2 - Amendment 0003 - Questions and Answers.pdf
PDF 162 KB Posted
- Attached to
- MCC Chicago - Replace SHU Doors Federal contract opportunity
- Solicitation number
- 15BFA025B00000025
About this file
This document is a Questions and Answers (Q&A) addendum for the MCC Chicago - Replace SHU Doors project (Solicitation 15BFA025B00000025). Valley Security Company submitted five clarification questions regarding project details, including contractor responsibilities for masonry repairs, dumpster supply, bio box manufacturer confirmation, reuse of detention locks and mounting plates, and detention frame specifications. The clarifications direct respondents to specific sections of the project documentation for detailed guidance, such as Section 1.1 (B), Section 1.11 (B), page 08 34 63-16 for bio-box references, Section 2.1 for detention hardware, and Section 2.1 (B) for detention hollow metal frames specifications.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Abstract of Offers - 1 page - Chicago SHU Doors.pdf | ||
| 2 - Amendment 0004 - SF30.pdf | ||
| 2 - Amendment 0004 - Att 1 - Wage Determination.pdf | ||
| 2 - Amendment 0003 - SF30.pdf | ||
| 2 - Amendment 0002 - SF30.pdf | ||
| 2 - Amendment 0002 - Att 1 - Wage Determination.pdf | ||
| 2 - Amendment 0001 - Att 2 - Wage Determination.pdf | ||
| 2 - Amendment 0001 - SF30.pdf | ||
| 2 - Amendment 0001 - Att 1 - Meeting Minutes with Photos.pdf | ||
| 1 - Attachment 3 - WD.pdf | ||
| 1 - Attachment 4 - Criminal History Check Form.pdf | ||
| 1 - Attachment 5 - Bid Bond.pdf | ||
| 1 - Instruction to Bidders - Chicago - 25Z4AA1.pdf | ||
| 1 - Solicitation 15BFA025B00000025.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MCC CHICAGO – REPLACE SHU DOORS
PROJECT 25Z4AA1- QUESTIONS & ANSWERS
SOLICITATION 15BFA025B00000025
From Valley Security Company:
1. Is the contractor responsible for masonry repairs?
CLARIFICATION: Yes, See Section 1.1 (B) (1., 2. ,3.)
2. Will the contractor be responsible for supplying dumpsters?
CLARIFICATION: See Section 1.11 (B)
3. Can you please confirm the manufacturer for the bio boxes?
CLARIFICATION: See page 08 34 63-16 – D4 Bio-Box Reference Sheet (Parts & Assembly Notes)
4. Are we also to reuse all detention locks and Hollow metal mounting plates per sheet A-2 of the drawings?
CLARIFICATION: See Section 2.1 MATERIALS - DETENTION HARDWARE (E)(1)
5. In lieu of an adjustable throat frame, can the Detention Frames be a standard 5-5/8” jamb depth to fit a standard 6” CMU block?
CLARIFICATION: See Section 2.1 (B) - Detention Hollow Metal Frames
| MCC CHICAGO – REPLACE SHU DOORS |
| From Valley Security Company: |
| 1. Is the contractor responsible for masonry repairs? |
| CLARIFICATION: Yes, See Section 1.1 (B) (1., 2. ,3.) |
| 2. Will the contractor be responsible for supplying dumpsters? |
| CLARIFICATION: See Section 1.11 (B) |
| 3. Can you please confirm the manufacturer for the bio boxes? |
| CLARIFICATION: See page 08 34 63-16 – D4 Bio-Box Reference Sheet (Parts & Assembly Notes) |
| 4. Are we also to reuse all detention locks and Hollow metal mounting plates per sheet A-2 of the drawings? |
| CLARIFICATION: See Section 2.1 MATERIALS - DETENTION HARDWARE (E)(1) |
| 5. In lieu of an adjustable throat frame, can the Detention Frames be a standard 5-5/8” jamb depth to fit a standard 6” CMU block? |
| CLARIFICATION: See Section 2.1 (B) - Detention Hollow Metal Frames |