Questions and Answers - MDC BRO.pdf

PDF 161 KB Posted

Attached to
Waste Removal Services - MDC Brooklyn, Dayton Manor, & Building 4 Federal contract opportunity
Solicitation number
15BFA024Q00000020
Issued by
Department of Justice Bureau of Prisons Field Acquisition Office

About this file

This document is a set of Questions and Answers related to Solicitation 15BFA024Q00000020 for Solid Waste Removal Services at the Metropolitan Detention Center Brooklyn, Dayton Manor, and Building 4.

The solicitation is being issued by the U.S. Department of Justice Federal Bureau of Prisons Field Acquisition Office. Key details include: pick-ups cannot be performed at night per the Statement of Work; estimated monthly tonnage is 70 tons for MDC Brooklyn and 26 tons for Dayton Manor, with no historical data available for Building 4; site visits can be scheduled in advance with the Contracting Officer's Representative or Facilities Manager; there was no previous contract covering all the required locations; the incumbent provider is Century Waste Services. The solicitation does not allow for a grace period on the scheduled pick-up times, which are at the discretion of the government. Overall, this document provides clarification on operational details and logistics in response to questions from potential offerors.

View the file

Other files for this federal contract opportunity

Other files attached to Waste Removal Services - MDC Brooklyn, Dayton Manor, & Building 4, newest first.
File Type Posted
RFQ - MDC Brooklyn Solid Waste Removal.pdf PDF
NEW - Questions and Answers II - MDC BRO.pdf PDF
RFQ - MDC Brooklyn Solid Waste Removal.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. Department of Justice

Federal Bureau of Prisons Administration Division

Field Acquisition Office Grand Prairie, Texas 75051

RE: Request for Quote – 15BFA024Q00000020

Solid Waste Removal Services Metropolitan Detention Center Brooklyn/Dayton Manor/Building 4

Questions and Answers:

1. Can pick-ups and dumps be performed at night?

No. Please refer to Section 2.2, Statement of Work of the solicitation.

2. What is the approximate tonnage per location?

The information below (provided by the institution) is based on 2023 monthly tonnage:

MDC Brooklyn – 70 Tons Dayton Manor – 26 Tons Building 4 (New requirement, no historical data available)

3. Is it possible to schedule a site visit?

Yes. Site visits must be coordinated in advance with the institution’s designated Contracting Officer’s Representative (COR) or the Facilities’ Manager, prior to the closing date of the solicitation. More information regarding this will be provided.

4. What was the previous contract number and the amount resulting in a five-year contract?

Be advised, there was not a previous contract that included all locations required for this solicitation.

5. Is there an incumbent providing services? If so, please provide the name.

Yes, Century Waste Services.

6. Given the pick-up times outlined in the Statement of Work, is there a grace period due to traffic and/or unforeseen circumstances?

The scheduled times provided in the Statement of Work are the operational hours dictated by the institution. Changes are at the discretion of the COR and/or Facilities’ Manager.

S. Christian-Carpenter, Contracting Officer DOJ-Federal Bureau of Prisons Field Acquisition Office U.S. Armed Forces Reserve Complex 346 Marine Forces Drive Grand Prairie, Tx 75051 Office: 202-598-6089 Email: schristian-carpenter@bop.gov mailto:schristian-carpenter@bop.gov