SOW-Replace Boiler Controls.pdf

PDF 54 KB Posted

Attached to
FCI Sandstone - 24Z4AZ3 Replace Boiler Controls - Sources Sought
Solicitation number
15B41325Q00000002
Issued by

About this file

This Statement of Work outlines requirements for replacing boiler controls at FCI Sandstone's Powerhouse facility in Minnesota. The project involves replacing controls on three high-pressure boilers and installing a compatible master panel with a minimum 12-inch color touch screen. The new system must be a Siemens LMV52 or equivalent.

The contractor's scope includes removing existing controls, installing and wiring new controls, providing updated schematics, installing a master panel in the operator's office with failsafe mode, implementing BACNET integration for monitoring, installing belly temp sensors and speed sensors, programming RPM control, tuning boilers on gas with file flow meter, starting up boilers on both gas and fuel oil with detailed reporting, and providing all documentation and onsite training. Work must be performed Monday through Friday between 7:00 AM and 3:00 PM at 2300 County Road 29, Sandstone, MN 55072, with advance approval required for work outside these hours. The contractor is responsible for all labor and materials needed for the complete installation and commissioning of the system.

View the file

Other files

File Type Posted
FCI Sandstone - MRQ - Replace Boiler Controls.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work FCI Sandstone

Replace Boiler Controls

FCI Sandstone is soliciting for the replacement of the boiler controls system on three (3) high pressure boilers and installing a compatible master panel with at least a 12-inch color touch screen.

The new boiler controls system will be replacing the controls on three (3) boilers in the Powerhouse at FCI Sandstone.

Contractor shall be responsible for providing labor, and all materials needed for the removal of old boiler controls and installation, programming and startup of the new boiler controls system. The new boiler control system will be a Siemens LMV52, or equivalent and compatible with a Siemens master panel and have at least a 12-inch color touch screen.

The contractor will also be responsible for:

• removing existing controls

• installation and wiring of new controls in boiler room, three (3) boilers

• provide updated wiring prints and schematics

• installation of new master panel (in operator’s office)

• program master panel (controls shall provide all operation of the boilers, failsafe mode if panel malfunctions will not interrupt boiler operation)

• provide full integration via BACNET (customer shall be able to monitor all operations of the boiler)

• installing compatible belly temp sensors (on each boiler)

• installing new compatible speed sensors on old blower motors (on each blower motor assembly)

• re-programming drive for RPM control

• tuning boilers on gas with file flow meter (which will provide better accuracy with load percentage of boiler equal to BTU/hr and will eliminate the need for separate gas flow meters at each boiler)

• contractor will be required to start up boilers on both gas and fuel oil and provide a detailed startup report

• provide FCI Sandstone all manuals, related paperwork and onsite training

Work Location: 2300 County Road 29, Sandstone, MN 55072.

Hours of operation will be Monday – Friday – 7:00 AM to 3:00 PM. Work to be completed during other times will need to be approved in advance.