| File | Type | Posted |
|---|---|---|
| 19. Attachment B - IPP Payment Requirements.pdf | ||
| 19. 89503223QWA000463.pdf | ||
| 19. Attachment C - Wage Determinations.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment A
Statement of Work
89503223QWA000463
24 October 2022
DEPARTEMENT OF ENERGY
WESTERN AREA POWER ADMINISTRATION
ROCKY MOUNTAIN REGEON
STATEMENT OF WORK
Repairs to Montrose Manlift
I. Scope: Western Area Power Administration has a requirement to have various repairs made to the Montrose Electrician Versalift manlift (asset# N170139). The unit will be delivered to a vendor by WAPA personal and picked up when the repairs have been complete.
I. Background: The Montrose Electrician crew Versalift bucket truck was inspected during the annual boom inspection and found to have multiple deficiencies that need to be addressed prior to the unit being put back into service. Many of these deficiencies are safety violation and the unit is currently inoperable. The unit was also inspection by a qualified repair facility and additional items needing repair were found.
II. Requirements:
• REPLACE TORN UPPER CONTROL RUBBER BOOT.
• REPLACE DAMAGED FIBERGLASS JIB BOOM.
• REPLACE ALL RIBBON HOSES IN UPPER BOOM THROUGH CAT TRACK.
• RESEAL BOOM TIP AND ELBOW JUNCTION MANIFOLDS.
• REPLACE ALL DAMAGED AND WORN SAFETY AND INSTRUCTION DECALS AS NEEDED.
• REPLACE DAMAGED START/STOP SWITCH AND BOOT AT TAIL SHELF.
• REPLACE WORN NON-SLIP SURFACE AT PLATFORM STEP.
• REPAIR LOWER BOOM REST AND REPLACE PAD.
• REPLACE MISSING TOOL FITTING DUST CAPS.
• REPLACE MISSING COVER BOLT INSULATORS AT UPPER CONTROLS.
• RESEAL LEAKING ROTARY JOINT IN TURRET.
• REPLACE HYDRAULIC FILTERS AND FILL HYDRAULIC RESERVOIR TO PROPER LEVEL.
• REPLACE WEAR PADS.
• REPLACE DAMAGED AND LEAKING HYDRAULIC HOSES AT UPPER CONTROLS, LOWER
• CONTROLS AND AT BOOM TIP MANIFOLD.
• REPLACE LEAKING ATMOSPHERIC VENT.
• REPLACE TWO-SPEED THROTTLE AIR PLUNGER.
• REPLACE LEAKING HYDRAULIC PUMP.
• REPAIR HYDRAULIC LEAK AT SUCTION HOSE.
• REPLACE TORN OUTRIGGER CONTROL BOOTS.
• REPLACE DAMAGED UNIT DATA PLATE.
• REPLACE LEAKING DRIVERS AIR SEAT SWITCH.
• CLEAN OIL, DIRT AND DEBRIS FROM PEDESTAL AREA AND WASH AND CLEAN UNIT.
• PERFORM OPERATIONAL TESTS TO ENSURE THAT ALL REPAIRS HAVE RESOLVED THE
IDENTIFIED PROBLEMS AND THAT THE UNIT IS WORKING PROPERLY.
• DIELECTRIC TEST BOOMS AND LINER.
• PERFORM ANNUAL AERIAL LIFT INSPECTION
• PERFORM ALL REPAIRS AND TESTING IN ACCORDANCE WITH ANSI, OSHA, AWS, AND
MANUFACTURER REQUIREMENTS.
If any additional repairs are noticed when these repairs are performed, the contractor shall contact the Contracting Officer for approval prior to commencement of any additional work. Additional repairs are not authorized without the prior written approval from the Contracting Officer.
III. Unit Information
a. Model: Versalift VST6000I
b. Serial Number: 6J070050
II. Points of Contact:
Technical Point of Contact:
To be provided at time of award.
| 05. PWS_WTF_Phase_Shifters_OLTC_Maintenance.pdf |
| 1. GENERAL |
| 1.1. SCOPE OF WORK |
| 1.2. Background |