15B40824Q00000001.pdf

PDF 472 KB Posted

Attached to
Asbestos Abatement Federal contract opportunity
Solicitation number
15B40824Q00000001
Issued by
Department of Justice Bureau of Prisons Field Acquisition Office

About this file

This document is a Solicitation for an asbestos abatement project. The selected contractor will be responsible for removing approximately 5,725 square feet of asbestos-containing floor tile and adhesive from the second floor of building 62. The solicitation is being issued by the Department of Justice Bureau of Prisons Field Acquisition Office. Sealed bids are due by 2:00 pm local time on July 12, 2024. The acquisition will be conducted under FAR Part 12 - Acquisition of Commercial Items and Part 13 - Simplified Acquisition Procedures, and the Government intends to award the contract to the lowest price, technically acceptable offeror. The contract is a firm-fixed price with a performance period of 14 calendar days. No bonds are required for contracts of $150,000 or less. Additional details are provided in the solicitation documents regarding contractor security requirements, submittals, payment procedures, and other special contract requirements.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

15B40824Q00000001 Page 1 of 44

SOLICITATION,OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NUMBER

15B40824Q00000001

SEALED BID (IFB)

INVITATION FOR BID

(RFP) REQUEST FOR

QUOTE

2. TYPE OF SOLICITATION 3. DATE ISSUED

06/20/2024

PAGE OF PAGES

1 44

IMPORTANT -The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER

15B40824PR000151

6. PROJECT NUMBER

24Z4AX2

CODE 15BFA0

Federal Bureau of Prisons Field Acquisition Office U.S. Armed Forces Reserve Complex 346 Marine Forces Drive Grand Prairie, TX 75051

7. ISSUED BY

Federal Bureau of Prisons Field Acquisition Office U.S. Armed Forces Reserve Complex 346 Marine Forces Drive Grand Prairie, TX 75051

Charles Dailey

(O) 202-598-6044 cdailey@bop.gov

8. ADDRESS OFFER TO

9. FOR

INFORMATION CALL:

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

SOLICITATION

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

The selected contractor will be responsible for removing approx. 5,725 sf of asbestos containing floor tile and adhesive from second floor of building 62.

PLEASE COMPLETE THE FOLLOWING ITEMS:

UNIQUE ENTITY IDENTIFIER (FORMERLY DUNS): ________________________

TAX IDENTIFICATION NUMBER: ___________________________

CAGE CODE: ____________________

CONTRACTOR EMAIL:_______________________________________________

calendar days and complete it within calendar days after receiving11. The Contractor shall begin performance within 30 14 award, X notice to proceed. This performance period is X mandatory negotiable. (See 52.211-10.)

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS? (If "YES," indicate within how many calendar days after award in Item 12b).

YES X NO

12b. CALENDAR DAYS

Sealed offers in original and copies to perform the work required are due at the place specified in item 8 by (hour) local time (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

02:00US/Centrala.

07/12/2024

b. An offer guarantee X is, is not required.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.c.

30d. Offers providing less than calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 12/2022)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d)

X

AWARD METHODOLOGY: This acquisition will be procured in accordance with FAR Part 12 – Acquisition of Commercial Items and Part 13 – Simplified Acquisition Procedures. The Government intends to evaluation quotes and award a contract to the lowest price, technically acceptable contractor, in accordance with FAR 52.212-1(g). The Government reserves the right to require the quoter to submit additional information as necessary to support a pre-award determination of responsibility.

bop12363 Highlight bop12363 Highlight bop12363 Highlight

15B40824Q00000001 Page 2 of 44

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

CODE FACILITY CODE

The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ___________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

17.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM

10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE

UNITED STATES CODE AT

26. ADMINISTERED BY 15B408

Federal Bureau of Prisons USP Leavenworth

1300 METROPOLITAN AVENUE

Leavenworth, KS 66048

Federal Bureau of Prisons USP Leavenworth

1300 METROPOLITAN AVENUE

Leavenworth, KS 66048

27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return __________ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

X 29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a.NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

Charles Dailey, FAO Contract Specialist

31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA

BY 06/20/2024

31c. DATE

STANDARD FORM 1442 (REV. 12/2022) BACK

15B40824Q00000001 Page 3 of 44

Table of Contents

Section Description Page Number

1 Solicitation, Offer and Award 2 Commodity or Services Schedule 3 Special Contract Requirements

FAO-0003 Required Insurance FAO-0004 Pre-Construction Conference FAO-0005 Submittals FAO-0006 Contractor Use of Premises FAO-0008 Request for Final Inspection FAO-0007 Payment Services FAO-0010 Assignment of Contract Administration Office and Functions FAO-0011 Schedule of Values FAO-0012 Progress Meetings FAO-0014 Contract Closeout Procedures (for construction contracts $150,000 or less) FAO-0015 Changes FAO-0016 Equitable Adjustments: Waiver and Release of Claims FAO-0001 Bonds FAO-0002 Magnitude FAO-0009(a) Construction Contract Security

4 Contract Clauses 52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984) 52.211-13 Time Extensions (Sept 2000) 52.242-14 Suspension of Work (Apr 1984) 52.212-4 Contract Terms and Conditions-Commercial Products and Commercial Services (Dec 2022) 52.202-1 Definitions (Jun 2020) 52.203-12 Limitation On Payments to Influence Certain Federal Transactions (Jun 2020) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (Jun 2020) 52.204-13 System for Award Management Maintenance (Oct 2018) 52.236-5 Material and Workmanship (Apr 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Apr 1984) 52.236-12 Cleaning Up (Apr 1984) 52.236-7 Permits and Responsibilities (Nov 1991) 52.236-10 Operations and Storage Areas (Apr 1984) 52.233-4 Applicable Law for Breach of Contract Claim (Oct 2004) 52.233-3 Protest after Award (Aug 1996) 52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013) 52.232-23 Assignment of Claims (May 2014) 52.232-5 Payments under Fixed-Price Construction Contracts (May 2014) 52.228-15 Performance and Payment Bonds-Construction (Jun 2020) 52.228-14 Irrevocable Letter of Credit (Nov 2014) 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment (Nov 2021) 52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Nov 2021) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015) 52.219-14 Limitations on Subcontracting (Oct 2022) 52.222-3 Convict Labor (June 2003) 52.222-4 Contract Work Hours and Safety Standards--Overtime Compensation (May 2018) 52.222-11 Subcontracts (Labor Standards) (May 2014) 52.222-12 Contract Termination - Debarment (May 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (May 2014) 52.222-14 Disputes Concerning Labor Standards (Feb 1988)

15B40824Q00000001 Page 4 of 44

52.222-15 Certification of Eligibility (May 2014) 52.222-6 Construction Wage Rate Requirements (Aug 2018) 52.222-7 Withholding of Funds (May 2014) 52.222-8 Payrolls and Basic Records (Jul 2021) 52.222-9 Apprentices and Trainees (July 2005) 52.222-10 Compliance with Copeland Act Requirements (Feb 1988) 52.222-26 Equal Opportunity (Sept 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (Apr 2015) 52.222-50 Combating Trafficking in Persons (Nov 2021) 52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026 (Jan 2022) 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022) 52.223-5 Pollution Prevention and Right-to-Know Information (May 2011) 52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts (Aug 2018) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (Jun 2020) 52.225-13 Restrictions on Certain Foreign Purchases (Feb 2021) 52.243-5 Changes and Changed Conditions (Apr 1984) 52.203-7 Anti-Kickback Procedures (Jun 2020) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) 52.204-9 Personal Identity Verification of Contractor Personnel (Jan 2011) 52.204-18 Commercial and Government Entity Code Maintenance (Aug 2020) 52.204-19 Incorporation by Reference of Representations and Certifications (Dec 2014) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (Nov 2021) 52.222-1 Notice to the Government of Labor Disputes (Feb 1997) 52.222-21 Prohibition of Segregated Facilities (Apr 2015) 52.222-37 Employment Reports on Veterans (Jun 2020) 52.222-54 Employment Eligibility Verification (May 2022) 52.223-6 Drug-Free Workplace (May 2001) 52.228-11 Individual Surety-Pledge of Assets (Feb 2021) 52.228-12 Prospective Subcontractor Requests for Bonds (Dec 2022) 52.228-2 Additional Bond Security (Oct 1997) 52.229-3 Federal, State and Local Taxes (Feb 2013) 52.232-17 Interest (May 2014) 52.232-27 Prompt Payment for Construction Contracts (Jan 2017) 52.232-33 Payment by Electronic Funds Transfer-System for Award Management (Oct 2018) 52.233-1 Alt I Disputes (May 2014) - Alternate I (Dec 1991) 52.236-2 Differing Site Conditions (Apr 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (Apr 1984) 52.236-6 Superintendence by the Contractor (Apr 1984) 52.236-8 Other Contracts (Apr 1984) 52.236-11 Use and Possession Prior to Completion (Apr 1984) 52.236-13 Alt I Accident Prevention (Nov 1991) - Alternate I (Nov 1991) 52.236-14 Availability and Use of Utility Services (Apr 1984) 52.236-21 Specifications and Drawings for Construction (Feb 1997) 52.236-26 Preconstruction Conference (Feb 1995) 52.244-6 Subcontracts for Commercial Products and Commercial Services (Mar 2023) 52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short Form) (Apr 1984) 2852.223-70 Unsafe Conditions Due to the Presence of Hazardous Material (NOV 2020) 52.24-403-70 Notice of Contractor Personnel Security Requirements (OCT 2005) DOJ-02 Contractor Privacy Requirements (JAN 2022) DOJ-08 Continuing Contract Performance During a Pandemic Influenza or other National Emergency (OCT 2007) 52.211-12 Liquidated Damages-Construction (Sept 2000) BOP 2852.201-71 Contracting Officer's Representative (COR) (June 2012)

15B40824Q00000001 Page 5 of 44

52.225-9 Buy American-Construction Materials (Oct 2022) 52.222-35 Equal Opportunity for Veterans (Jun 2020) 52.222-36 Equal Opportunity for Workers with Disabilities (Jun 2020)

5 Attachments 6 Solicitation Provisions

52.204-7 System for Award Management (Oct 2018) 52.214-19 Contract Award-Sealed Bidding-Construction (Aug 1996) 52.228-1 Bid Guarantee (Sept 1996) 52.228-17 Individual Surety-Pledge of Assets (Bid Guarantee) (Feb 2021) 52.214-7 Late Submissions, Modifications, and Withdrawals of Bids (Nov 1999) 52.214-6 Explanation to Prospective Bidders (Apr 1984) 52.214-5 Submission of Bids (Dec 2016) 52.214-4 False Statements in Bids (Apr 1984) 52.214-34 Submission of Offers in the English Language (Apr 1991) 52.214-3 Amendments to Invitations for Bids (Dec 2016) 52.214-18 Preparation of Bids-Construction (Apr 1984) 52.204-16 Commercial and Government Entity Code Reporting (Aug 2020) 52.204-22 Alternative Line Item Proposal (Jan 2017) 52.225-10 Notice of Buy American Requirement-Construction Materials (May 2014) 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction (Feb 1999) 52.216-1 Type of Contract (Apr 1984) 52.222-5 Construction Wage Rate Requirements - Secondary Site of the Work (May 2014)

7 Representations and Certifications 52.204-8 Annual Representations and Certifications (Mar 2023) 52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment (Nov 2021)

15B40824Q00000001 Page 6 of 44

Section 2 - Commodity or Services Schedule

Replace Water Softener Project

Firm Fixed Price

SCHEDULE OF SUPPLIES/SERVICES

CONTINUATION SHEET

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 The selected contractor will be responsible for removing approx.

5,725 sf of asbestos containing floor tile and adhesive from second floor of building 62.

PSC: 5680

1 EA $________ $_________________

The successful contractor shall be responsible for all applicable federal, state, and local taxes. No tax exemption certification will be issued by the Federal Bureau of Prisons. THE TOTAL PURCHASE PRICE SHALL BE WRITTEN IN BLOCK 17 OF SF 1442.

bop12363 Highlight

15B40824Q00000001 Page 7 of 44

Section 3 - Special Contract Requirements

Clauses By Full Text

FAO-0003 Required Insurance

See FAR 52.228-5, Insurance - Work on a Government Installation.

The Contractor shall, at its own expense, provide and maintain during the entire performance period of this contract, at least the kinds and minimum amounts of insurance required in the Schedule or elsewhere in the contract.

TYPE AMOUNT

(1) WORKERS COMPENSATION & EMPLOYER'S LIABILITY $100,000

The required Workmen's Compensation Insurance shall extend to cover employee's liability for accidental bodily injury or death and for occupational disease with a minimum liability of $100,000.

(2) COMPREHENSIVE GENERAL LIABILITY with a minimum limit of:

PER ACCIDENT OR

OCCURRENCE FOR BODILY INJURY $500,000

This insurance shall include contractor's protective and contractual liability.

(3) COMPREHENSIVE AUTOMOBILE LIABILITY with the following minimum limits:

PER PERSON $200,000

PER OCCURRENCE FOR BODILY INJURY $500,000

PER OCCURRENCE FOR PROPERTY DAMAGE $ 20,000

FAO-0004 Pre-Construction Conference

(a) Prior to the start of construction, Contracting Officers shall call a conference with the contractor, subcontractor(s), Warden, Controller/Business Administrator, Safety Manager, Facilities Administrator, Project Representative, A&E firm, Captain and other interested personnel to discuss the statutory labor standards, prevailing wage requirements, submission of the contractor's payrolls, subcontractor's responsibilities, institution work schedules, local policies, contraband, parking, storage of vehicles and equipment, etc.

Minutes of the conference shall be recorded, listing the names and titles of all attendees, and the subject matter of all items covered. The minutes shall be signed by the contractor and the Contracting Officer, and a signed copy placed in the contract file.

(b) The Contractor shall familiarize himself/herself with all procedures involved in normal institution routines. Any requirements which may constitute a problem or result in conflict, will be brought to the attention of the Contracting Officer or his representative for determination.

FAO-0005 Submittals

15B40824Q00000001 Page 8 of 44

Before commencement of work or as otherwise established by the Contracting Officer, all materials and articles requiring approval, as contemplated by the Materials and Workmanship clause, shall be submitted by the contractor.

The submittal process is in place to allow the Government the opportunity to determine whether materials or procedures used by the contractor are in accordance with contract requirements. It is ultimately the Contractor's responsibility via the quality control process to ensure submittal items installed under the contract and work performed on site are in accordance with industry standards and general practices.

(a) The types of submittal requirements specified in this contract may include, but is not limited to; shop drawings, product data, samples, certificates of conformance or compliance, certified test or inspection reports, equipment, materials, and miscellaneous work related submittals for construction. Individual submittal requirements are generally specified in applicable sections for each unit of work in the specifications and/or as a whole in one section in the statement of work.

(b) The Bureau of Prisons (BOP) Contracting Officer’s Representative (COR) shall act for the Contracting Officer in the review and acceptance of all submittals. The Contractor shall submit submittals as required by the contract/ specifications to the COR for transmittal to the Contracting Officer. Fabrication of any work or purchase or use of any submittals (such as materials for which samples are required or equipment, etc.) shall not take place until written acceptance is given by the COR, except at the Contractor's own risk.

(c) The Contractor shall submit all shop drawings and submittals sufficiently in advance (unless otherwise specified in the specifications) of the construction requirements to allow ample time for checking, re-submitting, and re-checking.

(d) Failure of any materials to pass their specified tests shall be sufficient cause for refusal to consider, under this contract, any further samples of the same brand or make of that material. The Government reserves the right to disapprove any material or equipment which has previously proven unsatisfactory in service.

(e) The Contracting Officer’s or designee’s approval or acceptance of submittals is not to be construed as a complete check. Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor is responsible for the satisfactory construction of all work. The Contractor is responsible for delivering a final product/system that is operational as intended by the contract requirements, regardless of any Government approvals or acceptance of submittals. The Government assumes no liability during the submittal approval/acceptance process. It is the sole responsibility of the Contractor to deliver a properly functioning product or system.

FAO-0006 Contractor Use of Premises

Work Hours The project schedule is based on a normal forty (40) hour work week, eight (8) hours per day, Monday through Friday, excluding Federal holidays. The Contracting Officer’s Representative (COR) shall establish the work hour time frames for the duration of the project, subject to the approval of the Contracting Officer. Work hours and work days may be altered only with a 48 hour advance approval of the Contracting Officer.

NOTE: Access to the site will be available during normal working hours except during emergencies. It shall be the responsibility of the Contractor to familiarize himself, his employees, and his subcontractors of the working hours and conditions in the correctional facility, as working hours may not constitute a full eight hour day. The Government assumes no responsibility to the Contractor, nor to any of his subcontractors, for shorter hours due to institutional emergencies or entry and/or exit of workers necessitated by normal institution routines. The procedures and institutional entrance/ exit routines applicable to this project will be explained at both the pre-bid conference/site visit and the pre-construction meeting.

Contraband The Contractor shall inform his employees that intoxicating beverages, drugs, weapons, etc., will not be allowed on the site. Introduction of contraband shall be subject to the penalties prescribed by Title 18 USC-1791.

Explosives The use of explosives is absolutely forbidden without written authorization from the Contracting Officer.

15B40824Q00000001 Page 9 of 44

Parking and Temporary Office Parking will be available at the site to the extent it does not interfere with construction activities. Otherwise, parking shall be provided for by the Contractor, at his expense, off the site for workmen employed on the project. Any temporary field office used by the Contractor shall be located in an area approved by the COR.

Safety and Accident Prevention In performing work under this contract the contractor shall:

(a) Conform to the specific safety requirements established by this contract;

(b) Comply with the safety rules of the Government institution that concern related activities not directly addressed in this contract;

(c) Take all reasonable steps and precautions to prevent accidents and preserve the life and health of contractor and Government personnel performing or in any way coming in contact with the performance of this contract; and

(d) Take such additional immediate precautions as the Contracting Officer and/or COR may reasonably require for safety and accident prevention purposes.

FAO-0008 Request for Final Inspection

The Contractor shall give the Contracting Officer’s Representative (COR) a minimum of ten (3) working days advanced written notice of the date on which the work will be fully completed and ready for the Government’s final inspection.

FAO-0007 Payment Services

(a) Original application for payment shall be prepared on AIA (American Institute of Architects) Form G-702 "Application and Certificate for Payment" and submitted to the Contracting Officer. The contractor may use another form;

however, it shall contain similar information as the AIA Form G-702. The Contracting Officer will approve the amount of payment by signing and forwarding the application and certificate as follows: Original to Accounting; Copy for Contract Award File.

(b) All small business contractors are required to self-certify on all invoices their small business status.

FAO-0010 Assignment of Contract Administration Office and Functions

Pursuant to FAR 42.201 and 42.202, the assigned Contract Administration Office is listed in Block 26 of the Standard Form 1442 Back. This assignment carries with it the authority to perform all of the contract administration functions listed in FAR 42.302(a) and 42.302(b) to the extent that those functions apply to the contract.

FAO-0011 Schedule of Values

The Contractor shall prepare a Schedule of Values (SOV) for the project and submit to the Contracting Officer for approval prior to submitting the first application for payment. The SOV shall be correlated with the construction schedule.

The SOV shall be formatted per the Construction Specification Institute Master Format structure. The Contractor may propose an alternate organizational format to the Contracting Officer for approval.

(a) The SOV shall include:

(1) Project name, location, and contract number;

(2) Contractor’s name and address;

(3) Date of submittal.

(b) The SOV shall be arranged in a tabular form with separate columns to indicate the following for each item listed:

(1) Description of Work or Material;

(2) Related specification section, if applicable;

(3) Name of subcontractor, if applicable;

15B40824Q00000001 Page 10 of 44

(4) Name of manufacturer or fabricator, if applicable;

(5) Name of supplier, if applicable;

(6) Change orders (modifications) that have affected value, if applicable;

(7) Dollar value;

(8) Percentage of Contract sum rounded to the nearest percent, adjusted to total 100 percent.

(c) The SOV shall breakdown the contract sum in sufficient detail to facilitate continued evaluation of applications for payment and progress reports. The contractor should separate principal subcontract amounts down into several line items.

(d) SOV amounts shall be rounded to the nearest whole dollar. The total of all SOV amounts shall equal the total contract amount.

(e) The contractor shall progress the percentage of completion, with the concurrence of the Contracting Officer’s Representative, for each value in conjunction with the preparation of each monthly application for payment. The progressed value percentages shall directly correlate to the calculated total amount due for each monthly progress payment.

(f) The SOV shall remain fixed for the duration of contract performance. Any revisions to the SOV must be requested in writing, with justification, for approval by the Contracting Officer.

FAO-0012 Progress Meetings

The Administrative Contracting Officer (ACO) shall conduct progress meetings at the project site as needed as determined by the ACO.

(a) At a minimum, the attendees shall include but is not limited to:

(1) FBOP: Administrative Contracting Officer, Contracting Officer’s Representative (COR), Facility Administrator/Manager, Architect/Engineer (if applicable), Other Personnel (Executive Staff, Captain, Safety Manager, etc.).

(2) Contractor: Project Manager, Superintendent, and technical support disciplines as appropriate (Subcontractors, Manufacturers, Suppliers, etc.).

(b) The meeting should include, but is not limited to issues such as:

Administrative Contracting Officer:

(1) Old business from previous progress meeting(s);

(2) Status of modifications, certified payrolls, submittals, requests for information (RFI);

(3) Review of payments made to date and review/approve current payment request;

(4) Status of modification proposal requests;

(5) Discuss new business.

COR:

(1) Status of escort coverage;

(2) Review gate or sallyport entrance/exit issues;

(3) Discuss other delays contractor may be experiencing;

15B40824Q00000001 Page 11 of 44

(4) Discuss performance/quality issues.

Contractor:

(1) Review/discuss updated progress schedule;

(2) Provide 30 day outlook;

(3) Discuss other issues affecting performance.

FAO-0014 Contract Closeout Procedures (for construction contracts $150,000 or less)

Contract Closeout must be completed upon receipt of property and final payment.

Prior to payment of final invoice:

The Contractor shall submit the following documentation:

(1) Guarantees and warranties;

(2) All operation/maintenance manuals;

(3) Consent of Surety to Final Payment (AIA Document G707), if the contractor furnished a bond;

(4) Release of Claims (GSA Form 1142);

(5) Evidence of no pending labor disputes;

(6) As-built drawings/shop drawings, (if applicable);

(7) Contractor’s final invoice.

AIA forms can be obtained from The American Institute of Architects at www.aiabookstore.com.

GSA forms can be obtained from the General Services Administration at www.gsa.gov (click on the “Forms Library” link).

FAO-0015 Changes

(a) Changes will be in accordance with the Changes clause 52.243-4 or Changes and Changed Conditions clause 52.243-5 whichever applies to this contract.

(b) When changes are made in the work that requires an equitable adjustment to the contract, the Contractor shall submit to the Contracting Officer, through the Contracting Officer’s Representative (COR), a written proposal for adjustment of the amount of increase or decrease. With the proposal, the Contractor shall submit an itemized breakdown in at least the following detail:

(1) Material quantities and unit cost

(2) Labor costs by material item

(3) Construction equipment cost

(4) Workmen's compensation and public liability insurance

(5) Overhead

(6) Profit or commission

(7) Employment taxes (FICA and FUTA)

(c) The maximum allowable overhead, profit and commission percentages are contained below. The percentages for overhead, profit and commission shall be negotiated and may vary according to the nature, extent and complexity of the work involved, but in no case shall exceed the following:

15B40824Q00000001 Page 12 of 44

(1) To the Contractor, on work performed by other than his own forces. The commission is 10% in the first $20,000, 7 1/2% on the next $30,000, 5% on the balance over $50,000.

(2) To the Contractor, and/or the Subcontractors for that portion of the work performed with their respective forces. The commission is 10% overhead and 10% profit on the first $20,000, 7 1/2% overhead and 7 1/2% profit on the next $30,000, and 5% overhead and 5% profit on the balance over $50,000.

Not more than three (3) percentages, not to exceed the maximum percentage amounts shown above, will be allowed regardless of the number of Subcontractors (i.e., the mark up on work subcontracted by the Subcontractor will be limited to the overhead percentage and one profit percentage in addition to the prime Contractor's commission percentage). On proposals covering both increases and decreases in the amount of the contract, overhead, profit and commission will be allowed on the net increase only.

(d) When certified cost or pricing data are required under FAR 15.403-4 for proposals over $2,000,000, the cost or pricing data shall be submitted in accordance with FAR 15.408, Table 15-2. No itemized breakdown will be required for proposals amounting to less than $1,000.

(e) When the necessity to proceed with a change does not allow sufficient time to negotiate a modification or because of failure to reach an agreement, the Contracting Officer may issue a change order instructing the contractor to proceed on the basis of a tentative price based on the best estimate available at the time, with the firm price to be determined later.

Furthermore, when the change order is issued, the contractor shall submit a proposal for cost of changes in work within 30 calendar days.

(f) The Contracting Officer will consider issuing a settlement by determination to the contract, if the contractor's proposal required by paragraphs (a) and (b) of this clause is not received within 30 calendar days, or if agreement has not been reached.

(g) Where a change involves credit items only, a proper measure of the amount of downward adjustment in the contract price is the reasonable cost to the contractor if he/she had performed the deleted work. A reasonable allowance for overhead and profit are properly includable as part of the downward adjustment for a deductive change. The amount of such allowance is subject to negotiation.

(h) Overhead and contractor's fee percentages shall be considered to include insurance other than mentioned herein, field and office supervisors and assistants, security police, use of small tools, incidental job burdens, and general home office expenses and no separate allowance will be made therefor. Assistants to office supervisors include all clerical, stenographic and general office help. Incidental job burdens include, but are not necessarily limited to, office equipment and supplies, temporary toilets, telephone and conformance to OSHA requirements. Items such as, but not necessarily limited to, review and coordination, estimating and expediting relative to contract changes are associated with field and office supervision and are considered to be included in the contractor's overhead and/or fee percentage.

(i) The Contractor shall submit with his proposal a request for time extension, if applicable.

(j) The COR shall review the proposal and check estimates in detail, utilizing unit prices where specified or agreed upon. If they are in agreement, the COR shall forward the proposal to the Contracting Officer. The Contracting Officer will forward copies to the Architect-Engineer (if applicable) and the Regional Project Manager for their review and recommendations. After their review, the Architect-Engineer and Project Manager will forward their comments to the Contracting Officer.

(k) If the Contracting Officer determines that an equitable adjustment is to be made, the contract shall be modified in writing utilizing the prescribed Standard Form 30 (Amendment of Solicitation/Modification of Contract)(SF-30). After the SF-30 has been signed by the Contractor and executed by the Contracting Officer, distribution shall be made as follows:

(1) Original: Contract file

(2) Copy to: Contractor

Regional Project Manager Contracting Officer’s Representative (COR) Architect-Engineer Firm (if applicable) Accounting Supervisor Contracting Officer

15B40824Q00000001 Page 13 of 44

FAO-0016 Equitable Adjustments: Waiver and Release of Claims

(a) When the Contractor, after receipt of notification of a change made pursuant to the clause of this contract entitled "Changes" or after affirmation of constructive change thereunder, submits any claim for equitable adjustment under this clause, such claim shall include all types of adjustments in the total amounts to which that clause entitles the Contractor, including but not limited to adjustments arising out of delays or disruptions or both caused by such change. Except as the parties may otherwise expressly agree, the Contractor shall be deemed to have waived (i) any adjustments to which it otherwise might be entitled under the aforesaid clause where such claim fails to request such adjustment, and (ii) any increase in the amount of equitable adjustments additional to those requested in its claim.

(b) Further, the Contractor agrees that, if required by the Contracting Officer, it will execute a release, in form and substance satisfactory to the Contracting Officer, as part of the supplemental agreement setting forth the aforesaid adjustment, and that such release shall discharge the Government, its officers, agents, and employees, from any further claims, including but not limited, to further claims arising out of delays or disruptions or both caused by the aforesaid change.

FAO-0001 Bonds

(a) Bid Guarantee. Each bidder shall submit with his bid a Bid Bond (Standard Form 24) with good and sufficient surety or sureties acceptable to the Government, or other security as provided in provision 52.228-1, in the form of twenty percent (20) of the bid price or not to exceed $3,000,000. The bid bond penalty may be expressed in terms of a percentage of the bid price or may be expressed in dollars and cents. A bid bond is not required for bids of $150,000 or less. (FAR 28.102-1)

(b) Performance and Payment Bonds. Within 10 days after award the contractor shall execute and submit to the Contracting Officer two bonds, each with good and sufficient surety or sureties acceptable to the Government, as follows;

a Performance Bond (Standard Form 25) and a Payment Bond (Standard Form 25A). The penal sums of such bonds will be as follows: (Not required for contracts of $150,000 or less)

(1) Performance Bond: The penal sum of performance bonds at the time of contract award shall be 100 percent of the original contract price.

(2) Payment Bond: The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.

(c) For construction contracts greater than $30,000 but not greater than $150,000, the Contracting Officer shall select two or more of the following payment protections, giving particular consideration to inclusion of an irrevocable letter of credit as one of the selected alternatives (FAR 28.102-1(b)(1)):

(1) A Payment Bond;

(2) An irrevocable letter of credit (ILC);

(3) A tripartite escrow agreement;

(4) A Certificate of Deposit; or

15B40824Q00000001 Page 14 of 44

(5) A deposit of the types of security listed in 28.204-1 and 28.204-2.

(d) Individual Sureties.

(1) Bidders may elect to furnish individual surety bonds. If individual surety bonds are furnished for bid guarantees, payment or performance bonds, the individual sureties must submit their bonds proof of ownership and value of the assets which they claim in their net worth at time of bid opening. The Government's preferred method of proof is to have a statement of net worth prepared by a Certified Public Accountant (CPA) in accordance with Generally Accepted Accounting Principles (GAAP). Statements from a CPA that contain disclaimers are not acceptable. The statement of net worth on the Standard Form 28, Affidavit of Individual Surety, is insufficient and will not be accepted without additional proof of value and ownership.

(2) Bidders are cautioned that individual sureties must provide complete and detailed information in Block 9 of Standard Form 28 concerning other contracts on which they have provided bonds. This information shall include contract number, contract location, amount, and type of bond and telephone number of the involved contracting office. Failure to provide the proof and information required may result in rejection of the bid or termination of the contract for failure to provide adequate bonds.

(a) Bid Guarantee. Each bidder shall submit with his bid a Bid Bond (Standard Form 24) with good and sufficient surety or sureties acceptable to the Government, or other security as provided in provision 52.228-1, in the form of twenty percent (20) of the bid price or not to exceed $3,000,000. The bid bond penalty may be expressed in terms of a percentage of the bid price or may be expressed in dollars and cents. A bid bond is not required for bids of $150,000 or less. (FAR 28.102-1)

(b) Performance and Payment Bonds. Within 10 days after award the contractor shall execute and submit to the Contracting Officer two bonds, each with good and sufficient surety or sureties acceptable to the Government, as follows; a Performance Bond (Standard Form 25) and a Payment Bond (Standard Form 25A). The penal sums of such bonds will be as follows: (Not required for contracts of $150,000 or less)

(1) Performance Bond: The penal sum of performance bonds at the time of contract award shall be 100 percent of the original contract price.

(2) Payment Bond: The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.

(c) For construction contracts greater than $30,000 but not greater than $150,000, the Contracting Officer shall select two or more of the following payment protections, giving particular consideration to inclusion of an irrevocable letter of credit as one of the selected alternatives (FAR 28.102-1(b)(1)):

(1) A Payment Bond;

15B40824Q00000001 Page 15 of 44

(2) An irrevocable letter of credit (ILC);

(3) A tripartite escrow agreement;

(4) A Certificate of Deposit; or

(5) A deposit of the types of security listed in 28.204-1 and 28.204-2.

(d) Individual Sureties.

(1) Bidders may elect to furnish individual surety bonds. If individual surety bonds are furnished for bid guarantees, payment or performance bonds, the individual sureties must submit their bonds proof of ownership and value of the assets which they claim in their net worth at time of bid opening. The Government's preferred method of proof is to have a statement of net worth prepared by a Certified Public Accountant (CPA) in accordance with Generally Accepted Accounting Principles (GAAP).

Statements from a CPA that contain disclaimers are not acceptable. The statement of net worth on the Standard Form 28, Affidavit of Individual Surety, is insufficient and will not be accepted without additional proof of value and ownership.

(2) Bidders are cautioned that individual sureties must provide complete and detailed information in Block 9 of Standard Form 28 concerning other contracts on which they have provided bonds. This information shall include contract number, contract location, amount, and type of bond and telephone number of the involved contracting office. Failure to provide the proof and information required may result in rejection of the bid or termination of the contract for failure to provide adequate bonds.

FAO-0002 Magnitude

The magnitude of this project is between $30,000.00 and $40,000.00.

FAO-0009(a) Construction Contract Security

FAO-0009(a) Construction Contract Security (Program Statement 3732.01 BOP Identifications and Background Investigation)

In addition to the information contained in clause “DOJ-03 Personnel Security Requirements For Contractor Employees (Nov 2021); (Alt. I) -- Classified Information – Cleared Contractors”, the following additional security is required to be completed and submitted for all contract employees who will be working under the terms of the contract:

Criminal History Check – BP-A0660 (May 2018) CJIS Name Check Request Form BOP Contractor Pre-employment Questionnaire BOP Authority for Release of Information The contactor should be aware that the time required for contractor security clearances to be completed may vary. For the purposes of this solicitation, 21 calendar days [contracting officer to insert the number of days based on performance period memo] have been included in the performance period specified in FAR clause 52.211-10. The number of days listed above is contingent upon the contractor providing completed clearance packages for their employees within 10 calendar days of the Notice to Proceed. For any subsequently awarded subcontract, completed security clearance packages for subcontractor workers shall be submitted in conjunction with the completed SF-1413.

**A form package will be issued by the Administrative Contracting Officer or Contracting Officer's Representative (COR) at the institution upon contract award. Completed packages shall be submitted by the PRIME CONTRACTOR ONLY to obtain clearance for each prime and sub-contract employee. Security Clearance packages will NOT be accepted from sub-contractors. Upon clearance being obtained the contractor will be

15B40824Q00000001 Page 16 of 44 notified. Should a contract employee NOT be cleared to enter the facility for this project, the contractor will be notified immediately. The contractor will be responsible to submit another contract employee as soon as possible for clearance. Be advised, the Federal Bureau of Prisons cannot disclose why an individual does not pass the security clearance process, as it is a violation of law.**

15B40824Q00000001 Page 17 of 44

Section 4 - Contract Clauses

Clauses By Reference

52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.acquisition.gov

Clause Title Fill-ins (if applicable)

52.211-10 Commencement, Prosecution, and Completion of Work

(Apr 1984)

Calendar Days: "30"

No Later Than: "14 calendar days"

52.211-13 Time Extensions (Sept 2000)

52.242-14 Suspension of Work (Apr 1984)

52.212-4 Contract Terms and Conditions-Commercial Products and Commercial Services (Dec 2022)

52.202-1 Definitions (Jun 2020)

52.203-12 Limitation On Payments to Influence Certain Federal

Transactions (Jun 2020)

52.204-10 Reporting Executive Compensation and First-Tier

Subcontract Awards (Jun 2020)

52.204-13 System for Award Management Maintenance (Oct 2018)

52.236-5 Material and Workmanship (Apr 1984)

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Apr 1984)

52.236-12 Cleaning Up (Apr 1984)

52.236-7 Permits and Responsibilities (Nov 1991)

52.236-10 Operations and Storage Areas (Apr 1984)

52.233-4 Applicable Law for Breach of Contract Claim (Oct 2004)

52.233-3 Protest after Award (Aug 1996)

52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013)

15B40824Q00000001 Page 18 of 44

Clause Title Fill-ins (if applicable)

52.232-23 Assignment of Claims (May 2014)

52.232-5 Payments under Fixed-Price Construction Contracts

(May 2014)

52.228-15 Performance and Payment Bonds-Construction (Jun

2020)

52.228-14 Irrevocable Letter of Credit (Nov 2014)

52.204-25 Prohibition on Contracting for Certain

Telecommunications and Video Surveillance Services or

Equipment (Nov 2021)

52.209-6 Protecting the Government's Interest When

Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Nov 2021)

52.209-10 Prohibition on Contracting with Inverted Domestic

Corporations (Nov 2015)

52.219-14 Limitations on Subcontracting (Oct 2022) (f)(1) End of Base Term: "X"

52.222-3 Convict Labor (June 2003)

52.222-4 Contract Work Hours and Safety Standards--Overtime

Compensation (May 2018)

52.222-11 Subcontracts (Labor Standards) (May 2014)

52.222-12 Contract Termination - Debarment (May 2014)

52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (May 2014)

52.222-14 Disputes Concerning Labor Standards (Feb 1988)

52.222-15 Certification of Eligibility (May 2014)

52.222-6 Construction Wage Rate Requirements (Aug 2018)

52.222-7 Withholding of Funds (May 2014)

52.222-8 Payrolls and Basic Records (Jul 2021)

52.222-9 Apprentices and Trainees (July 2005)

52.222-10 Compliance with Copeland Act Requirements (Feb

1988)

15B40824Q00000001 Page 19 of 44

52.222-26 Equal Opportunity (Sept 2016)

52.222-27 Affirmative Action Compliance Requirements for

Construction (Apr 2015)

52.222-50 Combating Trafficking in Persons (Nov 2021)

52.222-55 Minimum Wages for Contractor Workers Under

Executive Order 14026 (Jan 2022)

52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan

2022)

52.223-5 Pollution Prevention and Right-to-Know Information

(May 2011)

52.223-17 Affirmative Procurement of EPA-designated Items in

Service and Construction Contracts (Aug 2018)

52.223-18 Encouraging Contractor Policies to Ban Text Messaging

While Driving (Jun 2020)

52.225-13 Restrictions on Certain Foreign Purchases (Feb 2021)

52.243-5 Changes and Changed Conditions (Apr 1984)

52.203-7 Anti-Kickback Procedures (Jun 2020)

52.203-19 Prohibition on Requiring Certain Internal Confidentiality

Agreements or Statements (Jan 2017)

52.204-9 Personal Identity Verification of Contractor Personnel

(Jan 2011)

52.204-18 Commercial and Government Entity Code Maintenance

(Aug 2020)

52.204-19 Incorporation by Reference of Representations and

Certifications (Dec 2014)

52.204-23 Prohibition on Contracting for Hardware, Software, and

Services Developed or Provided by Kaspersky Lab and

Other Covered Entities (Nov 2021)

52.222-1 Notice to the Government of Labor Disputes (Feb 1997)

52.222-21 Prohibition of Segregated Facilities (Apr 2015)

52.222-37 Employment Reports on Veterans (Jun 2020)

15B40824Q00000001 Page 20 of 44

52.222-54 Employment Eligibility Verification (May 2022)

52.223-6 Drug-Free Workplace (May 2001)

52.228-11 Individual Surety-Pledge of Assets (Feb 2021)

52.228-12 Prospective Subcontractor Requests for Bonds (Dec

2022)

52.228-2 Additional Bond Security (Oct 1997)

52.229-3 Federal, State and Local Taxes (Feb 2013)

52.232-17 Interest (May 2014)

52.232-27 Prompt Payment for Construction Contracts (Jan 2017)

52.232-33 Payment by Electronic Funds Transfer-System for

Award Management (Oct 2018)

52.233-1 Alt I Disputes (May 2014) - Alternate I (Dec 1991)

52.236-2 Differing Site Conditions (Apr 1984)

52.236-3 Site Investigation and Conditions Affecting the Work

(Apr 1984)

52.236-6 Superintendence by the Contractor (Apr 1984)

52.236-8 Other Contracts (Apr 1984)

52.236-11 Use and Possession Prior to Completion (Apr 1984)

52.236-13 Alt I Accident Prevention (Nov 1991) - Alternate I (Nov 1991)

52.236-14 Availability and Use of Utility Services (Apr 1984)

52.236-21 Specifications and Drawings for Construction (Feb 1997)

52.236-26 Preconstruction Conference (Feb 1995)

52.244-6 Subcontracts for Commercial Products and Commercial

Services (Mar 2023)

52.249-1 Termination for Convenience of the Government (Fixed-

Price) (Short Form) (Apr 1984)

Clauses By Full Text

2852.223-70 Unsafe Conditions Due to the Presence of Hazardous Material (NOV 2020)

15B40824Q00000001 Page 21 of 44

(a) “Unsafe condition” as used in this clause means the actual or potential exposure of Contractor or Government employees to a hazardous material.

(b) “Hazardous Material” as used in this clause includes any material defined as hazardous under the latest version of Federal Standard No. 313 (including revisions adopted during the term of the contract), any other potentially hazardous material requiring safety controls, or any other material or working condition designated as hazardous by the Contracting Officer's Representative (COR).

(c) The Occupational Safety and Health Administration (OSHA) is responsible for issuing and administering regulations that require Contractors to apprise its employees of all hazards to which they may be exposed in the course of their employment; proper conditions and precautions for safe use and exposure; and related symptoms and emergency treatment in the event of exposure.

(d) Prior to commencement of work, Contractors are required to inspect for and report to the Contracting Officer the presence of, or suspected presence of, any unsafe condition including asbestos or other hazardous materials or working conditions in areas in which they will be working.

(e) If during the performance of the work under this contract, the Contractor or any of its employees, or subcontractor employees, discovers the existence of an unsafe condition, the Contractor shall immediately notify the Contracting Officer, or designee (with written notice provided not later than three (3) working days thereafter), of the existence of an unsafe condition. Such notice shall include the Contractor's recommendations for the protection and the safety of Government, Contractor and subcontractor personnel and property that may be exposed to the unsafe condition.

(f) When the Government receives notice of an unsafe…