graphic design covering normal equipment operations, control of equipment, loop tuning, trending, alarm management, point/device-naming conventions etc. CIC may at their discretion employ the use of an approved third-party graphics developer who shall lead session associated with their scope. An approved agenda shall

BUILDING AUTOMATION SYSTEMS FOR HVAC 23 09 23 - 10/50

be issued prior to the meeting and expected deliverables and schedule shall also be presented.

2. GUI shall be high resolution with containing 3D and motion simulation, photo realistic simulations of equipment operations; dashboards, histograms, scatter plots, line plots, thermal analysis, etc. Graphics should visually convey necessary information to the user depending on the user’s need whether engineering, operations, maintenance, diagnostics, utilities, forecasting, etc.

3. GUI presentation should be independent of operator workstation whether multi-screen display, laptop PC, tablet, or mobile device the graphics should be visible to approved users and scaling to fit the display format.

4. GUI screens shall be divided into types (minimum): Operational, Engineering, Analytics, Maintenance, Diagnostics, Occupant Education, and others as recommended by the CIC

5. Navigation: CIC shall present screen navigation options, short cuts, web links, etc. to the Owner for review and incorporate into the finished GUI.

6. Object and Property Status and Control. Provide a method for the operator to view, and edit if applicable, the status of any object and property in the system. The status shall be available by menu, on graphics, or through custom programs.

7. Graphics shall be capable of using data collected by individual BACnet devices, supervisory software, third part data sets (virtual or physical) within the Owner’s enterprise system, and approved external data sources (e.g. weather data).

8. CIC shall create the following graphics screens

a. Provide graphics for all systems and floor plans of the building. Point information on the graphic displays shall dynamically update. Show on each graphic all input and output points for the system. Also show relevant virtual points such as set points, calculated values, effective heat and cooling setpoints, FDD data, runtime hours, maintenance hours, etc.

b. Summary tables and pages matching existing GUI practice.

c. Electrical, Gas, and Weather Graphic Display a. Provide a graphic display for each electrical meter and gas meter and weather data point(s) with a data table and a current 24-hour trend plot. Include data values for the following time periods; today, previous day, week to date, previous week, month to date, previous month, year to date, previous year

9. Architectural Plans. Provide 3D site plan and floor plans based upon Owner’s floor plans.

Floor plans shall be used for communication of various information including location of control devices, thermal performance, energy consumption, equipment location, system boundaries, area served. Provide ability to click and zoom into selected locations of each floor.

10. Operational Graphic:

a. Performance: Provide individual equipment graphics covering all control parameters.

1) Control Device: Mode (H-O-A), On-line, Off-line, deviation from setpoint,

2) Control Loops: Clicking on Loop control devices will show loop details, includes of P, I, D parameters, set point, process variable, auto/manual switch, loop output, a real time multi-pen trend of process variable, loop set point and loop output with history, text indicating whether the loop is direct or reverse acting.

3) Trim and Respond Logic (T&R SL) performance summary tables

4) Equipment Summary Tables and Floor Zone Heat Maps

5) System Summary Tables and Overview Graphic per system

6) All damper analog position displays will show percent open.

7) Lead/Lag for parallel equipment. Provide ‘button’-style graphical user interface objects to identify and change lead/lag equipment settings.

BUILDING AUTOMATION SYSTEMS FOR HVAC 23 09 23 - 11/50

8) All VFDs shall display percent of full speed, actual speed, and setpoint.

Energy per day, power, and other virtual data from VFDs used to convey critical operational data shall be available for display through equipment graphic link.

9) All tank analog level displays will show percent full.

b. Cost: When possible, provide operating cost visualization of each building, manufacturing space, equipment, group of equipment, and system.

c. Efficiency: Provide visualization of major equipment and systems concerning their operating performance such as COP, kW/cfm, ton-hours/area, cfm/area, utility data/occupant.

11. Calendars: Graphics shall contain calendar links allowing information to be easily filtered by day, week, month, calendar events (e.g., shutdowns, holidays, etc.)

12. Utility Data: Graphics shall convey utility consumption and cost data using local utility tariffs and input from utility meters (if allowed) or Owner’s on-site meters.

13. Weather Data. Provide weather data as measured by locally measured instruments or optional connection to weather data from approved meteorological sources (ref plans).

Weather data shall be presented discreetly on each screen with the ability to click and zoom in for detailed weather and historical weather data.

14. Dashboards.

a. Dashboards shall visualize various performance parameters associated with individual equipment, groups of similar equipment, systems, utilities, analytical data, etc.

b. Dashboards shall be organized by:

1) Total Campus

2) Building

3) Floor

4) Manufacturing Area

5) System

6) Equipment

15. Occupant Education. Provide up to (3) Graphics that increase occupant awareness through the display of building performance data, demonstrations of sustainable building features, tips on how to be efficient, and other interactive educational features. Graphics should be able to show comparative building performance data among buildings and/or floors. These graphics should be very high quality and resolution for display on very large display units or across multiple displays.

16. Diagnostics including Fault Detection and Diagnostics (FDD).

a. Provide dedicated graphic pages covering FDD data obtained from equipment containing FDD information such as RTUs, Chillers, etc.

b. Provide advanced diagnostics analysis for each of the various systems to help engineers and operators analyze performance parameters and identify anomalies.

Use the latest research on fault diagnostics to develop graphics that will visualize the various systems and their performance issues. Provide drill down into individual equipment performance with comparisons of similar equipment (e.g., chiller to chiller performance comparisons, VAV/FCU comparisons); inefficient operations such as simultaneous heating and cooling

17. Maintenance.

a. Provide summary tables indicating runtime, maintenance, and lifetime equipment hours following current site standards.

BUILDING AUTOMATION SYSTEMS FOR HVAC 23 09 23 - 12/50

b. Provide visualization of maintenance activities such as filter changes, sensor calibration, equipment overhauls, etc.

c. CIC shall identify needed input data to provide visualization, identify missing data, data links, normalization factors, etc. that prohibit any of the visualizations.

18. CIC shall identify needed input data to provide operating visualization, identify missing data, data links, normalization factors, etc. that prohibit any of the visualizations.

19. Normalization Metrics. Analytics shall include absolute data analysis as well as data normalized by area served, cost of operation, utilities consumed, cooling degree days, heating degree days, runtime, cycle time, etc.

20. Data Storage. Screen captures with data storage shall be implemented with simple on-screen button clicks capturing all important parameters and graphical elements.

21. Trend Graph Displays

a. Design trend graphs that shall allow Operators to define and trend multiple data points over time on a graph for visualization as a diagnostic tool to identify inter-relationships between systems and associated components for:

22. Graphics impact on system performance.

a. CIC shall summarize the data requirements for the graphics in their proposal

b. CIC shall summarize the total memory requirements and network burden, if any, due to graphics.

1.7 SCHEDULE REQUIREMENTS

A. Schedule submitted with bid: The Contractor shall submit with their bid a project schedule depicting the major elements of the scope of work with sufficient detail to evaluate the overall project plan proposed by the CIC and demonstrate meeting of Owner’s milestone schedule requirements. It shall include design, submittals, procurement, installation for each major piece of equipment, start-up, pre-commissioning, commissioning, and Acceptance, refer to bid tabulation tables. All required downtimes shall be noted in the schedule. Downtimes that impact the Owner’s manufacturing operation may not be approved and CIC shall be required to work around Owner’s schedule. No additional compensation shall be provided for work outside of normal working times unless previously approved.

B. A detailed project schedule using MS Project or other approved software shall be submitted within 2 weeks from the date of award for approval. The project schedule should be in alignment with the bid schedule. The schedule shall be updated every week thereafter by means of a progress report submitted to the Construction Manager, Owner, and/or Engineer.

C. The schedule shall include, but not be limited to, the following:

1. A network diagram consisting of intended sequence of work items, starting and completion dates for all main activities and constraints. Activities to be scheduled include design, submittals, material procurement and delivery, installation of hardware, installation of software, programming, shutdowns or disruptions of Owner equipment, equipment start-up, OAT, FAT, Commissioning, Close-out

2. Schedule should be based upon a 24 hour/ 7day work week noting working…