STATEMENT OF WORK

South Central Regional Office/Grand Prairie Office Complex- B&F PROJECT

Replace Chiller

I. SPECIFICATIONS:

A. INTRODUCTION

A.1 The Federal Bureau of Prisons (FBOP), South Central Regional Office U.S. Armed Forces Reserve Complex 344 Marine Forces Drive, Grand Prairie, TX 75051, intends to make a single award to a responsible entity that will provide all necessary equipment, labor, materials, and incidentals to remove old chiller and installation of like new air cooled chiller.

All equipment specified in this statement must be brand name or an equal product. Should your firm choose to submit an equal product, you must submit all technical specification of the equal product to be analyzed and a technical determination issued with acceptance/non-acceptance.

B. SCOPE OF WORK

Replace Air-Cooled Chiller

This project basis for design is AGZ101E air-cooled water chiller with a period of performance of 60 calendar days.

Contractor shall remove the identified one of two existing Daikin Air Cooled Chiller Model # AGZ100EPMNN-ER00, serial #STNU161100155 and supply and installation of (1) new AGZ101E air-cooled water chiller or equivalent. Contractor shall protect existing piping and electrical connections during removal of chiller and of entire project. If components are damaged when disconnecting or during construction phase then contractor will have to replace damaged component.

During replacement of the chiller contractor shall ensure no interruption of chilled water to the associated buildings through the duration of the project. New chiller must meet all of the following specifications:

Operating Weight 4780 LBS Part Load Flow System Only, Minimum Flow Rate IP - GPM (97.4) DP ft.(2.3) SI - Ips (6.1) DP kpa (7.0) Full Load Flow System Only, Minimum Flow Rate IP - GPM (152.3) DP ft.(5.3) SI - Ips (9.6) DP kpa (15.9) Fixed and Variable Flow System Nominal Flow Rate, IP - GPM (243.6) DP ft. (11.6) SI - Ips (15.4) DP kpa (34.7) Maximum Flow Rate, IP - GPM (356.0) DP ft. (23.0) SI - Ips (22.5 ), DP kpa (68.7)

Dynamic Set Point Ranges and Defaults Condenser Target - 100% Circuit Capacity Default 37.78°C (100°F) Range 37.78 to 46.11°C (100 to 115°F) Condenser Target - 67% Circuit Capacity Default 32.22°C (90°F)Range 32.22 to 43.33°C (90 to 110°F) Condenser Target - 50% Circuit Capacity Default 32.22°C (90°F)Range 32.22 to 46.11°C (90 to 115°F) (100 to 115°F) Condenser Target - 33% Circuit Capacity Default 32.22°C (90°F)) Range 32.22 to 40.56°C (90 to 105°F) Fan Stage Up Deadband Default 111.11°C (20°F) Range 11.11 to 13.89°C (20 to 25°F) Fan Stage Up Deadband 2Default 8.33°C (15°F) Range 8.33 to 11.11°C (15 to 20°F) Fan Stage Up Deadband 3Default 5.56°C (10°F) Range 5.56 to 8.33°C (10 to 15°F) Fan Stage Up Deadband 4 Default 5.56°C (10°F)) Range 5.56 to 8.33°C (10 to 15°F) Fan Stage Down Deadband 4 Default 5.56°C (10°F) Range 3.33 to 5.56°C (6 to 10°F) Fan Stage Down Deadband 3 Default 5.56°C (10°F)Range 3.33 to 5.56°C (6 to 10°F) Fan Stage Down Deadband 2 Default 5.56°C (10°F)) Range 5.56 to 8.33°C (10 to 15°F) Fan Stage Down Deadband 1Default 11.11°C (20°F)Range 8.33 to 11.11°C (15 to 20°F)

4 Compressors Minimum Flows and Corresponding Maximum Effective Full Capacity Delta T with Variable Flow Unit Capacity 100% Minimum Flow (nominal %) 62.5% Max Effective Full Capacity DT 8.9 °C (16 °F) Unit Capacity 75% Minimum Flow (nominal %) 55% Max Effective Full Capacity DT 10.1 °C (18.2 °F) Unit Capacity 50% Minimum Flow (nominal %) 47.5% Max Effective Full Capacity DT 11.7 °C (21.1 °F) Unit Capacity 25% Minimum Flow (nominal %) 40% Max Effective Full Capacity DT 13.9 °C (25 °F)

Scope of Work Clarification

1. The existing air-cooled chiller, 100 Ton AGZ Daikin Model Number AGZ100EPMNN-ER00 shall be removed and replaced with new 100 Ton Daikin Model Number AGZ101E REVISED 3/8/2022 air-cooled chiller or equivalent.

2. Through duration of project, contractor must ensure there is no interruption of chilled water supplied to the system.

3. Valve off the chilled water supply and return currently feeding the existing Daikin Chiller.

4. Disconnect and protect all line voltage and low voltage from the existing chiller.

5. Disconnect and protect the chilled water piping.

6. Dispose of existing chiller in adherence to all applicable EPA guidelines.

7. Provide and install (1) replacement Daikin 100-ton air-cooled chiller.

8. Set new chiller onto existing chiller pad.

9. Reconnect all chilled water piping, line voltage, and low voltage to the new chiller.

10. Ensure chiller is connected and programed to existing Building Management System.

11. Fill and test system for leaks.

12. Insulate and piping disturbed or replaced during chiller replacement.

13. Re-use existing heat trace.

14. Perform Factory Startup.

C. QUALITY ASSURANCE/INSTALLATION REQUIREMENTS

The Contractor shall notify the COR a minimum of five (5) days prior to the final testing of manufacturer start up and certification so that arrangements can be made to have BOP required staff available to observe testing. A complete plan detailing test procedures must be submitted to the COR no later than ten (10) days in advance for final operational checks and testing of the chiller.

All seismic zone requirements, environmental compliance, Life Safety, NFPA, ADA-ABA, and Federal, State and Local codes and regulations will be considered during all phases of this project.

Services and materials provided by the contractor will adhere to and shall be consistent with the most current industry standards, the Underwriters Laboratories (UL) and the General and the National Electric Code (NEC).

It is the contractor’s responsibility to obtain permitting, should it be required. Copies of all permits must be submitted to the COR upon receipt from local agency.

D. UTILITIES

The FBOP will provide water, use of restrooms and minimal electricity service (120V) for small hand power tools including battery chargers. The contractor will provide all other equipment, supplies and materials needed to complete this project.

E. TESTING AND ACCEPTANCE

The Contractor shall notify the COR five (5) days prior to the final system testing and certification so that arrangements can be made to have BOP required staff available to observe manufacturer start-up and testing . A complete plan detailing test procedures must be submitted to the Contracting officers representative (COR) in advance for final check out and testing of the complete system.

F. HOUSEKEEPING AND MATERIAL DISPOSAL

The contractor awarded the contract will be responsible to ensure the premises are kept clean and free from accumulations of waste materials and rubbish at all times. The contractor will remove all debris, scrap, and rubbish from the work area daily. Surplus materials and all equipment shall be promptly removed from the site upon completion of the work. The Contractor shall be responsible to remove all debris and waste materials from the job site at South Central Regional Office site upon conclusion and acceptance of the project. These items must be disposed of in accordance with all Federal, State, and local laws.

G. SUBMITTALS & TRAINING

Submittals:

1. The contractor shall provide written submittals to the COR describing recommended equipment within (15) days from receiving the Notice to proceed for approval.

3. All security clearance paperwork/documentation shall be submitted to the COR a minimum of (14) working day prior to the start of work (see below).

4. The Contractor shall prepare and provide to the COR for approval, PDF file specifications of all material and products prior to their use. Submittals will be prepared as PDF package, and transmit to Government by sending via email.

Contractor shall also provide three (3) copies of the Safety Data Sheets (SDS) on all materials and substances that may be used during the course of the project. In the event the material is not approved by the Safety Manager, it shall be the responsibility of the Contractor to locate and procure an alternative product.

5. For security and safety purposes, forty-eight (48) hour advance notice in writing, prior to disruption to the system must be given to the Contracting Officer and COR.

6. Provide complete narrative descriptions of all system operations.

8. The contractor shall provide an Installation Certification of the completed and tested systems that contains an affidavit signed by the contractor and manufacturer’s representative, notarized, certifying that the complete systems meet the contract requirements and is fully operational per the manufacturer's recommendations.

9. Any deviations from this Statement of Work will be considered a Change Order Request and must be authorized through the institution’s Contracting Officer prior to the implementation of the requested change.

10. It is the Contractor’s responsibility to repair and/or replace any Government property damaged by contractors/subcontractors employees. Damage will be corrected and restored to previous condition at no cost to the Government.

11. It shall be the Contractor’s responsibility for obtaining all measurements and data requirements to comply with manufacturer’s installation recommendations. All installations must be in accordance with product manufacture’s recommendations.

Training:

Upon completion of the installation, testing, and acceptance by the Government, the contractor shall provide operation/maintenance manuals for each piece of equipment/system installed.

The contractor shall furnish manufacturer’s factory-certified training and provide system certification for two (2) Bureau of Prisons employees, thus enabling them to maintain and repair all equipment and systems.

II. CONTRACTOR SECURITY/WORKING REGULATIONS

A. Work Hours:

Work Hours for the contractor are 7:00 AM – 4:00 PM, Monday - Friday, excluding weekends and federal holidays. Any work required to be completed at any other time than noted above must be requested in writing to the COR five (5) working days prior to the start of the work. In the event of any equipment being replaced that would result in downtime of the normal orderly running of the institution, alternate work hours may be authorized in accordance with the time frame stated above.

Access to the site will be available during normal working hours except during emergencies. It shall be the responsibility of the Contractor to familiarize himself, his employees, and his subcontractors of the working hours and conditions in at the facility, as working hours may not constitute a full eight-hour workday. The Government assumes no responsibility to the Contractor nor to any of his subcontractors for shorter hours due to institutional emergencies or entry and/or exit of workers necessitated by normal institution routines.

B. Delivery of Materials:

All construction materials/equipment required for work on this project is required to be processed by the Contractor and coordinated with the institution COR for temporary storage.

Any construction related deliveries which are directly shipped to the contractor can be received between the hours of 7:00 a.m. to 12:00 p.m., Monday through Friday, excluding Federal Holidays. At no point will a Bureau of Prisons (BOP) staff member receive or sign for a delivery if the contractor or his representative is not present to verify and accept the delivery.

Under no circumstances will SCRO or its staff be responsible for the acceptance of any Contractor or company deliveries.

The contractor shall be responsible for providing their own means of loading and unloading contractor material or equipment.

C. Storage of Materials and Equipment:

Construction materials may be stored on site on a mutual agreeable location designated by the COR. Tools shall not be stored on site and must be brought in daily by the contractor.

All tools will be inventoried prior to beginning work and will be inventoried back in to ensure accurate accountability when leaving at the end of each work day.

Materials cannot be stored at a height that would create a fall hazard. All tools will be inventoried prior to entering the Institution. At the start of each work day all tools will be inventoried out on a daily tool inventory sheet and at the end of the work day all tools will be inventoried back in to ensure accurate accountability of all tools at the end of each work day.

All contractor owned extension cords that will be used during the project, regardless of length, shall be in good condition with no broken outer Insulation. Extension cords are considered a “high risk” tool having a Federal Bureau of Prisons’ tool classification of Double A. All contractor owned extension cords used for this project will be required to exit the institution at the end of every work day for the duration of the project.

All contractor owned ladders approved for use within the institution, regardless of the size, shall be stored in a pre-determined area and secured to a stationary fixture with a heavy link chain and lock which would prevent removal.

D. Security Clearance/Contractor Badges:

The contractor shall provide the COR with all the necessary security clearance documents for all contractors and subcontractor employees accessing the institution and be security cleared for badging within 14 days of receiving the Notice to Proceed, as stated above. Security clearance documents will only be accepted from the prime contractor. If submitted by a sub-contractor, they will be rejected. It is the prime contractor’s responsibility to review security clearance submissions to ensure they are complete.

In the event a contractor or subcontractor employee cannot pass the security clearance process, it will be the contractor’s responsibility to provide another candidate. By law the BOP cannot, and will not, release any information to the contractor concerning the nature of why a contractors or subcontractor employee was not able to pass the security clearance process.

All contractors/subcontractors working at MDC Los Angeles will be issued and required to wear a picture ID/contractor badge provided by the institution. For security reasons, the badge will be worn in a visible manner as directed by the

COR.

All contractors and subcontractor employees will provide a check list of all employees on site each day to the COR, verifying the number of workers on site each day and that all workers are approved to be on site.

E. Safety and Personal Protective Equipment:

All contractors and employees shall have and wear the required personal protective equipment (PPE) prescribed by industry standards at all times while on the job site. It is the responsibility of the contractor to provide all PPE equipment. All ladders regardless of the size shall be stored, and secured to a stationary fixture with a chain and lock in a predetermined area, in a way that they cannot be removed. If ladders are required, immediately consult with the COR to ensure that he or she can make timely notification to appropriate institution staff. All extension cords regardless of length shall be in good condition with no broken outer insulation and will be secured in a locked construction gang box.

Should a system require Lock-out/Tag-out, the system will be required to have both Contractor and MDC Los Angeles locks on the isolation point to prevent shock. All Lock-out/Tag-out procedures will be in compliance with the institution Lock-out program.

F. Additional Considerations:

1. Contractors will NOT be allowed to bring cell phones, cameras or two way pagers into MDC Los Angeles. The

Facilities Department maintains a digital camera that will be utilized by BOP staff to document the project work. The Contractor may request copies of these documentation photos for record keeping.

2. Contractor will be permitted to wear jeans in the institution, however, shorts, green or khaki-color clothing will not be allowed. The clothes will be proper and suitable for the services that are being provided.

3. Lunches will be consumed at the work site. Contractor shall ensure they have everything they need for their lunch when they check-in first thing in the morning.

4. Federal smoking policy on Federal property states that smoking is only allowed in outdoor designated areas. This policy will be strictly enforced.