This is a Statement of Work (SOW) for the assembly of Automated Surface Observation System (ASOS) AC Power Distribution Assemblies, part number 62828-40492-10, to be delivered to the National Weather Service.
The contractor must provide all materials, testing, equipment, facilities, and labor to assemble new units (no refurbished parts permitted) in accordance with Government-furnished drawings and specifications. The contractor is responsible for identifying unavailable parts and proposing substitutes within 10 days of purchase order award, with Government approval required within 5 days. A First Article Unit must be inspected, mechanically tested, and electrically tested before Government submission; the Government will complete acceptance testing within 30 business days at the National Reconditioning Center in Grandview, MO. Following Government approval of the First Article Unit, a written Notice to Proceed will authorize production of all units, which must be delivered within 30 days of that notice. All production units require contractor inspection and testing with a Certification of Compliance, and the Government reserves the right to test 100% of units or a random sample. Each unit includes a one-year workmanship warranty beginning upon Government acceptance, with the contractor responsible for all repairs or replacements due to workmanship defects at no additional cost, including shipping, parts, and labor; reworked units must be resubmitted within 30 days of receipt. Packaging must follow Government-specified marking and bar-coding instructions with barcoding supplies provided by the Government. First Article Units are delivered to the National Reconditioning Center at 14200 Merritt Road, Grandview, MO 64030, while production units are delivered to the National Logistics Support Center at the same address, with each package including inspection reports and Factory Acceptance Test documents.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1305M226Q0132 (3).pdf | ||
| 1305M226Q0132 Extended POP.pdf | ||
| 1305M226Q0132.pdf | ||
| Shipping Instructions.pdf | ||
| Drawing Package.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ASOS AC JUNCTION BOX
1 Scope of Work This Statement of Work (SOW) describes the actions and processes required to assemble the Automated Surface Observation System (ASOS) AC Power Distribution Assemblies, part number 62828-40492-10. All parts and components shall be new. No refurbished parts may be used. The contractor shall provide all material, testing, equipment, facilities and labor required to produce the units described herein. These actions include the building-to-print and testing using Government furnished drawings, packing, and shipping to the Government specified locations.
2 Government Furnished Data The Government shall provide the drawing package containing all drawings and parts lists required to build the assemblies. The following Adobe .pdf files are included:
62828-40492.pdf - Production drawing including wiring diagram.
PL62828-40492-10.pdf, 62828-90450.pdf, 62828-90452.pdf - Parts list for 62828-40492-10 62828-93022.pdf, 62828-93023.pdf – Enclosure and Back Plate PL-62828-43004-10.pdf, PL-62828-93023-01 – Parts List for enclosure and back plate
All proposed parts within the drawing package are a brand name or equal requirement.
3 Government Furnished Equipment (GFE) No Government Furnished Equipment shall be provided under this purchase order.
4 First Article The contractor shall identify any parts that are no longer available, along with a proposed substitute part, to the Government within 10 days of purchase order award. The Government shall evaluate the proposed part for acceptability, and if found acceptable, shall notify the contractor in writing within 5 days of receipt of notice. The contractor shall NOT be responsible for update to any Government drawings.
The contractor shall inspect, mechanical test, and electrical test one First Article Unit. The First Article Unit shall be submitted to the Government for evaluation and approval. No production units shall be made until receipt of Government approval of the First Article Unit. The Government shall complete acceptance testing of First Article Units within 30 business days of receipt at the National Reconditioning Center in Grandview, MO.
5 Production Upon successful Government acceptance of the First Article Units, the Government shall issue a written Notice to Proceed for the production quantities in accordance with the purchase order.
All production units shall be delivered within 30 days of the Notice To Proceed.
6 Inspection and Testing The contractor shall inspect and test all production units to verify compliance with the Government furnished drawings and shall provide a Certification of Compliance with each production unit. The Government may test 100% of the production units or test a random sample.
7 Warranty
The contractor shall provide a one-year workmanship warranty for each unit produced. Warranty shall begin upon the Government acceptance of each unit. The contractor shall repair or replace all items that fail due to workmanship during the warranty period at no additional cost to the Government. The warranty shall include shipping, parts, and labor to perform warranty repairs.
Returned units shall be reworked and re-submitted within 30 days of receipt at the contractor’s facility. The inspection shall include the packing and marking requirements in described in Section 8.
8 Packaging and Marking The contractor shall individually package each inspected and tested unit in a container suitable for stocking and reshipment. Each container shall include the inspection report and the Factory Acceptance Test document. Each individual package shall be marked, labeled, and bar coded according to the “Instructions to Commercial Vendors for Marking and Bar Coding Supplies for Shipment to the National Logistics Support Center” supplied with this purchase order. Barcoding supplies shall be provided by the Government.
9 Deliverables The First Article Unit shall be delivered to:
National Weather Service National Reconditioning Center Attn: (Insert PO#) 14200 Merritt Rd.
Grandview, MO 64030
Production Units shall be delivered to:
National Weather Service National Logistics Support Center Attn: (Insert PO#) 14200 Merritt Rd.
Grandview, MO 64030