This document provides details for a federal contract solicitation to replace the St. Mary Canal Diversion Works Dam and modify it for fish passage. The solicitation number is 140R6024R0002 issued by the Department of the Interior Bureau of Reclamation. It seeks contractors to replace the existing dam and make modifications to allow for improved fish passage on the St. Mary Canal. Interested vendors should review amendment number 0002 for additional details on the required work. The response due date and expected award date are not specified in this document.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

140R6024R0002 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

R60

01/05/20240002

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

Bureau of Reclamation Missouri Basin Region Regional Office PO Box 36900 Billings MT 59107

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

12/11/2023

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Ryan Cope

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

St. Mary Canal Diversion Works, Dam Replacement and Fish Modification, Milk River Project, Montana

See the attached for the changes incorporated by this amendment:

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

Solicitation No. 140R6024R0002 Amendment No. 0002

Description Attachments:

1. A list of the virtual organized site visit attendees is attached for informational purposes only.

2. A copy of the virtual organized site visit presentation is attached for informational purposes only.

Acknowledgement: See Block 11 above regarding how to acknowledge this amendment. The Government must also receive the acknowledgement at the place designated for Acknowledgement of Amendments (See Block 19 of the Standard Form 1442).

Receipt of Proposals: The hour and date for receipt of proposals remains the same; February 9, 2024 at 1600 MST.

Contractor Questions: The hour and date for contractor questions remains the same; January 17, 2024 at 1600 MST.

Third Party: If you have given a copy of the solicitation to someone else, please forward this amendment accordingly.

St. Mary Canal Diversion Works Amendment No. 0002 Dam Replacement and Fish Modifications Solicitation No. 140R6024R0002

Virtual Organized Site Visit

December 19, 2023 at 10:00 AM MST

Attendance List

Name Company Email (if provided) Phone (if provided)

Colt Augare Triple Divide Construction

406-529-6117 Bill Fenner tdc.llc1977@gmail.com 406-781-5068 Frank Augare Steve Ross Riverside

Contracting, Inc

406-721-9267 Cale Fisher ctfisher@riversidecontracting.com Ed Kennedy Edward Kennedy

& Associates eddiemartinkennedy@gmail.com 319-594-3982

Joe Willingham

AIS

Infrastructure, LLC

JWillingham@ais-infrastructurellc.com

770-834-4681 Kyle Miller kmiller@ais-infrastructurellc.com Matt Pike mpike@ais-infrastructurellc.com Judd Murphy judmurphy@ais-infrastructurellc.com Cathal Hayes chayes@ais-infrastructurellc.com Lauren Collins J.F. Brennan

Company, Inc.

lcollins@jfbrennan.com

608-784-7173 Trent Nedens tnedens@jfbrennan.com Rich King Thalle

Construction Company rking@thalle.com Andrew Ladd ALadd@thalle.com Seth Rowney SRowney@thalle.com 817-521-5557 Neil VanAmburg

NW

Construction, Inc neil.vanamburg@nwconstruction.us

406-587-1907 Darian Clemens darian.clemens@nwconstruction.us Casey Patterson casey.patterson@nwconstruction.us Mike Corcoran mike.corcoran@nwconstruction.us Sydny Cataldo St. Clair

Construction, Inc.

Sydny@stclairconstruction.com

406-722-3207 Ollie St. Clair ollie@stclairconstruction.com RG Dickey Swank

Enterprises rg@swankenterprises.com

406-279-3241 Ethan Pletan epletan@swankenterprises.com Ryan Sondgroth Prospect

Construction, Inc.

rsondgroth@prospectconst.com

Nick Patch npatch@prospectconst.com 406-493-1300 Matthew Herbers Lefever Building

Systems MHerbers@lefeverbuilding.com 970-290-3815

Cody Gordanier Shimmick Corp. cody.gordanier@shimmick.com 303-547-8122 Rory Sale rory.sale@shimmick.com mailto:tdc.llc1977@gmail.com mailto:ctfisher@riversidecontracting.com mailto:eddiemartinkennedy@gmail.com mailto:JWillingham@ais-infrastructurellc.com mailto:JWillingham@ais-infrastructurellc.com mailto:kmiller@ais-infrastructurellc.com mailto:mpike@ais-infrastructurellc.com mailto:judmurphy@ais-infrastructurellc.com mailto:judmurphy@ais-infrastructurellc.com mailto:chayes@ais-infrastructurellc.com mailto:lcollins@jfbrennan.com mailto:tnedens@jfbrennan.com mailto:rking@thalle.com mailto:ALadd@thalle.com mailto:SRowney@thalle.com mailto:neil.vanamburg@nwconstruction.us mailto:darian.clemens@nwconstruction.us mailto:casey.patterson@nwconstruction.us mailto:mike.corcoran@nwconstruction.us mailto:Sydny@stclairconstruction.com mailto:ollie@stclairconstruction.com mailto:rg@swankenterprises.com mailto:epletan@swankenterprises.com mailto:rsondgroth@prospectconst.com mailto:npatch@prospectconst.com mailto:MHerbers@lefeverbuilding.com mailto:cody.gordanier@shimmick.com mailto:rory.sale@shimmick.com

St. Mary Canal Diversion Works Amendment No. 0002 Dam Replacement and Fish Modifications Solicitation No. 140R6024R0002

Marc Neihaus Northern Engineering & Consulting, Inc.

marc.neihaus@neciusa.com

Gianluca Raseni ATB Riva Calzoni USA Inc.

gianluca.raseni@atbrc.com Andrew Berselli andrew.berselli@atbrc.com 403-708-6986 Corey Hale Superior

Lidgerwood Mundy (SLM) chale@lidgerwood.com 612-516-0850

Westly Woodruff

PCI

Manufacturing, LLC wwoodruff@pci-mfg-llc.com 251-368-0818 x1103

Hunter Burns Local Gravel Supplier hunterburns65@yahoo.com 406-399-4554

Ross Contway Sletten Construction Company rcontway@sletteninc.com 406-761-7920 Mike Winkler mwinkler@sletteninc.com

John Webster Pavlik Electric Co., Inc.

johnw@qwestoffice.net 406-543-8783

Dan Sewzak Zak Dirt dsewczak@zakdirt.com 970-535-4657 Ryan Rhodes Dick Anderson

Construction ryan.rhodes@daconstruction.com 406-925-9643

James (Microsoft Teams didn’t have additional information)

Possibly: Lazy JW Roofing

(LJWR) &

Construction -or- Two Medicine Construction

(TMC)

LJWR: James Weasel Tail – jweaseltail@gmail.com

TMC: James Running Fisher – runningfisherjames@gmail.com

LJWR: 406-

450-8422

TMC: 406-799-

Clint Billedeaux Clint Billedeaux Construction billedeauxcc@yahoo.com 406-450-0883 mailto:marc.neihaus@neciusa.com mailto:gianluca.raseni@atbrc.com mailto:andrew.berselli@atbrc.com mailto:chale@lidgerwood.com mailto:wwoodruff@pci-mfg-llc.com mailto:hunterburns65@yahoo.com mailto:rcontway@sletteninc.com mailto:mwinkler@sletteninc.com mailto:johnw@qwestoffice.net mailto:dsewczak@zakdirt.com mailto:ryan.rhodes@daconstruction.com mailto:jweaseltail@gmail.com mailto:runningfisherjames@gmail.com mailto:billedeauxcc@yahoo.com

St. Mary Canal Diversion Works Dam Replacement and Fish Modifications

Virtual Organized Site Visit Request For Proposal

Solicitation No.

140R6024R0002

U.S. Department of the Interior Bureau of Reclamation Missouri Basin Region

Billings, Montana

Presentation Agenda

• SF 1442 Summation

• Scope of Work

• Acquisition Strategy & Schedule

• Proposal Instructions

• TERO

• Location and Site Use

• Technical Specifications &

Drawings

• Evaluation Process

• Please submit any technical questions in writing to Charlene Maurer at camaurer@usbr.gov

• If you would like to see a slide again or for a longer period of time, please utilize the chat function during the presentation.

Note: we would like to keep interruptions to minimum.

Reclamation Presentation Team

• Presenter 1: Charlene Maurer, Contract Specialist

• Presenter 2: TERO

• Presenter 3: Kurt Anderson, Regional Construction Engineer

• Presenter 4: Ryan Kent, TSC Civil Engineer

This is a Request for Proposal in accordance with FAR Part 15, Contracting by Negotiation:

• Block 10 – SF 1442

• The estimated price range is between $50,000,000 and $100,000,000

• The NAICS code is 237990 Other Heavy and Civil Engineering Construction

• Small Business Size Standard for the Small Business Participation document and

Subcontracting Plan is of $45 Million.

• This project is issued for Full and Open Competition. (Block 10—SF 1442).

• Block 11 – SF 1442

• Completion of the entire contract work is 1,506 calendar days after receiving the Notice to Proceed. The 1,506-calendar days is mandatory and are inclusive of the submittal process, actual onsite construction work, clean up, etc.

• An offer guarantee is required, (Block 13b – SF 1442).

• Offers providing less than 120 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected, (Block 13 – SF 1442).

• Acknowledgement of all Amendments are required in Block 19 of the SF 1442, which is the form provided in the original solicitation.

• The closing date for acceptance of proposals is February 9, 2024 at 1600 MST.

• Proposals are to be submitted via email . File size limitations (25MB) may require multiple emails to submit entire proposal. Confirm with camaurer@usbr.gov that all emails were received.

mailto:camaurer@usbr.gov

Procurement Schedule & Information

• Anticipated award date – May 28, 2024

• Anticipated NTP date – June 7, 2024

• Liquidated damages of $9,970.00 will be assessed for each day of performance beyond the required completion date (Paragraph F.2).

• Payment of Technical Data (Paragraph H.2). The Contracting Officer shall retain 10 percent from all progress, or other payments made under this contract (excluding any payment for mobilization and preparatory work) until the Contractor receives final acceptance of the contract.

Procurement Schedule & Information (cont.)

• An offer guarantee (Bid Guarantee) is required to be submitted with proposals (Paragraph L.15). The amount of the bid guarantee shall be 20 percent of the bid price or $3 million, whichever is less.

• Performance and Payment Bonds are required (Paragraph I.10).

• Performance of work by the Contractor (Paragraph I.13). The Contractor shall perform on the site, and with its own organization, work equivalent to at least 15 percent of the total amount of work to be performed under the contract.

Procurement Schedule & Information (cont.)

• Liability Insurance requirements are covered in Paragraph I.28.

• Work is subject to the Construction Wage Rates Requirements for Glacier County, Montana and can be found in Section J (General Decision Number MT20230077 – August 25, 2023).

SECTION L – Instructions, Conditions and Notices to Offerors

• Section L, Paragraph L.22, WBR 1452.215-81 Proposal Instructions, identifies how proposals are to be organized and submitted.

• Proposals are submitted in three (3) separate volumes

• Volume I – Business Proposal (Representations, Certifications, and Offer)

• Volume II – Technical Proposal/Past Performance

• Volume III – Pricing Proposal

• Paragraph (f) describes the evaluation factors which must be addressed as a part of each offerors Volume II – Technical Proposal.

• Proposals shall be emailed to camaurer@usbr.gov. The subject line shall contain the word “Proposal” and the Solicitation number 140R6024R0002.

SECTION M – Evaluation Factors for Award Section M provides information with regard to the Evaluation Factors for Award and the evaluation standards the Government will use when evaluating the factors.

As stated in Paragraph M.2 (e), the relative importance of factors is as follows:

Factors 1 through 5 are equal and significantly more important than Factor 6. All non-price factors (factors 1 through 5), when combined, are significantly more important than price (factor 6).

Blackfeet T.E.R.O

TRIBAL EMPLOYEE RIGHTS OFFICE

MISSION: “ IT IS THE MISSION OF THE BLACKFEET TRIBAL EMPLOYMENT RIGHTS OFFICE TO

ENHANCE THE LIVES OF THE BLACKFEET PEOPLE THROUGH EMPLOYMENT AND TRAINING”

Purpose: To strictly enforce the Indian preference requirements as set forth by the Blackfeet Tribe.

Any companies working within the exterior boundaries of the Blackfeet Nation are to be aware of the full contents of the Blackfeet Tribal Employment Rights Ordinance & Safety Act of 2010. The entire document is available on our website, www.btero.com

All Titles’, sections and sub-sections can be reviewed in their entirety in the Blackfeet Tribal Employment Rights Ordinance and Safety Enforcement Act of 2021 on the Blackfeet TERO website, www.btero.com.

We welcome you to Blackfeet Country and look forward to a positive professional relationship with your company during this upcoming construction season.

http://www.btero.com/

TERO STAFF CONTACT LIST

Blackfeet TERO 406-338-7887

Teola Bird, Director Email: tbird@blackfeetnation.com Beverly Begay, Admin Assistant Email: blkft_tero@blackfeetnation.com Cinda Pepion, Employment Specialist/EEOC Email: cpepion@blackfeetnation.com Maryann Hall, Compliance Officer Email: maryannhall@blackfeetnation.com Nicole Edwards, Compliance Officer Email: nedwards@blackfeetnation.com Terry Whitcomb,Compliance Officer Email: t.whitcomb@blackfeetnation.com mailto:tbird@blackfeetnation.com mailto:blkft_tero@blackfeetnation.com mailto:cpepion@blackfeetnation.com mailto:maryannhall@blackfeetnation.com mailto:nedwards@blackfeetnation.com mailto:t.whitcomb@blackfeetnation.com

Project Overview Dwg 15-D-60042

Very remote location and harsh winter weather

• Dam Constructed in 1915 and is approximately 198 ft long and 6 ft tall; headworks has 6 gates.

• Dam is concrete, uncontrolled weir located on St.

Mary River; has several stoplog bays in Sluiceway

• Highway bridge is a steel truss bridge with timber deck; spans majority of dam and cannot support loads.

Drawing “No.6_Sht6of34_Frame1_FIO”

Drawing “No.6_Sht6of34_Frame2_FIO”

East Side Access Road

St. Mary Diversion Dam Babb, MT

(1 mile )

Highway 464 (Duck Lake Road)

St. Mary River

Contractor Use Area

Highway 89

St. Mary Canal

East Side Access Road

Temp. Diversion System (Approx. Location)

Contractor Use Area (Approx)

Canal Plugs

Approx. location of new diversion dam

Cardston, Alberta Canada

East Side Access Limits (Approximate)

Babb, MT

Private landowner

Private landowner

Headworks

Sluiceway

Diversion Dam

Main Objectives:

• Replace old infrastructure that is well past its design life.

Specification Section 51 00 90 - Photograph 24

• Provide fish screening and passage at the site which has been absent historically.

Drawing 15-D-60043

St. Mary River:

• River stages fluctuate with seasonal storms and runoff

• River fed mainly by uncontrolled flow from St. Mary lakes; some from Sherburne.

• Low flow periods typically occur in the fall until snow begins to melt.

• River flows on the left side of the riverbed during this low flow period while the sluiceway stoplogs remain open.

Project Overview

Specification Section 51 00 90

– Photographs 23 and 26

Figures from Specification Section 51 00 10 - Hydrographs

Diversion Dam and Rock Ramp:

Earthwork

• Need to reshape U/S riverbed (River regarding)

• Riprap Layer A for ramp

• Riprap Layer B for armoring

• Grouting at U/S end of ramp

• Large boulders placed per drawings

Dam Weir and Retaining Wall

• Can either be Reinforced Structural

Mass Concrete (RSMC) or Precast

• Placements allowed in standing water per specs/drawings.

No Mechanical or Electrical items

Sluiceway:

Earthwork

• Located in river channel.

• Riprap armoring D/S

Reinforced Cast-in-Place Concrete

• Must be placed in the dry

• Includes approach slab

Drawing 15-D-60043

Project Overview

Key Mechanical and Electrical Items

• (2) 14’x10’ radial gates with hoists

• Heat Tracing on the gate seal plates per drawings/specs.

• Associated electrical equipment

• Stoplog slots

Headworks:

• Located in riverbank.

• Riprap armoring U/S and D/S

Reinforced Cast-in-Place Concrete

• Must be placed in dry

• Closest structure to existing features.

• Portion of existing retaining wall required to be demo’d for construction

Key Mechanical and Electrical Items

• (6) 8’x6’ slide gates with associated electrical equipment

• Power panels

• Trash rake and controls

Transition Flume:

• Structure is partially located in riverbank and partially in existing canal

• No associated armoring

Reinforced Concrete

• Complex geometry and rebar details

• Similar to concrete test placement

No Mechanical or Electrical items

Fish Screen Structure:

• Structure located in existing canal

Reinforced Concrete

• Large structure and large placements (as shown in drawings)

• A lot of miscellaneous metalwork

Key Mechanical and Electrical items

• Fish screens, brush cleaners and associated electrical and control panels

Check Structure:

• Structure is located in existing canal

• Riprap armoring required D/S

Reinforced Concrete

• Large structure and large placements

(as shown in drawings)

• A lot of miscellaneous metalwork

Key Mechanical and Electrical items

• (3) 14’x10’ radial gates with hoists

• Heat Tracing on gate seal embeds

• Power panels and control panels

Fish Return:

• Structure transitions to open channel and ties into St. Mary river.

• Riprap armoring required in open channel portion.

• Section of structure is buried.

Reinforced Concrete

• Relatively narrow

Key Mechanical and Electrical items

• Overshot gate with hoist

O&M Yard:

Features:

• Metal building system

• Propane system

• Septic system

• Well system (water source)

• Transformer connection and power system.

Reinforced Concrete

• Building foundation and various slabs.

• Specifications Section 01 14 10 – Use of Site

• Housing for construction personnel will be permitted on Government land, including housing for guards or watchmen as allowable.

• Local housing will be permitted outside of Government land if available.

Specifications - Highlights

• Specifications Section 01 14 12 – Work Restrictions

• All public roadways shall remain open at all times throughout construction. Public shall be allowed access to their residences throughout construction.

• Work shall be limited to Monday to Friday with 10-hour workdays except for the following removal and control of water activities.

• Extended shifts and additional shifts to the 10-hour workdays may be requested.

• Monitor and maintain dewatering system continuously 24-hours a day while in operation.

• Requests for extended shifts shall be submitted in writing 7-calendar days in advance for extended shifts and 14-calendar days in advance for additional shifts, and shall be subject to approval by the COR.

• Dewatering system operation shall be in accordance with Section 31 03 33 – Removal and Control of Water.

• Specifications Section 01 14 12 – Work Restrictions (cont’d)

• Irrigation diversion flow shall be 650 cubic feet per second and may occur at any time between March 1 and October 1 (Diversion Season). Government will be responsible for operating existing structures in order to divert required water. If canal is used for dewatering discharge location, Contractor shall coordinate discharge with Government. No feature of work shall impact the delivery of water.

• In-water activities including cofferdam construction, in-water excavation, concrete placement in the wet, etc. cannot occur between January 1 and July 14. The only exception is maintenance or emergency repair of the cofferdam. For the remainder of the year, all equipment shall be removed from the river at the end of each workday.

• Currently, existing sluiceway located on the river left provides fish passage at the existing dam during non-diversion season. Any in-river cofferdam construction or other work that blocks flow through the existing sluiceway shall not remain in place longer than 16 months unless the Contractor provides another method for fish passage at the existing dam.

• Specifications Section 01 14 12 – Work Restrictions (cont’d)

• Daily reductions or increases in canal flow cannot be more than 150 cfs per day.

• Minimum flow depths in the river shall be a minimum of 6 inches for flows of 150 cubic feet per second and higher. This requirement shall be met in all locations from the existing dam to the new fish return for all construction sequences throughout the contract.

• Temporary housing shall be the first feature of work completed. The housing shall be installed and occupiable prior to any other work beginning on-site.

• Specifications Section 01 32 10 – Construction Program

• Baseline Schedule – Required 21 days after the preconstruction meeting and approved before mobilization.

• An approved Schedule of Values is required for progress payment on any lump-sum items

• Specifications Section 01 33 00 – Submittals

• Reclamation’s submittal process is extremely thorough, and the successful contractor will not be allowed to begin work until the appropriate submittals are reviewed and approved. The time required to review a submittal or resubmittal is 28 days, unless specified otherwise and resubmittals are within 7 days. DO NOT UNDERESTIMATE

THIS EFFORT.

• Division 2 through 40 submittals: Submit no more than 5 submittals, counting original and resubmittals per Division listed within one 7-calendar day period:

• Division 2 though 23

• Division 25 through 28

• Division 31 through 32

• Division 33 through 40

• Specifications Section 01 46 00 – Quality Procedures

• Refer to Paragraph 3.02 A. for a list of minimum definable features of work that shall be included in your program.

• Specifications Section 01 51 00 – Temporary Utilities

• Temporary Water

• Water from St. Mary Canal is available for construction use

• Temporary Electricity

• 120 kVa transformer, 3 phase, 400-amp meter loop will be installed by Glacier County electric

• Specifications Section 01 57 60 – Protected Species

• Grizzly Bears

• During nighttime hours, all attractants shall be stored in a bear resistant manner

• If grizzly bears are within the construction limits, all work shall stop until the bear leaves the area

• Eagles

• Government will perform a nest survey for eagles in the work area prior to onsite work beginning

• Bull Trout

• See Section 011412 for work restrictions

• Specifications Section 01 91 13 – Commissioning and Testing

• RSN 01 91 13-1: Test Plan

• Schedule for commissioning and testing.

• Pre-commissioning photos.

• Testing procedures.

• 1.05 Scope

• Control Systems.

• Network.

• Headworks Gates.

• Fish screen cleaners in full operation.

• Fish screen louvers in full operation.

• Velocity measurements required for this portion.

• Autodialer.

• Trash Rake Operation.

• Post-Commisioning Support.

• 7-day Government operational period with Contractor key support as specified.

• Specifications Section 03 05 00 – Concrete Weir

• RSN 03 05 00-1: Concrete Weir Construction Plan

• Describe materials to be used, construction equipment, schedule, sequence, and methods for placing concrete or precast weir.

• 1.03 Project Conditions

• Contractor has option of constructing concrete weir using cast-in-place concrete or precast concrete.

• 1.04 Design Requirements

• Cast-in-place concrete design is provided in the drawings.

• If selected, the precast concrete design for the weir shall include the design requirements in the specification.

• Specifications Section 03 30 00 – Cast-in-Place Concrete

• RSN 03 30 00-3: RSMC Temperature Control Plan

• Design temperature control plan using finite element type software capable of running thermal analysis to evaluate internal concrete temperature with ambient and construction influences..

• Show location, sequence, and date of concrete placements scheduled for each RSMC designated structure.

• NOTE: Only structure shown on drawings to be RSMC is the Diversion Dam Weir if the Contractor chooses to do cast-in-place in lieu of precast.

• RSN 03 30 00-6: Plan for On-site Batch Plant(s), if used

• Location, plan, and schematic drawing of on-site batch plant.

• Peak capacity and anticipated daily production rate including aggregate transporting; volume of aggregate and cementitious material storage; concrete batching, mixing, transporting and placing in cubic yards per hour.

• NOTE: The closest commercial batch plant is located in Cardston, Canada and the port at the border is open from 8am to 6pm.

• Specifications Section 03 30 00 – Cast-in-Place Concrete (cont’d)

• This project will require a Test Placement:

Drawing 15-D-60052

• Specifications Section 31 03 20 – Cofferdam Construction

• RSN 31 03 20-1 Cofferdam Plan:

• Describe Sequences, methods, schedule, rates, materials, equipment

• Plans for protecting existing structures to remain and new construction

• Include plans for removal and disposal of materials

• Show plan for maintaining and repairing system

• RSN 31 03 20-3 Cofferdam Design and Drawings:

• Drawings and Calcs stamped by a P.E.

• Show layout in plan and profile and typical cross-sections

• Hydraulic modeling with proposed cofferdam alignment, flow depths, freeboard, velocities, armoring of cofferdam for velocities. Model shall reflect sequencing proposed.

• All design analyses – seepage, stability. Reflect unwatering/dewatering design.

• Specifications Section 31 03 20 – Cofferdam Construction (cont’d)

• 1.03 Project Conditions:

• Hydrographs of Saint Mary’s River are provided as information to aid in timing of construction operations to prepare for flood surcharge or flow bypassing as may be necessary for cofferdam design. Refer to Section 51 00 10 – Hydrographs.

• The cofferdam and unwatering/dewatering system shall be installed and operational in accordance with submittal outlined in Section 31 03 33 – Removal and Control of Water.

• 1.04 System Requirements:

• Prevent water from inundating excavation and dry work areas

• Design system in accordance with Section 01 14 12 – Work Restrictions.

• Specifications Section 31 03 33 – Removal and Control of Water

• RSN 31 03 33-1: Dewatering and Unwatering Plans, System Design

Calculations, Hydrogeologic Conceptual Model:

• Refer to Section 53 10 00 – Geologic Investigations and Section 53 20 00 – Records of Geologic and

Subsurface Investigations, for additional information regarding subsurface conditions encountered during Government field exploration.

• 1.07 Contractor Responsibility

• The water level, as measured from the nearest observation well, shall remain 3 feet below the base of the excavation, except for the temporary diversion system, as shown on drawings.

• Following construction of the structures and prior to operation, maintain a maximum water level, as shown on the drawings for each structure, to prevent floatation. If the water level is not maintained at the specified elevation, follow the procedure in the approved submittal for ballasting the structures.

• Specifications Section 31 03 33 – Removal and Control of Water (cont’d)

• 1.08 Project Conditions

• Conditions which may influence the dewatering and unwatering systems may include, but is not limit to

• Flows in St. Mary River and St. Mary Canal.

• Including ice jams and subsequent flooding.

• Including construction related diversions.

• Efficiency of unwatering systems, sumps, collectors, and discharge systems.

• Leakage from the temporary diversion system, soil plugs, or cofferdam, as referenced in Section

31 03 20 – Cofferdam Construction.

• 1.10 Monitoring Requirements

• A minimum of seven new observation wells shall be installed, developed, and monitored across the site.

• Specifications Section 31 23 12 – Temporary Diversion System

• RSN 31 23 12-1: Temporary Diversion System Plan

• Describe construction sequence, methods, schedule, materials, and equipment types, including any work required during transitions between non-diversion and diversion seasons.

• Include details on how temporary diversion system spatially interacts with and/or impacts the removal and control of water and construction sequencing.

• Include maintenance plan, repair plan, and Emergency Action plan.

• RSN 31 23 12-3: Temporary Diversion System Design and Drawings:

• Design drawings and calculations stamped by Professional Engineer. Showing layout in plan and profile, and typical cross-sections for each feature of the system, including soil plugs.

• Hydraulic modeling with proposed system and alignment showing flow depths, flow velocities, diversion capacity, and flow rates for diversion system, and hydraulic loading of soil plugs and diversion features. Model shall reflect construction sequencing being proposed.

• Include all design analyses, including but not limited to seepage and stability analyses for diversion system and soil plugs based on developed hydraulic modeling and anticipated water surface elevations, armoring requirements for anticipated velocities, and groundwater elevation.

• Specifications Section 31 23 12 – Temporary Diversion System (cont’d)

• 1.03 Project Conditions:

• Hydrographs of the St. Mary river and groundwater readings are provided in Section 51 00 10 and

51 00 70 to aid in the timing of construction and preparation for groundwater conditions.

• Contractor is responsible for the design, analysis, construction, and maintenance of the diversion system.

• The Government will be responsible for measuring flow and operating the existing headworks to maintain required flows through the system.

• 1.04 System Requirements:

• Temporary diversion system is required to convey canal flows from the existing headworks, around the work areas, and back into the existing canal.

• Diversion flows must be met with a minimum upstream water surface elevation of 4471.8 and a downstream water surface elevation in the canal of 4469.4. The locations of these elevations are shown on Drawing 15-D-60052.

• Temporary diversion system includes soil plugs. Construct soil plugs to maintain impervious barrier between diversion flows and dry work areas, and to maintain diversion flows. Contractor may elect for an alternative design for a water retaining feature where soil plugs are indicated on drawings.

• Specifications Section 31 23 12 – Temporary Diversion System (cont’d)

Drawing 15-D-60052

• Specifications Section 31 37 00 – Riprap, Grout, Boulders, and River

Grading

• 2.01 Material

• Riprap Layer A is 30-inch minus, predominantly rounded except for one location indicated on drawings

• Riprap Layer B is 13-inch minus, predominantly rounded.

• Riprap Bedding is 6-inch minus.

• Obtain rock from excavated materials placed in stockpile or commercial sources.

• Boulders shall be minimum 36 inches in diameter, maximum 48 inches diameter.

• Materials for river grading shall be sourced from within the limits for grading shown on drawings.

Additional material required to meet lines and grades shown on drawings for river regrading shall conform to requirements for Riprap Layer B for uppermost 1.5 feet of river grading. Outside of the upper 1.5 feet of materials, materials shall conform to requirements for general backfill (not requirements for backfill within 2 feet of structures) for earthwork for structures, outlined in Section 31 23 11 – Earthwork For Structures.

• Grout mix shall conform to all requirements for grout outlined in Section 03 30 00 – Cast-In-Place Concrete

• Specifications Section 31 37 00 – Riprap, Grout, Boulders, and River Grading (cont’d)

• Specifications Section 35 21 70 – Trash Rake

• 1.04 System Description

• Design, furnish, and install trash rake system with articulating boom mechanism capable of manual, and semi-automatic modes of operation to make a complete operational system.

• Trash rake designed to clean the entire trashrack structure under normal operating conditions from top to bottom and transport debris to designated dumping area shown on Drawing 15-D- 60161.

• Test and commission the new trash rake control system and equipment in accordance with Section 01 91 13 – Commissioning and Testing.

• 2.01 Trash Rake

• Trash rake System: Lakeside/Muhr Hydronic M Series Trash rake, Model M-2000 K with articulating boom mechanism, hydraulic cylinders, rake head with hydraulic gripper (4,000-pound capacity) and traversing unit or equal, having the salient characteristics in the specifications

• Specifications Section 35 22 08 – Overshot Gate

• 1.07 Design Drawings

• Contractor shall prepare a complete set of electronically generated design drawings approved by designer of record and submit for Government-acceptance

• 2.01 Overshot Gate

• A complete gate system, including the Overshot gate, Hoist, and ancillary components, shall be supplied by the same manufacturer.

• Overshot gate shall be as manufactured by any of the following:

• Fresno Gate, 7736 East Springfield Avenue, PO Box 40, Selma, CA 93662, (800) 333-1658, info@fresnovalves.com.

• Hydro Gate, 12000 East 47th Avenue, Suite 200, Denver, CO 80239, (800) 678-8228, moreinfo@hydrogate.com.

• Waterman, 25500 Road 204, Exeter, CA 93221, (559) 562-4000, ContractSales@WatermanUSA.com.

• Approved equal with the essential characteristics as outlined in specifications

• Specifications Section 35 23 31 – Heat Tracing for Gates

• 1.03 Systems Description

• Design, furnish, install, and test heating cable systems for the Radial Gates.

• Performance Requirements:

• Design based on the manufacturer recommended calculations and methods to prevent reservoir water from freezing and to maintain at least 40-degrees Fahrenheit temperature during winter at the following exterior surfaces:

• All sealing surfaces including wallplates, and sillplates for Check Structure and Sluiceway Radial Gates.

• Provide conduit and pull cable for future heat tracing of skinplate for Check Structure and Sluiceway Radial Gates.

• Provide separate heat trace circuits for sillplate and wallplate heaters.

• Provide heater conduits attached to embedded side of Wallplates and Sillplates to mitigate the formation of ice and prevent seals freezing to the Wallplates and Sillplates. Coordinate details of heater conduits with connection to junction boxes at top of spillway walls.

• Specifications Section 35 23 50 – Radial Gates

• 1.07 Design Requirements

• Statements throughout this specification apply to both the sluiceway and the canal check structure gates.

• Gates are to be identical 10-foot-wide by 14-foot-tall radial gates.

• Conceptual design of gates is provided on the contract drawings. The following are design requirements:

• Pin location.

• Skinplate radius.

• Sillplate elevation and location.

• Wallplate radius

Thank you for attending the Bureau of Reclamation’s Virtual Organized Site Visit.

Please email Contract Specialist Charlene Maurer to acknowledge your attendance, whereby an amendment will provide the attendance list to facilitate interested suppliers and sub-contractors: camaurer@usbr.gov

St. Mary Diversion Dam Construction Animation (sequencing may vary)

Video Link:

https://www.youtube.com/watch?v=_8SDg64Dta4 https://www.youtube.com/watch?v=_8SDg64Dta4

SF 30 - Amendment of Solicitation No. 140R6024R0002
Description of Amendment
Attachment 1 - Virtual Site Visit Attendees & Contact Information
Attachment 2 - Virtual Site Visit Presentation Slides

File details come from the government source that posted it. Updated .