This is a Sealed Bid Invitation for Bid (IFB) solicitation for construction services issued by the Federal Bureau of Prisons Field Acquisition Office. The solicitation number is 15BBNF26Q00000086, issued on May 20, 2026, with sealed bids due June 17, 2026, at 11:00 AM Central Time.
The contractor shall provide all materials, labor, and equipment to complete an emergency replacement of an education chair lift at the Federal Correctional Institution (FCI) Oxford located in Oxford, Wisconsin. The work is firm fixed price on a 100% small business set-aside basis. Performance must begin within 10 calendar days of award and be completed within 140 calendar days. The project magnitude is estimated between $25,000 and $100,000. A bid bond of 20% of the bid price (not to exceed $3,000,000) is required, and within 10 days of award, the contractor must furnish performance and payment bonds each at 100% of the original contract price. For contracts between $35,000 and $150,000, the contracting officer shall select two or more payment protections from specified alternatives. Required insurance includes workers' compensation with $100,000 minimum liability, comprehensive general liability at $500,000 per occurrence for bodily injury, and comprehensive automobile liability with $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage. The contractor must comply with prevailing wage requirements, construction wage rate determinations, labor standards, and security clearance procedures specific to federal prison operations. All offers must be submitted electronically to lbonner@bop.gov.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 0001.pdf | ||
| 1 - Criminal History Check Form.pdf | ||
| 1 - Instructions to Offerors.pdf | ||
| Wage Determination.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
15BBNF26Q00000086 Page 1 of 37
SOLICITATION,OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NUMBER
15BBNF26Q00000086
SEALED BID (IFB)
INVITATION FOR BID
NEGOTIATED (RFP)
REQUEST FOR PROPOSAL
2. TYPE OF SOLICITATION 3. DATE ISSUED
05/20/2026
PAGE OF PAGES
1 37
IMPORTANT -The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER
15B41026PR000265
6. PROJECT NUMBER
26Z4AS3
CODE BFAO
Federal Bureau of Prisons Field Acquisition Office U.S. Armed Forces Reserve Complex 346 Marine Forces Drive Grand Prairie, TX 75051
7. ISSUED BY
Federal Bureau of Prisons Field Acquisition Office U.S. Armed Forces Reserve Complex 346 Marine Forces Drive Grand Prairie, TX 75051
8. ADDRESS OFFER TO
9. FOR
INFORMATION CALL:
a. NAME
Luke Bonner, Contracting Officer
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
SOLICITATION
NOTE: In sealed bid solicitations "offer" and "offeror" means "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
The selected contractor shall provide all materials, labor, and equipment to complete the project titled Emergency Replace Education Chair Lift at the Federal Correctional Institution (FCI) Oxford located in Oxford, WI in accordance with the attached Statement of Work.
PLEASE COMPLETE THE FOLLOWING ITEMS:
UNIQUE ENTITY IDENTIFIER:_____________________________
TAX IDENTIFICATION NUMBER: ____________________________
CAGE CODE:________________________________
CONTRACTOR E-MAIL:________________________________
11. The Contractor shall begin performance within calendar days and complete it within calendar days after receiving10 140 award, X notice to proceed. This performance period is X mandatory negotiable. (See __________________________.)
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS? (If "YES," indicate within how many calendar days after award in Item 12b).
YES X NO
12b. CALENDAR DAYS
Sealed offers in original and copies to perform the work required are due at the place specified in item 8 by (hour) local time (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
11:00US/
Central a.
06/17/2026
b. An offer guarantee is, X is not required.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.c.
90d. Offers providing less than calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) lbonner@bop.gov
15BBNF26Q00000086 Page 2 of 37
OFFER (Must be fully completed by offeror)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
CODE FACILITY CODE
The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ___________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
17.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM
10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE
UNITED STATES CODE AT
26. ADMINISTERED BY BFAO
Federal Bureau of Prisons Field Acquisition Office U.S. Armed Forces Reserve Complex 346 Marine Forces Drive Grand Prairie, TX 75051
Federal Bureau of Prisons FCI Oxford
PO BOX 500
Oxford, WI 53952
Brooke Ruesink bruesink@bop.gov
27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return __________ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30a.NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
Lucas Bonner
31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA
BY
31c. DATE
STANDARD FORM 1442 (REV. 12/2022) BACK
TOTAL FIRM-FIXED PRICE OFFER AMOUNT: $__________________________________
15BBNF26Q00000086 Page 3 of 37
Table of Contents
Section Description Page Number
1 Solicitation, Offer and Award 2 Commodity or Services Schedule 3 Special Contract Requirements 4 Contract Clauses 5 Attachments 6 Solicitation Provisions 7 Representations and Certifications
15BBNF26Q00000086 Page 4 of 37
Section 2 - Commodity or Services Schedule
FCI Oxford Solicitation for Emergency Replace Education Chair Lift Offers must be submitted electronically to lbonner@bop.gov.
Firm Fixed Price
100% Small Business Set Aside
Firm Fixed Price
SCHEDULE OF SUPPLIES/SERVICES
CONTINUATION SHEET
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 The selected contractor shall provide all materials, labor, and equipment to complete the project titled Emergency Replace Education Chair Lift at the Federal Correctional Institution (FCI) Oxford located in Oxford, WI in accordance with the attached Statement of Work.
PSC: Z2FF
1 JB $________ $_________________
15BBNF26Q00000086 Page 5 of 37
Section 3 - Special Contract Requirements
Clauses By Full Text
FAO-0001 Bonds
(a) Bid Guarantee. Each bidder shall submit with his bid a Bid Bond (Standard Form 24) with good and sufficient surety or sureties acceptable to the Government, or other security as provided in provision 52.228-1, in the form of twenty percent (20) of the bid price or not to exceed $3,000,000. The bid bond penalty may be expressed in terms of a percentage of the bid price or may be expressed in dollars and cents. A bid bond is not required for bids of $150,000 or less. (FAR 28.102-1)
(b) Performance and Payment Bonds. Within 10 days after award the contractor shall execute and submit to the Contracting Officer two bonds, each with good and sufficient surety or sureties acceptable to the Government, as follows;
a Performance Bond (Standard Form 25) and a Payment Bond (Standard Form 25A). The penal sums of such bonds will be as follows: (Not required for contracts of $150,000 or less)
(1) Performance Bond: The penal sum of performance bonds at the time of contract award shall be 100 percent of the original contract price.
(2) Payment Bond: The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.
(c) For construction contracts greater than $35,000 but not greater than $150,000, the Contracting Officer shall select two or more of the following payment protections, giving particular consideration to inclusion of an irrevocable letter of credit as one of the selected alternatives (FAR 28.102-1(b)(1)):
(1) A Payment Bond;
(2) An irrevocable letter of credit (ILC);
(3) A tripartite escrow agreement;
(4) A Certificate of Deposit; or
(5) A deposit of the types of security listed in 28.204-1 and 28.204-2.
(d) Individual Sureties.
(1) Bidders may elect to furnish individual surety bonds. If individual surety bonds are furnished for bid guarantees, payment or performance bonds, the individual sureties must submit their bonds proof of ownership and value of the assets which they claim in their net worth at time of bid opening. The Government's preferred method of proof is to have a statement of net worth prepared by a Certified Public Accountant (CPA) in accordance with Generally Accepted Accounting Principles (GAAP). Statements from a CPA that contain disclaimers are not acceptable. The statement of net worth on the Standard Form 28, Affidavit of Individual Surety, is insufficient and will not be accepted without additional proof of value and ownership.
(2) Bidders are cautioned that individual sureties must provide complete and detailed information in Block 9 of Standard Form 28 concerning other contracts on which they have provided bonds. This information shall include contract number, contract location, amount, and type of bond and telephone number of the involved contracting office. Failure to provide the proof and information required may result in rejection of the bid or termination of the contract for failure to provide adequate bonds.
FAO-0002 Magnitude
The magnitude of this project is between $$25,000.00 and $$100,000.00.
15BBNF26Q00000086 Page 6 of 37
FAO-0003 Required Insurance
See FAR 52.228-5, Insurance - Work on a Government Installation.
The Contractor shall, at its own expense, provide and maintain during the entire performance period of this contract, at least the kinds and minimum amounts of insurance required in the
Schedule or elsewhere in the contract.
TYPE AMOUNT
(1) WORKERS COMPENSATION & EMPLOYER'S LIABILITY $100,000
The required Workmen's Compensation Insurance shall extend to cover employee's liability for accidental bodily injury or death and for occupational disease with a minimum liability of $100,000.
(2) COMPREHENSIVE GENERAL LIABILITY with a minimum limit of:
PER ACCIDENT OR
OCCURRENCE FOR BODILY INJURY $500,000
This insurance shall include contractor's protective and contractual liability.
(3) COMPREHENSIVE AUTOMOBILE LIABILITY with the following minimum limits:
PER PERSON $200,000
PER OCCURRENCE FOR BODILY INJURY $500,000
PER OCCURRENCE FOR PROPERTY DAMAGE $ 20,000
FAO-0004 Pre-Construction Conference
(a) Prior to the start of construction, Contracting Officers shall call a conference with the contractor, subcontractor(s), Warden, Controller/Business Administrator, Safety Manager, Facilities Administrator, Project Representative, A&E firm, Captain and other interested personnel to discuss the statutory labor standards, prevailing wage requirements, submission of the contractor's payrolls, subcontractor's responsibilities, institution work schedules, local policies, contraband, parking, storage of vehicles and equipment, etc.
15BBNF26Q00000086 Page 7 of 37
Minutes of the conference shall be recorded, listing the names and titles of all attendees, and the subject matter of all items covered. The minutes shall be signed by the contractor and the Contracting Officer, and a signed copy placed in the contract file.
(b) The Contractor shall familiarize himself/herself with all procedures involved in normal institution routines. Any requirements which may constitute a problem or result in conflict, will be brought to the attention of the Contracting Officer or his representative for determination.
FAO-0005 Submittals
Within 10 calendar days after commencement of work or as otherwise established by the Contracting Officer, all materials and articles requiring approval, as contemplated by the Materials and Workmanship clause, shall be submitted by the contractor.
The submittal process is in place to allow the Government the opportunity to determine whether materials or procedures used by the contractor are in accordance with contract requirements. It is ultimately the Contractor's responsibility via the quality control process to ensure submittal items installed under the contract and work performed on site are in accordance with industry standards and general practices.
(a) The types of submittal requirements specified in this contract may include, but is not limited to; shop drawings, product data, samples, certificates of conformance or compliance, certified test or inspection reports, equipment, materials, and miscellaneous work related submittals for construction. Individual submittal requirements are generally specified in applicable sections for each unit of work in the specifications and/or as a whole in one section in the statement of work.
(b) The Bureau of Prisons (BOP) Contracting Officer’s Representative (COR) shall act for the Contracting Officer in the review and acceptance of all submittals. The Contractor shall submit submittals as required by the contract/specificat ions to the COR for transmittal to the Contracting Officer. Fabrication of any work or purchase or use of any submittals (such as materials for which samples are required or equipment, etc.) shall not take place until written acceptance is given by the COR, except at the Contractor's own risk.
(c) The Contractor shall submit all shop drawings and submittals sufficiently in advance (unless otherwise specified in the specifications) of the construction requirements to allow ample time for checking, re-submitting, and re-checking.
(d) Failure of any materials to pass their specified tests shall be sufficient cause for refusal to consider, under this contract, any further samples of the same brand or make of that material. The Government reserves the right to disapprove any material or equipment which has previously proven unsatisfactory in service.
(e) The Contracting Officer’s or designee’s approval or acceptance of submittals is not to be construed as a complete check. Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor is responsible for the satisfactory construction of all work. The Contractor is responsible for delivering a final product/system that is operational as intended by the contract requirements, regardless of any Government approvals or acceptance of submittals. The Government assumes no liability during the submittal approval/acceptance process. It is the sole responsibility of the Contractor to deliver a properly functioning product or system.
FAO-0006 Contractor Use of Premises
Work Hours The project schedule is based on a normal forty (40) hour work week, eight (8) hours per day, Monday through Friday, excluding Federal holidays. The Contracting Officer’s Representative (COR) shall establish the work hour time frames for the duration of the project, subject to the approval of the Contracting Officer. Work hours and work days may be altered only with a 48 hour advance approval of the Contracting Officer.
NOTE: Access to the site will be available during normal working hours except during emergencies. It shall be the responsibility of the Contractor to familiarize himself, his employees, and his subcontractors of the working hours and conditions in the correctional facility, as working hours may not constitute a full eight hour day. The Government assumes no responsibility to the Contractor, nor to any of his subcontractors, for shorter hours due to institutional emergencies or entry and/or exit of workers necessitated by normal institution routines. The procedures and institutional entrance/
15BBNF26Q00000086 Page 8 of 37 exit routines applicable to this project will be explained at both the pre-bid conference/site visit and the pre-construction meeting.
Contraband The Contractor shall inform his employees that intoxicating beverages, drugs, weapons, etc., will not be allowed on the site. Introduction of contraband shall be subject to the penalties prescribed by Title 18 USC-1791.
Explosives The use of explosives is absolutely forbidden without written authorization from the Contracting Officer.
Parking and Temporary Office Parking will be available at the site to the extent it does not interfere with construction activities. Otherwise, parking shall be provided for by the Contractor, at his expense, off the site for workmen employed on the project. Any temporary field office used by the Contractor shall be located in an area approved by the COR.
Safety and Accident Prevention In performing work under this contract the contractor shall:
(a) Conform to the specific safety requirements established by this contract;
(b) Comply with the safety rules of the Government institution that concern related activities not directly addressed in this contract;
(c) Take all reasonable steps and precautions to prevent accidents and preserve the life and health of contractor and Government personnel performing or in any way coming in contact with the performance of this contract; and
(d) Take such additional immediate precautions as the Contracting Officer and/or COR may reasonably require for safety and accident prevention purposes.
FAO-0007 Payment Services
(a) Original application for payment shall be prepared on AIA (American Institute of Architects) Form G-702 "Application and Certificate for Payment" and submitted to the Contracting Officer. The contractor may use another form;
however, it shall contain similar information as the AIA Form G-702. The Contracting Officer’s Representative (COR) will approve the amount of payment by signing. The approved application for payment shall be forwarded as follows: Original to Accounting; Copy for Contract Award File.
(b) All small business contractors are required to self-certify on all invoices their small business status.
(c) The following information is required with each application for payment:
• Name and address of contractor
• Contract number
• Contractor invoice/application for payment number
• Description, price, and quantity of construction completed/rendered
• Payment terms (reference the contract payment clause)
• Other substantiating documentation or information required by the contract
• Name, title, and phone number of official to be notified in the event of a defective invoice
• Contractor TIN (Tax ID Number)
FAO-0008 Request for Final Inspection
The Contractor shall give the Contracting Officer’s Representative (COR) a minimum of ten (10) working days advanced written notice of the date on which the work will be fully completed and ready for the Government’s final inspection.
FAO-0009(a) Construction Contract Security
FAO-0009(a) Construction Contract Security (Program Statement 3732.01 BOP Identifications and Background Investigation)
15BBNF26Q00000086 Page 9 of 37
In addition to the information contained in clause “DOJ-03 Personnel Security Requirements For Contractor Employees (Nov 2021); (Alt. I) -- Classified Information – Cleared Contractors”, the following additional security is required to be completed and submitted for all contract employees who will be working under the terms of the contract:
Criminal History Check – BP-A0660 (May 2018) CJIS Name Check Request Form BOP Contractor Pre-employment Questionnaire BOP Authority for Release of Information The contactor should be aware that the time required for contractor security clearances to be completed may vary. For the purposes of this solicitation, ____ calendar days [contracting officer to insert the number of days based on performance period memo] have been included in the performance period specified in FAR clause 52.211-10. The number of days listed above is contingent upon the contractor providing completed clearance packages for their employees within 10 calendar days of the Notice to Proceed. For any subsequently awarded subcontract, completed security clearance packages for subcontractor workers shall be submitted in conjunction with the completed SF-1413.
**A form package will be issued by the Administrative Contracting Officer or Contracting Officer's Representative (COR) at the institution upon contract award. Completed packages shall be submitted by the PRIME CONTRACTOR ONLY to obtain clearance for each prime and sub-contract employee. Security Clearance packages will NOT be accepted from sub-contractors. Upon clearance being obtained the contractor will be notified. Should a contract employee NOT be cleared to enter the facility for this project, the contractor will be notified immediately. The contractor will be responsible to submit another contract employee as soon as possible for clearance. Be advised, the Federal Bureau of Prisons cannot disclose why an individual does not pass the security clearance process, as it is a violation of law.**
FAO-0010 Assignment of Contract Administration Office and Functions
Pursuant to FAR 42.201 and 42.202, the assigned Contract Administration Office is listed in Block 26 of the Standard Form 1442 Back. This assignment carries with it the authority to perform all of the contract administration functions listed in FAR 42.302(a) and 42.302(b) to the extent that those functions apply to the contract.
The Contract Administration Office is required, however, to obtain written authorization from the Procuring Contracting Officer (PCO) to perform any function listed under 42.302(b). Specifically, the Administrative Contracting Officer (ACO) is required to obtain written authorization to perform the below referenced functions FOR CONSTRUCTION CONTRACT
AWARDS:
(1) Negotiate or negotiate and execute supplemental agreements incorporating contractor proposals resulting from change orders issued under the Changes clause. Before completing negotiations, coordinate any delivery schedule change with the contracting office.
(2) Negotiate prices and execute priced exhibits for unpriced orders issued by the contracting officer under basic ordering agreements.
(3) Negotiate or negotiate and execute supplemental agreements changing contract delivery schedules.
(4) Complete Contractor Performance Assessment Report System (CPARS) evaluations of contractor performance in accordance with FAR Subpart 42.15.
15BBNF26Q00000086 Page 10 of 37
Should any other function under FAR Subpart 42.15 not listed above be required, the ACO is required to contact the PCO for authority.
FAO-0011 Schedule of Values
The Contractor shall prepare a Schedule of Values (SOV) for the project and submit to the Contracting Officer for approval prior to submitting the first application for payment. The SOV shall be correlated with the construction schedule.
The SOV shall be formatted per the Construction Specification Institute Master Format structure. The Contractor may propose an alternate organizational format to the Contracting Officer for approval.
(a) The SOV shall include:
(1) Project name, location, and contract number;
(2) Contractor’s name and address;
(3) Date of submittal.
(b) The SOV shall be arranged in a tabular form with separate columns to indicate the following for each item listed:
(1) Description of Work or Material;
(2) Related specification section, if applicable;
(3) Name of subcontractor, if applicable;
(4) Name of manufacturer or fabricator, if applicable;
(5) Name of supplier, if applicable;
(6) Change orders (modifications) that have affected value, if applicable;
(7) Dollar value;
(8) Percentage of Contract sum rounded to the nearest percent, adjusted to total 100 percent.
(c) The SOV shall breakdown the contract sum in sufficient detail to facilitate continued evaluation of applications for payment and progress reports. The contractor should separate principal subcontract amounts down into several line items.
(d) SOV amounts shall be rounded to the nearest whole dollar. The total of all SOV amounts shall equal the total contract amount.
(e) The contractor shall progress the percentage of completion, with the concurrence of the Contracting Officer’s Representative, for each value in conjunction with the preparation of each monthly application for payment. The progressed value percentages shall directly correlate to the calculated total amount due for each monthly progress payment.
(f) The SOV shall remain fixed for the duration of contract performance. Any revisions to the SOV must be requested in writing, with justification, for approval by the Contracting Officer.
FAO-0012 Progress Meetings
The Administrative Contracting Officer (ACO) shall conduct progress meetings at the project site on a monthly basis, or at intervals as determined by the ACO.
(a) At a minimum, the attendees shall include but is not limited to:
(1) FBOP: Administrative Contracting Officer, Contracting Officer’s Representative (COR), Facility Administr ator/Manager, Architect/Engineer (if applicable), Other Personnel (Executive Staff, Captain, Safety Manager, etc.).
(2) Contractor: Project Manager, Superintendent, and technical support disciplines as appropriate (Subcontractors, Manufacturers, Suppliers, etc.).
(b) The meeting should include, but is not limited to issues such as:
15BBNF26Q00000086 Page 11 of 37
Administrative Contracting Officer:
(1) Old business from previous progress meeting(s);
(2) Status of modifications, certified payrolls, submittals, requests for information (RFI);
(3) Review of payments made to date and review/approve current payment request;
(4) Status of modification proposal requests;
(5) Discuss new business.
COR:
(1) Status of escort coverage;
(2) Review gate or sallyport entrance/exit issues;
(3) Discuss other delays contractor may be experiencing;
(4) Discuss performance/quality issues.
Contractor:
(1) Review/discuss updated progress schedule;
(2) Provide 30 day outlook;
(3) Discuss other issues affecting performance.
FAO-0014 Contract Closeout Procedures (for construction contracts $150,000 or less)
Contract Closeout must be completed upon receipt of property and final payment.
Prior to payment of final invoice:
The Contractor shall submit the following documentation:
(1) Guarantees and warranties;
(2) All operation/maintenance manuals;
(3) Consent of Surety to Final Payment (AIA Document G707), if the contractor furnished a bond;
(4) Release of Claims (GSA Form 1142);
(5) Evidence of no pending labor disputes;
(6) As-built drawings/shop drawings, (if applicable);
(7) Contractor’s final invoice.
AIA forms can be obtained from The American Institute of Architects at www.aiabookstore.com.
GSA forms can be obtained from the General Services Administration at www.gsa.gov (click on the “Forms Library” link).
15BBNF26Q00000086 Page 12 of 37
Section 4 - Contract Clauses
Clauses By Reference
52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.acquisition.gov
Clause Title Fill-ins (if applicable)
52.203-17 Contractor Employee Whistleblower Rights (Nov 2023)
52.203-19 Prohibition on Requiring Certain Internal Confidentiality
Agreements or Statements (Jan 2017)
52.204-9 Personal Identity Verification of Contractor Personnel
(Jan 2011)
52.204-13 (DEV) System for Award Management-Maintenance (Oct 2018)
(DEVIATION NOV 2025)
52.204-19 Incorporation by Reference of Representations and
Certifications (Dec 2014)
52.209-6 (DEV) Protecting the Government's Interest When
Subcontracting with Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded (Jan
2025) (DEVIATION NOV 2025)
52.209-10 (DEV) Prohibition on Contracting With Inverted Domestic
Corporations (Nov 2015) (DEVIATION NOV 2025)
52.212-4 (DEV) Terms and Conditions-Commercial Products and
Commercial Services (Nov 2023) (DEVIATION NOV
2025)
52.219-6 (DEV) Notice of Total Small Business Set-Aside (Nov 2020)
(DEVIATION DEC 2025)
52.219-28 (DEV) Postaward Small Business Program Rerepresentation
(Jan 2025) (DEVIATION DEC 2025)
52.212-4 is hereby tailored IAW FAR Dev 12.205(b) (1)(ii):
(b) Inspection/Acceptance IAW FAR Dev 52.246-12.
(d) Changes. IAW FAR Dev 52.243-5.
(i) Payment. Retain (i) payment, supplement with FAO-0023 Progress Payment.
15BBNF26Q00000086 Page 13 of 37
Clause Title Fill-ins (if applicable)
52.222-1 (DEV) Notice to the Government of Labor Disputes (Feb 1997)
(DEVIATION DEC 2025)
52.222-3 (DEV) Convict Labor (June 2003) (DEVIATION DEC 2025)
52.222-6 (DEV) Construction Wage Rate Requirements (Aug 2018)
(DEVIATION AUG 2025)
52.222-7 (DEV) Withholding of Funds (May 2014) (DEVIATION DEC
2025)
52.222-8 (DEV) Payrolls and Basic Records (Jul 2021) (DEVIATION
DEC 2025)
52.222-9 (DEV) Apprentices and Trainees (July 2005) (DEVIATION DEC
2025)
52.222-10 (DEV) Compliance with Copeland Act Requirements (Feb
1988) (DEVIATION DEC 2025)
52.222-11 (DEV) Subcontracts (Labor Standards) (May 2014)
(DEVIATION DEC 2025)
52.222-12 Contract Termination - Debarment (May 2014)
52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (May 2014)
52.222-14 (DEV) Disputes Concerning Labor Standards (Feb 1988)
(DEVIATION DEC 2025)
52.222-15 Certification of Eligibility (May 2014)
52.222-19 (DEV) Child Labor-Cooperation with Authorities and Remedies
(Jan 2025) (DEVIATION MAR 2026)
52.222-36 (DEV) Equal Opportunity for Workers with Disabilities (Jun
2020) (DEVIATION DEC 2025)
52.222-50 (DEV) Combating Trafficking in Persons (Oct 2025)
(DEVIATION DEC 2025)
52.222-55 (DEV) Minimum Wages for Contractor Workers Under
Executive Order 14026 (Jan 2022) (DEVIATION DEC
2025)
15BBNF26Q00000086 Page 14 of 37
52.222-62 (DEV) Paid Sick Leave Under Executive Order 13706 (Jan
2022) (DEVIATION DEC 2025)
52.222-90 Addressing DEI Discrimination by Federal Contractors
(APR 2026)
52.223-5 Pollution Prevention and Right-to-Know Information
(May 2024)
52.223-23 (DEV) Sustainable Products (May 2024) (DEVIATION DEC
2025)
52.225-1 (DEV) Buy American-Supplies (Oct 2022) (DEVIATION DEC
2025)
52.225-9 (DEV) Buy American-Construction Materials (Oct 2022)
(DEVIATION DEC 2025)
List of expected materials:
"None"
52.225-10 Notice of Buy American Requirement-Construction
Materials (May 2014)
52.226-8 Encouraging Contractor Policies To Ban Text
Messaging While Driving (May 2024)
52.227-1 Authorization and Consent (Jun 2020)
52.227-2 Notice and Assistance Regarding Patent and Copyright
Infringement (Jun 2020)
52.227-4 Patent Indemnity-Construction Contracts (Dec 2007)
52.228-2 Additional Bond Security (Oct 1997)
52.228-11 Individual Surety-Pledge of Assets (Feb 2021)
52.228-13 Alternative Payment Protections (July 2000)
52.228-14 Irrevocable Letter of Credit (Nov 2014)
52.232-23 Assignment of Claims (May 2014)
52.232-27 Prompt Payment for Construction Contracts (Jan 2017)
52.232-33 Payment by Electronic Funds Transfer-System for
Award Management (Oct 2018)
52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013)
15BBNF26Q00000086 Page 15 of 37
52.232-40 Providing Accelerated Payments to Small Business
Subcontractors (Mar 2023)
52.233-1 (DEV) Disputes (May 2014) (DEVIATION NOV 2025)
52.233-3 (DEV) Protest after Award (Aug 1996) (DEVIATION NOV 2025)
52.233-4 (DEV) Applicable Law for Breach of Contract Claim (Oct 2004)
(DEVIATION NOV 2025)
52.236-2 (DEV) Differing Site Conditions (Apr 1984) (DEVIATION AUG
2025)
52.236-3 (DEV) Site Investigation and Conditions Affecting the Work
(Apr 1984) (DEVIATION AUG 2025)
52.236-5 (DEV) Material and Workmanship (Apr 1984) (DEVIATION
AUG 2025)
52.236-6 (DEV) Superintendence by the Contractor (Apr 1984)
(DEVIATION AUG 2025)
52.236-7 (DEV) Permits and Responsibilities (Nov 1991) (DEVIATION
AUG 2025)
52.236-8 (DEV) Other Contracts (Apr 1984) (DEVIATION AUG 2025)
52.236-9 (DEV) Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Apr 1984)
(DEVIATION AUG 2025)
52.236-10 (DEV) Operations and Storage Areas (Apr 1984) (DEVIATION
AUG 2025)
52.236-11 (DEV) Use and Possession Prior to Completion (Apr 1984)
(DEVIATION AUG 2025)
52.236-12 (DEV) Cleaning Up (Apr 1984) (DEVIATION AUG 2025)
52.236-13 (DEV) Accident Prevention (Nov 1991) (DEVIATION AUG
2025)
52.236-14 (DEV) Availability and Use of Utility Services (Apr 1984)
(DEVIATION AUG 2025)
52.236-17 (DEV) Layout of Work (Apr 1984) (DEVIATION AUG 2025)
15BBNF26Q00000086 Page 16 of 37
52.236-21 (DEV) Specifications and Drawings for Construction (Feb 1997)
(DEVIATION AUG 2025)
52.240-91 (DEV) Security Prohibitions and Exclusions (DEVIATION NOV
2025)
52.240-92 (DEV) Security Requirements (DEVIATION NOV 2025)
52.240-93 (DEV) Basic Safeguarding of Covered Contractor Information
Systems (DEVIATION NOV 2025)
52.242-14 Suspension of Work (Apr 1984)
52.243-5 (DEV) Changes and Changed Conditions (Apr 1984)
(DEVIATION JUL 2025)
52.246-12 Inspection of Construction (Aug 1996)
52.246-21 Warranty of Construction (Mar 1994)
52.249-1 Termination for Convenience of the Government (Fixed-
Price) (Short Form) (Apr 1984)
52.253-1 (DEV) Computer Generated Forms (Jan 1991) (DEVIATION
NOV 2025)
2852.201-70 Contracting Officer's Representative (COR) (NOV 2020) COR Name: "Jacob Harrison"
Org: "FCI Oxford"
Address: "350 Elk Ave, Oxford, WI 53952"
Phone: "608-584-6184"
Contract: "[Contract Number]"
Period: "[Period]"
Clauses By Full Text
52.252-2 Clauses Incorporated by Reference (Feb 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
www.acquisition.gov
15BBNF26Q00000086 Page 17 of 37
[Insert one or more Internet addresses]
(End of clause)
52.252-6 Authorized Deviations in Clauses (Nov 2020)
(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the clause.
(b) The use in this solicitation or contract of any Justice Acquisition Regulation. [insert regulation name] (48 CFR Chapter
28) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
(End of clause)
2852.223-70 Unsafe Conditions Due to the Presence of Hazardous Material (NOV 2020)
(a) “Unsafe condition” as used in this clause means the actual or potential exposure of Contractor or Government employees to a hazardous material.
(b) “Hazardous Material” as used in this clause includes any material defined as hazardous under the latest version of Federal Standard No. 313 (including revisions adopted during the term of the contract), any other potentially hazardous material requiring safety controls, or any other material or working condition designated as hazardous by the Contracting Officer's Representative (COR).
(c) The Occupational Safety and Health Administration (OSHA) is responsible for issuing and administering regulations that require Contractors to apprise its employees of all hazards to which they may be exposed in the course of their employment; proper conditions and precautions for safe use and exposure; and related symptoms and emergency treatment in the event of exposure.
(d) Prior to commencement of work, Contractors are required to inspect for and report to the Contracting Officer the presence of, or suspected presence of, any unsafe condition including asbestos or other hazardous materials or working conditions in areas in which they will be working.
(e) If during the performance of the work under this contract, the Contractor or any of its employees, or subcontractor employees, discovers the existence of an unsafe condition, the Contractor shall immediately notify the Contracting Officer, or designee (with written notice provided not later than three (3) working days thereafter), of the existence of an unsafe condition. Such notice shall include the Contractor's recommendations for the protection and the safety of Government, Contractor and subcontractor personnel and property that may be exposed to the unsafe condition.
(f) When the Government receives notice of an unsafe condition from the Contractor, the parties will agree on a course of action to mitigate the effects of that condition and, if necessary, the contract will be amended. Failure to agree on a course of action will constitute a dispute under the Disputes clause of this contract.
(g) Nothing contained in this clause shall relieve the Contractor or subcontractors from complying with applicable Federal, State, and local laws, codes, ordinances and regulations (including the obtaining of licenses and permits) in connection with hazardous material including but not limited to the use, disturbance, or disposal of such material.
(End of Clause)
DOJ-02 Contractor Privacy Requirements (JAN 2022)
A. Limiting Access to Privacy Act and Other Sensitive Information
(1) Privacy Act Information
In accordance with FAR 52.224-1 Privacy Act Notification (APR 1984) and FAR 52.224-2 Privacy Act (APR 1984), if this contract requires Contractor personnel to have access to information protected by the Privacy Act of 1974, the contractor is advised that the relevant DOJ system of records notices (SORNs) applicable to this Privacy Act information may be found at https://www.justice.gov/opcl/doj-systems-records.[1] Applicable SORNs published by other agencies may be accessed through those agencies’ websites or by searching the Federal Digital System (FDsys) available at http://www.gpo.gov/fdsys/. SORNs may be updated at any time.
(2) Prohibition on Performing Work Outside a Government Facility/Network/Equipment
Except where use of Contractor networks, IT, other equipment, or Workplace as a Service (WaaS) is specifically authorized within this contract, the Contractor shall perform all tasks on authorized Government networks, using
15BBNF26Q00000086 Page 18 of 37
Government-furnished IT and other equipment and/or WaaS and Government information shall remain within the confines of authorized Government networks at all times. Any handling of Government information on Contractor networks or IT must be approved by the Senior Component Official for Privacy of the component entering into this contract. Except where remote work is specifically authorized within this contract, the Contractor shall perform all tasks described in this document at authorized Government facilities; the Contractor is prohibited from performing these tasks at or removing Government-furnished information to any other facility; and Government information shall remain within the confines of authorized Government facilities at all times. Contractors may only access classified materials on government furnished equipment in authorized government owned facilities regardless of remote work authorizations.
(3) Prior Approval Required to Hire Subcontractors
The Contractor is required to obtain the Contracting Officer's approval prior to engaging in any contractual relationship (Subcontractor) in support of this contract requiring the disclosure of information, documentary material and/or records generated under or relating to this contract. The Contractor (and any Subcontractor) is required to abide by Government and Agency guidance for protecting sensitive and proprietary information.
(4) Separation Checklist for Contractor Employees
The Contractor shall complete and submit an appropriate separation checklist to the Contracting Officer before any employee or Subcontractor employee terminates working on the contract. The Contractor must submit the separation checklist on or before the last day of employment or work on the contract. The separation checklist must verify: (1) return of any Government-furnished equipment; (2) return or proper disposition of personally identifiable information (PII)[2], in paper or electronic form, in the custody of the employee or Subcontractor employee including the sanitization of data on any computer systems or media as appropriate; and (3) termination of any technological access to the Contractor’s facilities or systems that would permit the terminated employee’s access to PII or other sensitive information.
In the event of adverse job actions resulting in the dismissal of a Contractor or Subcontractor employee before the separation checklist can be completed, the Prime Contractor must notify the Contracting Officer within 24 hours and confirm receipt of the notification. In the case the Contractor is unable to notify the Contracting Officer, then the Contractor should notify the Contract Officer’s Representative (COR).
Contractors must complete the separation checklist with the Contracting Officer or COR by returning all Government-furnished property including, but not limited to, computer equipment, media, credentials and passports, smart cards, mobile devices, Personal Identity Verification (PIV) cards, calling cards, and keys and terminating access to all user accounts and systems. Unless the Contracting Officer requests otherwise, the relevant Program Manager or other Key Personnel designated by the Contracting Officer or COR may facilitate the return of equipment.
B. Privacy Training, Safeguarding, and Remediation
(1) Required Security and Privacy Training for Contractors
The Contractor must ensure that all employees take appropriate privacy training, including Subcontractors who have access to PII as well as the creation, use, dissemination and/or destruction of PII at the outset of the employee’s work on the contract and every year thereafter. Training must include procedures on how to properly handle PII, including heightened security requirements for the transporting or transmission of sensitive PII, and reporting requirements for a suspected breach or loss of PII. These courses, along with more information about DOJ security and training requirements for Contractors, are available at https://www.justice.gov/jmd/learndoj.
The Federal Information Security Modernization Act of 2014 (FISMA) requires all individuals accessing DOJ information to complete training on records management, cybersecurity awareness, and information system privacy awareness. Contractor employees are required to sign the “Privacy Rules of Behavior,” acknowledging and agreeing to abide by privacy law, policy, and certain privacy safeguards, prior to accessing DOJ information. These Rules of Behavior are made available to all new users of DOJ’s computer network and to trainees at the conclusion of DOJ-OPCL-CS-0005.
The Contractor should maintain copies of certificates as a record of compliance and must submit an email notification annually to the COR verifying that all employees working under this contract have completed the required privacy and cybersecurity training.
15BBNF26Q00000086 Page 19 of 37
(2) Safeguarding PII Requirements
Contractor employees must comply with DOJ Order 0904 and other guidance published to the publicly-available Office of Privacy and Civil Liberties (OPCL) Resources page[3] relating to the safeguarding of PII, including the use of additional controls to safeguard sensitive PII (e.g., the encryption of sensitive PII). This requirement flows down from the Prime Contractor to all Subcontractors and lower tiered subcontracts.
(3) Non-Disclosure Agreement Requirement
Prior to commencing work, all Contractor personnel that may have access to PII or other sensitive information shall be required to sign a Non-Disclosure Agreement (NDA) and the DOJ IT Rules of Behavior. The Non-Disclosure Agreement:
(a) prohibits the Contractor from retaining or divulging any PII or other sensitive information, or derivatives therefrom, furnished by the Government or to which they may otherwise come in contact as a result of their performance of work under the contract/task order that is otherwise not publicly available, whether or not such information has been reduced to writing; and
(b) requires the Contractor to report any loss of control, compromise, unauthorized disclosure, or unauthorized acquisition of PII or other sensitive information to the component-level or headquarters Security Operations Center within one (1) hour of discovery.
The Contractor should maintain signed copies of the NDA for all employees as a record of compliance. The Contractor should also provide copies of each employee’s signed NDA to the Contracting Officer before the employee may commence work under the contract/task order.
(4) Prohibition on Use of PII in Vendor Billing and Administrative Records
The Contractor’s invoicing, billing, and other financial or administrative records or databases is not authorized to regularly store or include any sensitive PII or other confidential government information that is created, obtained, or provided during the performance of the contract without the written permission of the Senior Component Official for Privacy (SCOP). It is acceptable to list the names, titles and contact information for the Contracting Officer, COR, or other personnel associated with the administration of the contract in the invoices as needed.
(5) Reporting Actual or Suspected Data Breach
Contractors must report any actual or suspected breach of PII within one hour of discovery.[4] A “breach” is an incident or occurrence that involves the loss of control, compromise, unauthorized disclosure, unauthorized acquisition, or any similar occurrence where: (1) a person other than an authorized user accesses or potentially accesses PII or (2) an authorized user accesses or potentially accesses PII for an other than authorized purpose.
The report of a breach must be made to DOJ. The Contractor must cooperate with DOJ’s inquiry into the incident and efforts to minimize risks to DOJ or individuals, including remediating any harm to potential victims.
(a) The Contractor must develop and maintain an internal process by which its employees and Subcontractors are trained to identify and report the breach, consistent with DOJ Instruction 0900.00.01[5], Reporting and Response Procedures for a Breach of Personally Identifiable Information.
(b) The Contractor must report any such breach by its employees or Subcontractors to the DOJ Security Operations Center (dojcert@usdoj.gov, 202-357-7000); Component-level Security Operations Center and Component-level Management Team, where appropriate; the COR; and the Contracting Officer within one (1) hour of the initial discovery.
(c) The Contractor must provide a written report to the DOJ Security Operations Center (dojcert@usdoj.gov, 202-357-7000) within 24 hours of discovery of the breach by its employees or Subcontractors. The report must contain the following information:
(i) Narrative or detailed description of the events surrounding the suspected loss or compromise of information.[6] Date, time, and location of the incident.
15BBNF26Q00000086 Page 20 of 37
(ii) Amount, type, and sensitivity of information that may have been lost or compromised, accessed without authorization, etc.
(iii) Contractor’s assessment of the likelihood that the information was compromised or lost and the reasons behind the assessment.[7]
(iv) Names and classification of person(s) involved, including victim, Contractor employee/Subcontractor and any witnesses.
(v) Cause of the incident and whether the company’s security plan was followed and, if not, which specific provisions were not followed.[8]
(vi) Actions that have been or will be taken to minimize damage and/or mitigate further compromise.
(vii) Recommendations to prevent similar situations in the future, including whether the security plan needs to be modified in any way and whether additional training may be required.
(d) The Contractor shall provide full access and cooperation for all activities determined by the Government to be required to ensure an effective incident response, including providing all requested images, log files, and event information to facilitate rapid resolution of sensitive information incidents.
(e) At the Government’s discretion, Contractor employees or Subcontractor employees may be identified as no longer eligible to access PII or to work on that contract based on their actions related to the loss or compromise of PII.
(6) Victim Remediation
At DOJ’s request, the Contractor is responsible for notifying victims and providing victim remediation services in the event of a breach of PII held by the Contractor, its agents, or its Subcontractors, under this contract. Victim remediation services shall include at least 18 months of credit monitoring and, for serious or large incidents as determined by the Government, call center help desk services for the individuals whose PII was lost or compromised. When DOJ requests notification, the Department Chief Privacy and Civil Liberties Officer and SCOP will direct the Contractor on the method and content of such notification to be sent to individuals whose PII was breached. By performing this work, the Contractor agrees to full cooperation in the event of a breach.
The Contractor should be self-insured to the extent necessary to handle any reasonably foreseeable breach, with another source of income, to fully cover the costs of breach response, including but not limited to victim remediation.
C. Government Records Training, Ownership, and Management
(1) Records Management Training and Compliance
(a) The Contractor must ensure that all employees and Subcontractors that have access to PII as well as to those involved in the creation, use, dissemination and/or destruction of PII take the DOJ Records and Information Training for New Employees (RIM) training course or another training approved by the Contracting Officer or COR.
This training will be provided at the outset of the Subcontractor’s/employee’s work on the contract and every year thereafter.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .