Questions and Answers Danbury Replace Switchgear.pdf

PDF 7 MB Posted

Attached to
FCI Danbury - Replace Switchgear Federal contract opportunity
Solicitation number
15BFA023B00000010
Issued by
Department of Justice Bureau of Prisons Field Acquisition Office

About this file

This document contains questions and answers regarding a solicitation for replacing switchgear at the Federal Correctional Institution in Danbury, Connecticut. The solicitation seeks to award a firm-fixed-price construction contract to replace the switchgear, main distribution panels, and accessories inside the facility's Food Services electrical room. Clarification is provided that the solicitation description contains a clerical error and will be edited to correctly reference replacing the switchgear rather than a generator. Additional clarification addresses the allowed duration for a power shutdown contingent on temporary power provisions. The North American Industry Classification System code applicable is 238210 for the electrical contractor industry with a small business size standard of $19 million. The solicitation is set aside exclusively for small businesses and will be distributed solely through the System for Award Management website.

View the file

Other files for this federal contract opportunity

Other files attached to FCI Danbury - Replace Switchgear, newest first.
File Type Posted
Abstract of Offers - FCI Danbury - Replace Switchgear .pdf PDF
Amendment 0001.pdf PDF
Pre-Bid Meeting Minutes and Sign in Sheet.pdf PDF
Construction Wage Determination 6-16-23.pdf PDF
Instruction to Bidders.pdf PDF
Construction Wage Determination 6-9-23.pdf PDF
SF-24 Bid Bond Form.pdf PDF
Solicitation.pdf PDF
1 - Attachment 4 - Criminal History Check Form.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FCI Danbury – Replace Switchgear

PROJECT 23Z2AQ9 QUESTIONS & ANSWERS

SOLICITATION 15BFA023B00000010

1. If possible, please provide panels schedules and one line diagram of existing electrical equipment?

CLARIFICATION: See attached, panel schedules and existing line diagram

2. What is the allowed time duration for a shutdown of power?

CLARIFICATION: Contingent on the temporary power provided in section 8 page 3 of the Statement of Work

3. On the Solicitation in Section 2 – Commodity or Services Schedule, the description reads Replace Generator.

CLARIFICATION: The clerical error in the description will be edited to read replace Swithchgear.

Questions Danbury Replace Switchgear
Answers
Answer 2
Answers 3
Answers 4
Answers 5
Answers 6