BENCH TOP CYANOACRYLATE CHAMBER

SOLICITATION 15DDHQ18Q00000198

QUESTIONS & ANSWERS

AUGUST 21, 2018

Q1. Will all of the units requested in the RFQ be ordered simultaneously or will they be broken up over a period of time? And if so, what is that period of time? Also, when is the expected order/performance period of the contract--2018 or 2019?

A1. All the units requested in the RFQ will be ordered simultaneously; the expected delivery date will be in 2018.