1412236078 Appendix A - Technical Specifications.pdf

PDF 5 MB Posted

Attached to
(RFP-CCNA) Progressive Design-Build Services for the New World Substation
Solicitation number
1412236078
Issued by
Duval County, Florida

About this file

Summary

This is a Technical Specifications and Scope of Work document for a Progressive Design-Build (PDB) contract issued by Jacksonville Electric Authority (JEA) for the New World Substation project located at the southwest corner of Normandy Boulevard and New World Road in Jacksonville, Florida. JEA is soliciting an experienced design and construction team to provide comprehensive engineering, permitting, design, material procurement, and construction services for a new 230/26 kilovolt (kV) substation. The project scope includes designing and constructing a substation provisioned for three power transformers, nine distribution feeders, and three capacitor banks, with initial installation of two power transformers, six distribution feeders, one CapSwitcher, and one capacitor bank. The mandatory pre-response meeting is scheduled for November 13, 2026, at 10:00 AM EST, with an optional site visit on November 17, 2026, at 1:00 PM EST. Responses are due by December 8, 2026, at 12:00 PM EST. The project has a substantial completion target date of November 22, 2028, with construction scheduled to begin February 14, 2028. Design milestones are established at 10 percent, 30 percent, 60 percent, 90 percent, and 100 percent design completion, with the 60 percent checkpoint requiring submission of the Guaranteed Maximum Price (GMP).

JEA will procure major equipment items including two power transformers, one CapSwitcher, eight 230kV SF-6 breakers, and nine 26kV vacuum breakers, while the Proposer is responsible for all other materials, labor, construction equipment, transportation of specified breakers, and procurement and construction services. The Proposer must submit a GMP no later than the 60 percent design checkpoint that includes material procurement and construction costs, along with a risk register, final schedule, permitting matrix, and cost breakdown. The contract requires the Proposer to coordinate with multiple JEA departments including Transmission Projects, Distribution Projects, System Protection and Control Projects, and the System Operations and Control Center throughout design and construction phases. Environmental requirements include coordinating gopher tortoise removal prior to construction commencement and obtaining all necessary environmental, city, county, state, and FAA permits. The Proposer must provide comprehensive engineering deliverables including civil, architectural, substation, structural, and electrical drawings in formats compatible with OpenUtilities Substation 3D, along with engineering studies using specified software (SKM, CDEGS, and AGi32) and detailed design documentation at each milestone.

View the file

Other files

File Type Posted
1412236078 Appendix B - Response Forms.pdf PDF
1412236078 Appendix B- Subcontractor Form.xlsx XLSX spreadsheet
1412236078 Appendix C - Evaluation Matrix.xlsx XLSX spreadsheet
1412236078 Solicitation.pdf PDF
1412236078 Appendix C - Drawings.zip ZIP file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCOPE OF WORK OUTLINE FOR

PROGRESSIVE-DESIGN-BUILD

FOR NEW WORLD SUBSTATION

JEA TRANSMISSION AND SUBSTATION PROJECTS

Contents Technical Specifications for Progressive-Design-Build

01. OBJECTIVES AND DESCRIPTION OF PROJECT

01.01 Background

01.02 Project Description

02. SCOPE OF SERVICES

02.01 Additional Substation Details:

02.02 Outages

02.03 Engineering and Construction Scope of Work

03. TASK PLAN

03.01 Surveying

03.02 Permitting:

03.03 Geotechnical Data

03.04 Soil Boring Data

03.05 General Arrangement

03.06 Site Development

03.07 Detailed Electrical Design

03.08 Grounding Design

03.09 Conduit Design

03.10 Control House

03.11 Foundation Design

03.12 Engineering Specifications

03.13 Engineering and Inspection Assistance During Construction

03.14 Substation Engineering Drawings

04. ENGINEERING DELIVERABLES

04.01 Drawings

04.02 Electronic Files

04.03 Engineering Review and Schedule Requirements

01. OBJECTIVES AND DESCRIPTION OF PROJECT

JEA is seeking an experienced and qualified design and construction team to perform all engineering, permitting, design, structure/material procurement, and construction services required to build a new 230/26kV substation at the southwest corner of the intersection of Normandy Blvd and New World Rd, in Jacksonville FL, 32221. See Figure 1.

Figure 1: Substation Site

01.01 Background

JEA has secured a transmission corridor to extend an existing 230kV transmission circuit to serve existing and new customers in the area. A distribution substation, to be named New World Substation, will be built on the south side of Normandy Blvd to serve the needs in the area. The substation has a proposed in-service date of

November, 2028.

01.02 Project Description

This substation will be provisioned for three (3) power transformers, nine (9) distribution feeders, and three (3) cap banks. There is an additional provision within the substation for either one (1) additional power transformer, or a transmission line. Initially, two (2) power transformers, six (6) distribution feeders, one (1) CapSwitcher, and one (1) cap bank will be installed, while the remaining 3rd power transformer will be installed at a future, undetermined date.

The high-side of the substation will be of a breaker-and-a-half scheme, with a voltage of 230kV, as shown in

Figure 2.

Figure 2: 230kV Portion of Substation

The low-side of the substation will consist of a 26kV bus system to accommodate three (3) power transformers, with nine (4) 1200 amp feeder breakers, and one (1) 5.4MVAR capacitor bank associated to each transformer, as shown in Figure 3. The three (3) transformer will be interconnected with the use of two (2) main bus tie breakers. This project will install (9) 1200 amp feeder breakers, and one (1) 5.4MVAR capacitor bank, with provisions made for a T2 capacitor bank, to be installed at a future undetermined date.

Figure 3: 26kV Portion of Substation

Figure 4 is a depiction of the initial, geographically referenced, breaker-and-a-half scheme substation layout.

The layout establishes a transmission corridor, fence, roadway, and areas for retention pond(s).

Figure 4: Initial Substation Layout

At the commencement of construction, the Proposer shall clear the substation parcel, except for the first 135’ on the north side of the substation parcel, which will be cleared by the supporting scope coordinated by JEA

Transmission Projects group. See Figure 5. This transmission project will clear their portion of the parcel in advance of this project to establish a transmission corridor.

Figure 5: Boundary for site Clearing. Area is green to be cleared by another

The JEA Transmission Projects group will install two (2) poles directly north of the two eastmost 230kV substation bays. During construction, the Proposer shall coordinate with the JEA transmission group, and inform the transmission group on when the substation project is ready to attach the transmission conductors and shield wire from the #1 and #2 transmission poles to the two (2) substation A-frames. See figure 6.

Figure 6: Transmission Coordination

Prior to the commencement of site clearing and construction of the substation, the JEA Distribution Projects group will remove the existing distribution line, located in the center of the substation parcel. See figure 7.

Figure 7: Existing Distribution OH Line

02. SCOPE OF SERVICES

JEA intends to award one (1) contract to the most highly qualified team that meets the minimum qualifications to submit a proposal and with which JEA can successfully negotiate a contract. The project delivery method will be a progressive design build (PDB), with the goal of substantially completing (energizing substation) the project in its entirety by November 22nd, 2028. During design and construction, JEA intends to hold weekly, Bi-weekly, and/or monthly meetings, as required, with the winning Proposer maintaining the project schedule throughout. The Proposer shall initially correspond with a single JEA point of contact (POC). Additional JEA

POC may be identified as the project progresses.

The Proposer shall provide the guaranteed maximum price (GMP) no later than the 60 % design checkpoint.

The GMP will include procurement and construction.

Major items that shall be procured by JEA, include the two (2) T1 and T2 power transformers, one (1)

CapSwitcher, eight (8) 230kV SF-6 breakers, and nine (9) 26kV vacuum breakers. The Proposer is responsible for the transportation of all eight (8) 230kV SF-6 breakers (JEA Maintenance shall be responsible for verifying correct level of SF-6 gas in each breaker), and all nine (9) 26kV vacuum breakers to site from JEA’s

Commonwealth Service Center. JEA shall be responsible for transportation of the T1 and T2 power transformers to site, performing all lifts, including onto the concrete pad, assembly, and testing of the power transformers. At the commencement of construction, the T1 and T2 power transformers, along with the 230kV and 26kV breakers shall be stored at an existing substation nearby TBD.

A list of materials to be furnished by JEA through their storeroom shall be provided in Appendix A of the bid documents. Early in the project, the Proposer shall be responsible for identifying storeroom supplied material not provided by the Proposer, and inform the JEA POC of the need to order the pertinent material through the storeroom within enough time to meet the project schedule. The Proposer shall transport all storeroom supplied material to site.

All other materials required to construct the substation shall be procured by the Proposer. All labor, construction materials, and equipment needed to complete construction shall be supplied by the Proposer.

JEA shall perform all services required for testing and commissioning of the substation. JEA shall also perform all engineering related to protection and control, along with procurement of the relay panels.

During all phases of construction and inspection, work hours on site shall be as directed by any permits and the

JEA project representative. Typical workdays shall be from Monday to Friday 7:00 am to 5:00 pm.

The table below identified most tasks required to energize the substation, along with the party that will be responsible to perform the task.

Task

Responsible Party

Substation Physical Proposer

P&C Design JEA SPCP

Transmission Design Burns and Mac

Fire Alarm System JEA Security

Network Switch JEA Networking Group

Pulling Fiber from Street into

Patch Panel

JEA Telecom

Remote End testing JEA Telecom / SPC

Transformer Checkout JEA Substation Maintenance

P&C Checkout JEA SPC

Switch Checkout JEA Substation Maintenance

02.01 Additional Substation Details:

. JEA has or expects to have the following files available:

The following are pertinent substation files and documents that shall be provided to the winning The Proposer.

• Major equipment ratings

• Panel front views and panel layouts from JEA System Protection and Control Projects (SPCP) team.

• Site boundary survey, in PDF and CADD formats, with legal descriptions of the proposed site.

• System Fault Data and existing transmission line information.

• Environmental and wetland delineation survey.

• Preliminary substation 3D layout, in .dgn CADD format.

An initial environmental site survey was performed. Gopher tortoises were identified as existing onsite. The

Proposer is required to coordinate removal of the gopher tortoise prior to commencement of construction. Based on the preliminary project schedule, construction is scheduled to begin spring, 2028, so the tortoises shall need to be removed in September, 2027.

The New World substation site is in close proximity to an airport, so an FAA permit shall be required. In addition to filing the permit, the Proposer shall be required to identify any vertical restrictions associated with design and construction.

At the commencement of the project, JEA will provide the following documents as specifications and guidelines that the Proposer will use to design and build the substation, and formatting information for design study deliverables to JEA.

• Project Definition (PD) Word Document

• Substation Single-Line

• Initial substation 3D CAD layout (.dgn format)

• Engineering Specifications

• Construction Specifications

• Security Design standards

• Facilities Design standards

• Substation Packager Specifications (approved JEA equipment, equipment ratings, fabrication specifications)

• SKM deliverable standard

• AGi32 deliverable standard

• CDEGS deliverable standard

• CAD Standards

• Two (2) substation go-by designs

02.02 Outages

With assistance from the JEA point of contact, during design, The Proposer shall develop, with approval from

JEA’s SOCC (System Operations and Control Center), the JEA substation Planning Department, and the consultant’s contractor, a proposed feasible outage schedule. If required, with their contractor’s input, The

Proposer shall develop a design solution that limits outage durations where possible. Outages are expected to be granted in the Spring and Fall months only.

02.03 Engineering and Construction Scope of Work

The scope of work includes the pursuit of all site investigations, badge access, surveys, site design, foundation/geotechnical engineering, electrical design, grounding design, permitting, post design construction inspection services, post design engineering aid during construction, and construction services related to the

New World Substation.

03. TASK PLAN

03.01 Surveying

The winning Proposer shall be responsible for obtaining all surveys needed for the successful completion of a design package. These shall include:

1) Topographical Survey

2) Tree Survey

3) Wetland Survey

4) Improvement Survey

5) Underground facility locates

6) Any other surveys the Proposer deems necessary to complete all tasks.

03.02 Permitting:

The winning Proposer shall be responsible for obtaining all permits needed for design and construction. Any work related to environmental permitting shall be coordinated with JEA’s Environmental Department to ensure proper JEA procedures are followed. These shall include, but not be limited to:

1) Environmental permits: (SJRWMD, CEO, and FDEP) State and federal including wetland permitting, storm water discharge, hydrological study, protected species (gopher tortoise, birds, etc.) identification, and others as required.

2) City of Jacksonville: 10 set drawing review and approval, landscape/irrigation, tree clearing, tree removal, tree mitigation, maintenance of traffic and others as required.

3) Duval County Health Permits: Drain field and septic tank, well construction and well limited use water permits.

4) State of Florida permits: Onsite sewage treatment and disposal system septic tank and construction permit.

5) Storm water management control permits.

6) FAA permits

03.03 Geotechnical Data

The winning Proposer shall be responsible for defining and obtaining all soil borings and any other geotechnical explorations needed for the design of new structure foundations and any other tasks needed for the complete installation of structures within the New World Substation.

03.04 Soil Boring Data

Proposer to acquire soil borings needed for future foundation and ground grid design. All borings per ASTM

D-1586, shall be up to 50 feet deep with SPT’s at three (3) foot intervals. Note elevation of ground water at time of boring. Soil resistivity shall be measured for all borings at two (2) and twenty (20) foot depths. Also provide recommendations for maximum soil bearing capability.

03.05 General Arrangement

The consultant will be provided with an initial substation general arrangement design by JEA. JEA has coordinated the geographical location of the substation to align with the future transmission poles. The Proposer shall verify, and if necessary, make necessary modifications to the initial substation general arrangement. The

Proposer shall coordinate with structures provided by the substation material packager.

The design shall include, but not be limited to, the following: bus layout, switch locations, circuit breaker locations, transformer locations, control house, substation fence, area and perimeter lights, proposed drain field and retention pond, roads, confinement system, etc.

03.06 Site Development

The Proposer will design all substation site clearing, grading, pavement (including substation rock yard), fencing, draining (including retention pond if necessary), primary and secondary oil containment, landscape and irrigation plans, etc. The Proposer shall be responsible for determining and designing any site access improvements needed for construction. The Proposer shall also consider site access.

03.07 Detailed Electrical Design

The Proposer shall perform short circuit analysis to verify bus support, spacing and insulator selection.

The Proposer shall design lightning protection for the substation.

The Proposer shall design station service to include transformers, transfer switch, metering, and low voltage AC circuits for the substation yard and control house.

The Proposer shall design low voltage AC with the use of SKM software.

The Proposer shall design perimeter street lighting and structure area lighting, with the use of AGi32 illumination software.

03.08 Grounding Design

The Proposer shall perform the grounding study and design, with the use of CDEGS grounding software.

Grounding details shall be included.

03.09 Conduit Design

The Proposer shall design the conduit system for all equipment, fiber, and 26kV distribution within the substation property. The design shall include the use of cable trench and entrance into the control house. The

Proposer shall provide a cable and conduit schedule. JEA will provide an initial, and finalized cable schedule, at milestones indicated in this document.

03.10 Control House

The Proposer shall modify JEA’s standard control house design for use in the proposed substation.

03.11 Foundation Design

The Proposer shall design all foundations for all new substation structures using the best design techniques and practices. Foundation details shall be included.

03.12 Engineering Specifications

03.12.01 The Proposer shall work with the JEA project manager to create a “Civil Specification.” JEA’s general Civil Specification template shall be modified by the project manager with input and comments from the Proposer to reflect the unique conditions of the substation.

03.12.02 The Proposer shall work with the JEA Project Manager to create an “Electrical Specification.” JEA’s general Electrical Specification template shall be modified by the Project Manager with input and comments from the Proposer to reflect the unique conditions of the substation.

03.12.03 The Proposer shall work with the JEA project manager to create a “Specific Instructions.” JEA’s general Specific Instruction template shall be modified by the project manager with input and comments from the Proposer to reflect the unique conditions of the substation.

03.13 Engineering and Inspection Assistance During Construction

03.13.01 The Proposer shall provide engineering assistance during construction of the project on an as-requested basis. This shall include attending pre-construction meetings, meetings onsite during construction, meeting with relay technicians, and availability to resolve any field issues.

03.13.02 The Proposer shall also provide professional construction inspection services for the entire duration of the construction process to oversee the contractor’s work and help resolve any issues in a timely manner.

03.14 Substation Engineering Drawings

03.14.01 The following is a list of drawings that the Proposer will need to provide. All drawings shall be placed in JEA Construction Title Blocks, specifically, those containing the “BORDER” cell, used for batch printing. The use of reference files is recommended to avoid widespread conflicts due to changes that may arise during submittal reviews and other means, but final electronic submittals shall be self-contained with all references deleted. Please note that the list below is not intended to be complete, it shall be up to the Proposer to ensure all necessary drawings are created. intended to be complete:

1) Cover Sheet

2) General Notes

3) General Arrangement

4) Site Plan and Details

5) Temporary Security Plan

6) Clearing Plan

7) Grading and Drainage Plan and Details

8) MOT Plan and Access

9) Driveways and Rocking Plan and Details

10) Water and Sewer Plan and Details

11) Landscaping Plan and Details

12) Sodding Plan and Details

13) Irrigation Plan and Details

14) Foundation Plan and Details

15) Erosion Prevention Plan

16) Fencing Plan and Details

17) Electrical Layout Plan and Details

18) Foundation Plan and Details

19) Control House Plan and Details

20) Grounding Plan and Details

21) Conduit Plan and Details

22) Station Service and Electrical Panels

04. ENGINEERING DELIVERABLES

04.01 Drawings

04.01.01 The winning Proposer shall provide complete sets of civil, architectural, substation, structure, and electrical drawings as needed for construction, procurement, and analysis.

04.01.02 Provide signed and sealed electronic files in CADD format compatible with OpenUtilities Substation

3D. Provide PDFs scalable to 11”x17” as well as 24”x36” including a combined PDF of the drawing set.

04.01.03 Provide printed 11”x17” and 24”x36” copies of construction prints for use by the contractor, inspector, and JEA project manager during construction.

04.01.04 Provide as-built drawing sets (signed digital copies in CADD format compatible with OpenUtilities

Substation 3D, and PDF as directed by JEA project manager) per field markups.

04.01.05 PDF files of engineering studies, including studies for low voltage (SKM), grounding (CDEGS), lightning protection, and illumination (AGi32), and any other studies performed for the design of the project.

04.02 Electronic Files

04.02.01 Electronic files of all surveys specified section 3 in PDF and CADD format compatible with

OpenUtilities Substation.

04.02.02 Electronic files of soil boring reports in PDF format

04.02.03 Electronic files of foundation, structural, and all other applicable engineering calculations in PDF format along with the source files if possible.

04.02.04 Complete permits as specified in section 3 in PDF format.

04.02.05 Construction, material, and structure estimates at different design stages of the project.

04.02.06 Construction schedule in Microsoft project or P6, and PDF format at different design stages of the project.

04.02.07 Backup files in CADD format, compatible with OpenUtilities Substation 3D, of the proposed designs as well as as-built CADD format files, compatible with OpenUtilities Substation 3D, to reflect any changes during construction.

04.02.08 Electronic software files of engineering studies, including studies for low voltage (SKM), grounding

(CDEGS), lightning protection, and illumination (AGi32), and any other studies performed for the design of the project.

04.03 Engineering Review and Schedule Requirements

The Proposer shall submit 10%, 30%, 60%, 90%, and 100% design documents and drawings as shown in table

1 below. The milestone schedule shall be refined and finalized during the first few initial design meetings / teleconferences:

Milestone

~Due Date Design Documents to be Submitted for Review, and additional Tasks

(not all inclusive)

PO Issued 1/4/2027 JEA to issue a PO

10% 2/19/2027 • Begin site surveys

• Identify permits

• Review and approve preliminary 3D substation layout and single-line provided by JEA

• Deliver Single-line

• Develop Total Project estimates

• Identify long-lead material

• JEA deliverables – preliminary ctrl cable schedule

30% 4/2027 • Preliminary drawings - Electrical Plan, electrical elevation plan, control house plan, conduit plan, grounding plan, foundation plan, oil containment plan, substation layout.

60%

5/2027 • Gopher tortoise permit o Survey (Performed by JEA, 6/2027) o Removal of gopher tortoise (by JEA) (9/2027) o Coordinate Silt fence installation to prevent tortoise migration to site (by Proposer).

o *Include silt fence scope in design pricing.

• Preliminary studies documentation (SKM, Grounding, lightning).

• Design checkpoint JEA stakeholder meeting.

• Submit GMP to JEA (includes material procurement and construction) o GMP total project cost.

o Risk Register o Final Schedule o Permitting Matrix o Cost breakdown/cashflow

90% 9/17/2027 • JEA deliverable – Finalized ctrl cable schedule.

• Finalized drawings from previous milestones, all detail drawings, control house mechanical plan, control house plumbing plan, illumination plan, grading and drainage, landscaping plan, erosion prevention plan.

• Completed studies documentation (SKM, Grounding, illumination, lightning, etc.).

• Substation civil layout (yard, control house location, pavement, fence, retention pond location, W/WW, drain field (if applicable), clearing Plan).

• Applicable permits complete.

• Design checkpoint JEA stakeholder meeting.

• Outage Sequencing Document

100% 10/1/2027 • Final construction package to include all project drawings, specifications, calculations, studies, etc.

Start

Construction

Feb 14, 2028 • Contractor to begin construction.

• Material submittals for JEA approvals and record keeping.

Substantial

Completion

Nov 22, 2028 • Contractor substantially complete with construction.

Testing and

Commissioning

Nov 27, 2028 • Performed by JEA.

The Proposer shall account for design milestones checkpoint meetings, project progression and design meetings, the procurement process, and all other meetings not listed above required for successful completion of this project. The Proposer shall also account for initial weekly design meetings, and later, bi-weekly design meetings, bi-weekly construction meetings, and the Proposer shall have a dedicated construction manager/superintendent to attend each meeting to track and manage progress of construction.

File details come from the government source that posted it. Updated .