175 IDA LEWIS SOW 2125405Y6175M89006 MDE Exhaust Insulation.docx

DOCX document 27 KB Posted

Attached to
EXHAUST INSULATION
Solicitation number
70Z04025Q61038Y00
Issued by

About this file

This is a Statement of Work (SOW) for MDE Exhaust Insulation Blankets procurement for the USCGC 175' MMA IDA LEWIS Hull#1, solicitation number 2125405Y6175M89006. The project requires providing materials and labor to insulate both Main Diesel Engine exhaust systems from turbochargers up to the stack top, covering Port and Starboard exhaust piping, fittings, expansion joints, and silencers. The work is to be completed within a 6-week period of performance, with a tentative start/finish date of 11/3/25-12/15/25.

Key technical requirements include fabricating insulation blankets with proper thickness to ensure external surface temperatures do not exceed 130°F, despite operating exhaust gas temperatures ranging from 729°F to 900°F. The contractor must follow specific installation guidelines, use steel lacing for attachments, and coordinate closely with the Coast Guard Yard. Additional requirements include RAPIDGate security credentials, compliance with OSHA standards, ISO qualifications, and strict environmental protection protocols. The U.S. Coast Guard Surface Forces Logistics Center intends to award a Firm Fixed Price Purchase Order using simplified acquisition procedures and a best value basis.

View the file

Other files

File Type Posted
2125405Y6175M89006 RFQ.docx DOCX document
Smart Matrix Acquisition.GOV.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT of WORK For MDE Exhaust Insulation Blankets Procurement Request: 2125405Y6175M89006 USCGC 175’ MMA IDA LEWIS Hull#1 Yard POC: James Johnston (410) 636-3461 Tentative Start/Finish Date: 11/3/25-12/15/25 Period of Performance: 6 Weeks Provide all Materials & Labor for insulating Both 2 (ea.) Main Diesel Engine Exhaust from the turbochargers up to and including 01 Level, 02 Level, 03 Level terminating to the underside of Stack Top in the plenum space.

The exhaust insulation blankets and pads are required upon Shipyards completing the installation of:

Port and Stbd MDE 10” Exhaust Piping, Fittings, Expansion Joints and Silencers Please use the Following drawing(s):

· 175-WLM-259-005, Rev C, 2000, Combustion Exhaust A&D, Hull Block 970

· 175-WLM-259-001, Rev A, 1994, Combustion Exhaust Diagram 175-WLM-508-02 provided as guidance for the manufacturing of piping insulation and pads. Materials do not have to be 100% exact, they can be equal too.

General Information:

All exhaust piping, including mufflers and flexible joints, shall be insulated in accordance with MIL-STD-769J or Equal to Industry standard. For all piping, the insulation should have proper thickness for all temperature ratings for system to be insulated.

1) External surface temperature for exhaust piping shall not exceed 130 F. Operating exhaust gas temperatures range from 729 F. to 900 F.

2) All insulation blankets shall be fabricated and installed with proper lagging anchors and attachments. The insulation blankets shall be attached with steel lacing.

3) Any Newly Manufactured Flange Materials and Expansion Joint materials (Raw/Live fibrous insulation) can be installed/ Dry fit up for measurement purposes but cannot stay in place. The removable Flange Pads must be clearly identified, labeled and placed in such a position that it is well coordinated with Yard and Ships Forces for ease of install. When Operational Testing is taking place, the contractor must be present within 48-72hours to reinstall all associated removable pads/blankets in their final designated spots. The Ship Superintendent will give the final blessing.

It is recommended to take measurements to manufacture the pads after CG Yards installation of all exhaust piping, brackets, and expansion joints are completely installed. Shipyard Forces will have Expansion Joints removed due to commercial brush cleaning. Please note, the drawings depict the actual representation of what is currently installed and no deviations to supports or piping mods will be made during this CG Yard Dry-dock.

All work shall be completed in a timely and efficient manner. The contractor shall communicate all work or changes via Contracting Officer and Ship’s Superintendent.

FAR 52.237-1 Site Visit: Offerors or quoters are urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after contract award.

Controlled Unclassified Information: JCP certification is required for United States (U.S.) or Canadian contractors who wish to obtain access to unclassified technical data disclosing militarily critical technology with military or space application that is under the control of, or in the possession of the U.S. Department of Defense (DOD) or the Canadian Department of National Defense (DND).

ORAL MODIFICATION: No oral statement of any person other than the contracting officer shall in any manner or degree, modify, or otherwise affect the terms of this contract.

ACCEPTANCE CRITERIA: Criteria evaluated for payment approval. The government will review work in its entirety prior to issuing invoice approval.

GOVERNMENT FURNISHED ITEMS AND SERVICES:

Services: The Government shall provide material handling services to load and unload Contractor machinery and for the set up of equipment. The Coast Guard Yard shall provide timely assistance as requested by the Contractor. The Contractor shall provide 48-hour notice to the Government when there is a need for material handling services.

Utilities: The Government will provide water, compressed air, and electricity for the Contractor as defined herein. The Contractor shall instruct employees in utilities conservation practices. The Contractor shall be responsible for operating in such a manner that precludes the waste of utilities, for example turning off the water faucets or valves after using the required amount to accomplish assigned work.

Compressed Air: The Government shall provide a source of compressed air for Contractor machinery. The Contractor shall be responsible for ensuring that their compressed air hookup connections are compatible with the Yard’s compressed air sources.

Electricity: The Government shall provide up to 200 amps and up to 480 volts of electrical services.

CONTRACTOR FURNISHED ITEMS, SERVICES AND RESPONSIBILITIES:

General: The Contractor shall furnish all equipment and services required to perform work under this SOW, other than those explicitly addressed in government furnished services.

The Contractor shall report to the designated work site on the date specified on the written notification by the Contracting Officer in the form of a signed order. No other individual has the authority to direct the Contractor to begin work, other than a warranted Contracting Officer. Pending Coast Guard Yard production schedules, services may be required on an intermittent basis within the period and quantity specified.

Contractor Equipment: vehicles and tanks which holds or can hold hazardous materials that is left on CG Yard premises must have the Contractor’s contact information placed in the driver’s side window indicating the Emergency Contact Number (answered 24/7/365) for the owner/operator of the vehicle. If a tank is left on the premises, the Emergency Contact Number (answered 24/7/365) for the owner/operator of the tank must be painted on the tank in a prominent location. The government will not assume liability for any vehicles/tanks left on CG YARD property. The COR/SS will coordinate the location with the Yard Environmental/Security/Materials Handling.

RAPID GATE SECURITY REQUIREMENTS: Effective September 1, 2016, all contractors and subcontractors performing on this contract/purchase order/task order must utilize the RAPIDGate Program and/or Transportation Worker Identification Credentials (TWIC) if repeat access to the CG Yard is required for seven (7) or more days annually. RAPIDGate manages the non-Common Access Credential (CAC) eligible vendor/contractor companies and their employees who require access to Coast Guard Yard, Baltimore. Vendor/contractor CAC eligibility has been restricted to only those who require physical access to Coast Guard Yard AND logical access to a DoD or DHS network or system.

Vendor/contractor companies that require repeat (7 or more days annually) access to the CG Yard, pay an annual company enrollment subscription to participate in the RAPIDGate Program and an annual employee registration subscription for each employee to participate in the program. The company enrollment fee is waived for sole proprietors. Vendor/contractor companies must be approved by a government sponsor at each DoD and DHS installation where their employees require access. Vendor/contractor employees who are registered, undergo initial and regular vetting and are issued a single credential, which is valid for perimeter access to those DoD and DHS installations where access privileges have been granted. All company enrollments are submitted via the web at www.rapidgate.com and managed by phone or email. Initial employee registrations take place at a Program Registration Kiosk, typically located at participating DoD and DHS Installation Pass & ID Offices. The CG Yard’s Registration Kiosk is located at 2401 Hawkins Point Road, Baltimore, MD 21226, BLDG. 144, Security [brick building adjacent to the main gate]. Credentials will be available for pick-up at BLDG. 144 fourteen (14) days after the employee’s initial registration. Costs incurred for delays at the gate due to the contractor’s failure to comply with this requirement or to provide qualified, authorized personnel will not be reimbursed by the Government. Your tenant sponsor is, the Yard POC or Ship Superintendent listed at the beginning of this document. This sponsor will need a list of individual employee names and DOB’s with your quotation. Any RAPIDGate program questions should be directed to: 1-877-727-4342

General: The Contractor will be required to follow 29 CFR 1915 (OSHA Shipyard Industry Standard), 16 CFR1303, 29 CFR 1910, 29 CFR 1915.1025, 29 CFR 1926.62, 15 U.S.C. 2601, while performing this work at the U.S. Coast Guard Yard.

Safety Equipment: The area where this work taking place requires hard hats, safety harnesses and safety glasses always. The Contractor will provide all required personnel safety equipment for their employees, including, but not limited to, safety helmet and safety glasses with side shields. All safety equipment shall meet OSHA standards. The Contractor shall follow all applicable OSHA guidelines and regulations. It is also required that all COVID safety practices are followed.

ISO Qualifications: Contractor shall comply with all the U.S. Coast Guard Yard International Organization for Standardization (ISO) 9001 Quality Management and ISO 14001 Environmental Management Systems. The Contractor may be periodically audited to ensure conformity to these standards. If the contractor fails to perform as specified, the contracting officer may direct that employees be replaced or suspend work.

EMERGENCY SERVICES: The U.S. Coast Guard Yard has 24-hour first aid, spill response and fire protection available. If necessary, the Contractor may call 410-636-3993 from non-Yard phones and extension 3000 from Yard phones for emergency situations. Injuries shall be reported immediately and followed up with a written report to the COR.

ENVIRONMENTAL PROTECTION REQUIREMENTS: All contractors working on CG Yard shall abide by all federal, state, and local environmental regulations as published by the Environmental Protection Agency, 40 CFR (series) and the following Yard Environmental plans/policies:

· CG Yard Environmental Management Systems (EMS)

· CG Yard Storm Water Pollution and Prevention Plan (SWPPP)

· CG Yard Spill Prevention Control and Counter Measure Plan (SPCC)

Transport and Disposal: All material removed from tanks shall be taken off CG Yard property immediately after cleaning operations are complete. Material shall be processed in accordance with Section 10.2.2 before leaving the Yard. Prior to removing material, the Government environmental dept. reserves the right to inspect the transport vehicle status of contents, to ensure accurate quantities being removed from the CG Yard.

The Contractor must properly remove and dispose of all materials in compliance with applicable Federal, state, and local environmental laws and regulations. Contractor assumes all responsibility and liability for the transport and proper disposal of materials and in particular the following requirements:

1. If a spill occurs, the CG Yard Environmental Branch shall be immediately notified and can be reached at (410) 636-3111. The Contractor must also report the spill to the USCG Yard Main Gate (410) 636-3993 or YARD extension 3000 IMMEDIATELY. A letter describing the incident shall be submitted within 24 hours after the spill. During a spill, the Contractor will receive direction from the Yard Incident Commander/ Firehouse / Environmental or YARD/Vessel OOD.

1. The Contractor MUST follow the USCG Yard Facilities Response Plan, when operating on USCG Yard property.

1. Written notification must be provided to the Environmental Protection Specialist Brandace Timbers 410-636-3775, brandace.t.timbers@uscg.mil of any activity that could potentially cause an environmental violation. Some examples of these activities are: any activity that could result in a spill or discharge into a waterway or introducing a hazardous material into the environment.

1. The Contractor will be solely responsible for the transportation and proper disposal of waste material. Contractor must submit disposal sites to CG Yard Environmental Department for site approvals and copies of Bill Of Lading or waste manifests. If Contractor elects to use dumpsters for holding or transportation of waste, dumpsters must be covered to prevent waste from becoming airborne.

1. Only the Yard Environmental Dept is authorized to sign hazardous waste manifest.