Q A_-_PSC_IDIQ_Part_II_missed.pdf
PDF 12 KB Posted
- Attached to
- Program Support Center Task Order Contracts Federal contract opportunity
- Solicitation number
- 14-233-SOL-00009
About this file
The following are two questions that were submitted before the June 27 deadline but failed to be incorporated into the Q A Part II document. The Government is no longer accepting questions on this solicitation.
View the file
Other files for this federal contract opportunity
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers Part II – Missed Questions
14-233-SOL-00009
July 18, 2014
1. Question: Section L.2 Proposal, (A) Business Proposal, (2) Other Information states that “The business proposal shall consist of the following… f. Organizational Conflict of Interest Statement detailed in Section L.8 should be included and, if necessary, the mitigation plan.” Whereas, Section L.8 Organizational Conflict of Interest Disclosure/Mitigation states that, “…If an actual or potential OCI is identified, the offeror shall submit a mitigation plan as part of its technical proposal.” Can you please confirm that the OCI Disclosure/Mitigation should be included as part of the business only?
Answer: The OCI Disclosure/Mitigation plan should be included as part of the business proposal.
2. Question: It is understood that a separate Small Disadvantaged Participation Plan is required. L.2.A2 paragraph G(3), states that the minimum required goal for SDBs in the Participation Plan is 0.5% of the Total Contract Value. Would the government reconsider this requirement in light of current revisions to this section in Amendment 2?
Answer: The Government does not plan to make any changes to the requirement.