JOFOC September 1, 2019 - August 31, 2020

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

JUSTIFICATION FOR OTHER THAN FULL AND OPEN COMPETITION (JOFOC)

RESIDENTIAL REENTRY CENTER (RRC)

CONTRACT #15BRRC19D00000259

Located in •Greensboro, NC

1 . Agency:

The United States Department of Justice, Bureau of Prisons (Bureau), Administration Division, Procurement Management Branch, Residential Reentry Contracting Section.

2. Description of Action Being Approved:

Pursuant to the Federal Acquisition Regulation (FAR) Part 6 . 302 - 2 (b) ( 1) and ( 2), the Bureau has determined the need for RRC services lbcated in Greensboro, North Carolina meets the criteria established for other than full and open competition. This limitation of competition is justified in accordance with FAR Subpart 6 . 303-2, Content.

The action to be approved is for a contract to provide RRC services under other than full and open competition procedures for continued RRC services for Federal offenders located in Greensboro, North Carolina.

3. Description of the Services Required to Meet the Agency Needs:

RRC services located in Greensboro, North Carolina for the period September 1, 2019 through August 31, 2020.

A new contract numbered 15BRRC19D00000259 with a guaranteed minimum of

4. Statutory Authority Permitting Other than Fu11 and Open Competition:

Other than full and open competition is based on the authority of 41 U. S.C. 3304(a) (2) as implemented by FAR 6.302-2, Unusual and Compelling Urgency.

5. Determination that proposed Contractor's unique qualifications or the nature of the acquisition requires use of the authority cited:

The current contract, DJB200179, for RRC services in Greensboro

The length of time and need for this contract is a direct result of the time required in the award and start up process. In addition, the contractor is provided up to 120 days to prepare facilities prior to the start of the operation. This time period will allow for the award of a new contract and provide flexibility on these dates to account for any unforeseen delays in award.

The services required are of an unusual and compelling urgency due to the Bureau's essential need. There is only one contract for RRC services for federal offenders located within Greensboro. If services cannot be provided at this location, the Bureau has two options: transfer offenders to another RRC to continue receiving services or return the offenders to a secure institution.

The mission of the reentry program is to assist federal offenders during the transition from prison to the community by providing services which include self-improvement opportunities, as well as, assistance to secure employment and locate a permanent residence after their program is complete.

Offenders are typically assigned to a RRC near the location where they will eventually be released. The Bureau contracts with these RRCs to provide assistance to inmates who are nearing release from federal custody. RRC placements provide a safe, structured, supervised environment in the indi victual' s community, as well as, assistance , drug treatment, and other reentry programs and services.

RRCs help inmates gradually rebuild their ties to the community and supervise their activities during this community re - adjustment period . Therefore , returning the offenders to a secure institution for the 12 month period requested in this justification would cause serious harm to the mission of the Bureau and would be a disruption to the inmate's reentry programming.

Relocating the offenders does not support the overall mission of the Reentry Services Division or the Bureau in the attempt to re - integrate the offenders into society as law abiding citizens .

6. Efforts made to solicit from as many sources as practicable, including whether or not a notice was published in the GPE:

Based on the urgent requirements of these services, the exception at FAR 5. 202 (a) (2) applies;

7. Contracting Officer's determination that cost to the Government will be fair and reasonable:

The Contracting Officer has determined that the anticipated costs to the Government will be fair and reasonable based on a comparison of current Government contract prices for RRC services.

RRC Services:

8. Description of the market survey conducted:

9. Other facts supporting the use of other than full and open competition :

N/A

10. List of sources, expressing in writing , interest in the acquisition:

11. Actions taken by the agency to remove or overcome barriers to competition:

12 . Contracting Officer's Certification :

I certify that the justification is accurate and complete to the best of the Contracting Officer ' s knowledge and belief.