16-01_Summary_of_Work.pdf
PDF 26 KB Posted
- Attached to
- SPECIFICATION NO. 16-01, CONTRACT NO. C51520
- Solicitation number
- SPEC 16-01
- Issued by
- Sacramento County, California
About this file
This is a Summary of Work section from project specifications for fish release sites on Sherman Island in Rio Vista, California. The project involves construction of two fish release sites located approximately half mile apart along the Sacramento River levee, including earthwork, concrete slabs, steel platforms with gratings, piping systems, 16-inch diameter steel pipe piles, structural steel frameworks, bollards, downspouts, electrical work, self-cleaning fish screens, various gates and fencing, site lighting, access control systems, and pavement markings. The work must begin within 5 days of notice and has key completion milestones: pile driving and riprap replacement must be completed by September 12, 2016, with all remaining work completed by December 31, 2017.
The project has strict scheduling restrictions, with pile driving work only allowed August 1-September 12, 2016, non-pile driving in-water work restricted to August 1-October 31, 2017, and on-land excavation/earthwork limited to May 1-October 1, 2017. Liquidated damages are set at $3,500 per day for missing the pile driving deadline and $3,000 per day for missing the final completion date, with a maximum of $6,000 per day. The contractor must coordinate with ongoing PG&E electrical upgrades and RD 341 levee improvement work occurring in parallel during 2016-2017. The project requires various permits including Sacramento County encroachment permits and US Coast Guard notifications.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Summary of Work
01110-1 E-15
SECTION 01110
SUMMARY OF WORK
PART 1 GENERAL
1.01 DESCRIPTION
A. The term project is defined in Document 00701 – Abbreviations and Definitions, Paragraph 2. This project includes the following principal features:
1. Earthwork, concrete slabs on grade.
2. Steel platforms with metal gratings.
3. Piping, valves, flowmeters, and submersible pumps.
4. Steel pipe piles, 16 inch diameter.
5. Structural steel frameworks to support the piping.
6. Bollards.
7. Overhead downspout systems.
8. Electrical work for the fish screen pumps, lights and gates.
9. Self-cleaning, retrievable, fish screens.
10. Vertical lift gates, automated swing gates, manual walk gates, manual sliding gates, and chain link fencing.
11. Site lighting.
12. Access control system for the gates.
13. Pavement markings, wheel stops, and surface-mounted delineators.
14. Providing underwater diving services for performing underwater construction work, conforming to the provisions in Section 01351 – Diving Provisions.
1.02 RELATED SECTIONS
A. Supplementary General Conditions, General Conditions, other Division 1 sections, and Drawings apply to this section.
01110-2 E-15
1.03 LOCATION AND ACCESS
A. The two fish release sites are on the northwest side of Sherman Island, Rio Vista, California, on the levee along the Sacramento River. They are off of West Sherman Island Road, with each site located where the road transitions from on top of the levee crown to along the levee toe.
The sites are southwest of the Rio Viento RV Park and northeast of Sherman Island County Park. The two sites are approximately a half mile apart. The Manzo Ranch site Latitude/Longitude coordinates are 38°04’0.56”N /121°46’18.62”W. The Little Baja site, southwest of Manzo Ranch, Latitude/Longitude coordinates are 38°03’48.01”N /121°46’46.63”W.
1.04 TIME OF COMPLETION
A. Pursuant to Document 00705 – Prosecution of Work, Paragraph 1.A, the Contractor shall begin work within
5 DAYS
from date of receipt of notice to begin work.
B. The Contractor shall complete all pile driving including riprap replacement before the expiration of
September 12, 2016.
C. The Contractor shall complete the balance of the work before the expiration of
December 31, 2017.
D. The above completion dates are based on the Contractor receiving the notice to begin work within 40 days from the date of the bid opening.
The Department will extend the completion dates by the number of days after the 40 days specified above that the Contractor receives the notice to begin work, except to the extent that the delay in issuance of the notice to begin work results from the failure of the Contractor to perform obligations specified in Document 00200 – Instructions to Bidders. Notwithstanding the provisions of Document 00705 – Prosecution of Work, Paragraph 5, the Contractor shall not be entitled to adjustment in compensation for such extension of the completion dates.
01110-3 E-15
1.05 LIQUIDATED DAMAGES
A. Pursuant to Document 00705 – Prosecution of Work Paragraph 2:
1. Liquidated damages for failure to complete the work specified in Paragraph 1.04 B within the time specified will be $3,500 per day.
2. Liquidated damages for failure to complete the balance of the work specified in Paragraph 1.04 C will be $3,000 per day.
3. The maximum sum per day for liquidated damages for which the Contractor will be liable will be $6,000 per day.
1.06 PROJECT RESTRICTIONS
A. Pile driving, pile pre-drilling, splicing and welding, riprap removal and replacement will only be allowed from August 1, 2016 to September 12, 2016.
B. All other work not directly associated with pile driving will only be allowed in 2017.
C. Non-pile driving in-water work will only be allowed from August 1, 2017 to October 31, 2017.
D. Non-pile driving on-land work involving excavation, earthwork, trench excavation and backfill, concrete foundations or shoreline earthwork will only be allowed from May 1, 2017 to October 1, 2017.
E. Activities such as intake pipe and release pipe replacement, fish screen attachment, platform construction, electrical set-up, and construction of the screen retrieval system may be allowed outside of the previously specified work windows providing that such activities do not affect the water channel bed or disturb the site grade.
F. Devices for catching welding debris will be required at times when field welding over waterways is performed.
1.07 PERMITS AND LICENSES
A. Pursuant to Document 00703 – Applicable Laws and Regulations, Contractor shall obtain necessary permits and licenses including the following:
1. Transportation and hauling permits as required from Caltrans and local counties.
01110-4 E-15
2. Contractor shall comply with the Sacramento County encroachment permit from Sacramento County as listed in Document 00300 – Information Available. Applicant is exempt from posting a $2,500 deposit as specified in Chapter 12.08 of Sacramento County Code.
3. Request for publication in the United States Coast Guard, District 11, Local Notice to Mariners (LNM), 14 days prior to the start of in-water operations.
B. The Contractor shall obtain such permits and licenses and pay charges and fees, except as specified in Section 01570 – Environmental Protection. Permits and licenses shall be obtained in sufficient time to prevent delay to the project.
1.08 COOPERATION WITH OTHERS
A. Pursuant to Document 00706 – Control of Work, Paragraph 3.E, the Contractor shall cooperate with others. Other anticipated work under construction or scheduled during the period of the contract includes:
1. PG&E electrical upgrade work for power to the project site.
a. Estimated start date for PG&E work is May 23, 2016.
b. Estimated end date for PG&E work is December 31, 2016.
c. A pre-construction meeting shall be held with PG&E, prior to PG&E or the Contractor starting electrical-related work.
2. RD 341 levee and county road improvement work adjacent to the site. The major construction activities scheduled by RD 341 include:
a. Place Phase 1 fill on levee, May 4, 2016 – July 5, 2016.
b. Place Phase 2 fill on levee, September 1, 2016 – November 2, 2016.
c. Place Phase 3 fill on levee, April 19, 2017 – June 20, 2017.
d. Place Phase 4 fill on levee, August 17, 2017 – August 30, 2017.
e. Grade upper access road and fish release pads, August 31, 2017 – September 13, 2017.
f. Install electrical conduits and pullboxes, September 14, 2017 – September 27, 2017.
01110-5 E-15
g. Finish grade and rock upper access roads and fish release pads, October 4, 2017 – October 17, 2017.
h. Pave county road, access roads and fish release pads, October 18, 2017 – October 24, 2017.
1.09 VERIFICATION OF EXISTING FACILITIES
A. The Contractor shall verify the applicable structural dimensions, the location, elevations, and dimensions of existing facilities, and other dimensions and data required to complete the project.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
PART 4 PAYMENT
4.01 PAYMENT
A. The contract prices shall include full compensation for all costs incurred under this section.
END OF SECTION
| SECTION 01110 |
| SUMMARY OF WORK |
| PART 1 GENERAL |
| 1.01 DESCRIPTION |
| 1.02 RELATED SECTIONS |
| 1.03 LOCATION AND ACCESS |
| 1.04 TIME OF COMPLETION |
| 1.05 LIQUIDATED DAMAGES |
| 1.06 PROJECT RESTRICTIONS |
| 1.07 PERMITS AND LICENSES |
| 1.08 COOPERATION WITH OTHERS |
| 1.09 VERIFICATION OF EXISTING FACILITIES |
| PART 2 PRODUCTS |
| PART 3 EXECUTION |
| PART 4 PAYMENT |
| 4.01 PAYMENT |
END OF SECTION