This document is an Amendment to Solicitation No. 140R6024Q0073 for the WY Alcova Power Plant Roof (Membrane) Replacement project.
The key details are:
- The Bureau of Reclamation has a requirement to replace the roof membrane at the Alcova Power Plant in Wyoming. The current roof is approximately 20 years old and has had multiple repairs due to ongoing leaks.
- The contractor shall replace the 121 ft x 81 ft roof membrane with a new 60-mil EPDM single-ply membrane, including installation of new flashings, fasteners, sealants, and metal roof edging. The contractor shall also inspect and repair the roof drains to ensure positive drainage.
- The period of performance is 120 calendar days, with the onsite work estimated to be completed between September and October 2024. The due date for quotations remains July 17, 2024 at 1:00 PM MDT.
- The contractor must comply with strict safety and security requirements for the power plant facility, including a mandatory "Stop Work" policy. A detailed quality control plan and various submittals are required.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140R6024Q0073_Amd_0001.pdf | ||
| Sol_140R6024Q0073.pdf | ||
| Construction_Contract_Administration.docx | DOCX document | |
| Solicitation_No__140R6024Q0073.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1
1. CONTRACT ID CODE
I
PAGE OF PAGES
1 I 3
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO.
5. PROJECT NO. (If applicable)
0001 07/08/2024
6. ISSUED BY CODE R60 7. ADMINISTERED BY (If other than Item 6) CODE I
Bureau of Reclamation
Missouri Basin Region
Regional Office
2021 4th Avenue North
Billings MT 59101
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
9A. AMENDMENT OF SOLICITATION NO .
140R6024Q0073
X
9B. DATED (SEE ITEM 11)
06/18/2024
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
� The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers X is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment. and is received prior to the opening hour and dale specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
ORDER NO. IN ITEM 10A.
E. IMPORTANT:
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Contractor Dis not Dis required to sign this document and return ______ _ copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
WY Alcova Power Plant Roof (Membrane) Replacement, Kendrick Project, Wyoming
Please see the following continuation pages to view this Amendment No. 0001 in its entirety.
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 1 0A, as heretofore changed, remains unchanged and in full force and effect .
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED
(Signature of person authorized to sign)
Previous edition unusable
Darlene Dillon
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Solicitation No. 140R6024Q0073 Amendment No. 0001
1) Description of amendment details:
a. Performance Work Statement (PWS)—Remove the Performance Work Statement (PWS) in its entirety, and substitute therefor with the attached revised Performance Work Statement (PWS).
b. Informational Purposes Only—Responses to questions are provided for informational purposes only.
For convenience, essential changes on the revised solicitation pages are indicated by a vertical line within the margin, whereby the lines or paragraphs are changed from the previous version.
However, all portions of the revised solicitation pages shall apply, whether changes thereon have or have not been indicated.
2) Acknowledgement:
See Block 11 above regarding acknowledgement by offerors to this amendment. To be considered for evaluation and award, the Government requires acknowledgement of this and all amendment(s). (Please See Block 19 of the Standard Form 1442, on the original solicitation, ACKNOWLEDGEMENT OF AMENDMENTS).
3) Receipt of Proposals:
The date for receipt of quotations remains July 17, 2024. The hour for receipt of quotations is 1:00 PM (Mountain Daylight Time-Denver).
4) Third Party:
If you have provided a copy of this solicitation to another company or person, please forward this amendment accordingly.
PWS-1
Revised
Solicitation No. 140R6024Q0073 Amendment No. 0001
PERFORMANCE WORK STATEMENT (PWS)
Alcova Power Plant Roof (Membrane) Replacement
1.0 Need
The Bureau of Reclamation has a need for the replacement of the roof membrane at the Alcova Power Plant, Wyoming.
2.0 Background
The current roof is a cement roof covered with a single layer membrane and is approximately 20 years old. Multiple repairs have been made to the existing roof membrane over the past years, however, leaks continue to damage the equipment inside the plant.
3.0 Locations of Project work
The Alcova Power Plant is located at 22105 Alcova Dam Access Road, Alcova Wyoming, which is approximately 30 minutes from Casper, Wyoming, near the intersection of State Road 220 and Kortes Road.
4.0 Scope
A) The contractor shall replace the roof membrane, which is approximately 121 feet x 81 feet.
Access to the roof is via an interior permanently affixed ladder, through a 3 feet x 3 feet hatch. (See Figure 1).
B) The contractor shall examine and repair the roof drains to reduce pooling of water.
C) The Contractor shall dispose of all debris, conduct a magnetic sweep of area to ensure all metallic hardware is picked up, and restore the work site to original or better condition, including filling in ruts caused by equipment, if necessary. Use of government dumpsters is NOT allowed.
D) The principal components of work include and are not limited to the following:
1) Sweep existing rock ballast to the side and remove existing membrane roofing, flashing and all caulking/sealant.
2) Inspect and repair/improve roof drains to address standing water on roof, especially near the center. Ensure positive drainage on the roof, whereby all water flows to the drains to avoid future problems. Flow test to ensure the drains are not restricted.
3) Replace the roof membrane with recycled 60-mil EPDM single-ply membrane.
a) Install all necessary flashings, fasteners, plates, adhesives, caulking, sealants, and termination bars, including flashing(s) of all roof penetrations and fabrication and installation of new metal roof edging.
PWS-2
Solicitation No. 140R6024Q0073 Amendment No. 0001 i)The contractor shall submit color samples for the new metal roof edging, whereby the COR will make the selection of color.
4) Sweep existing rock ballast back over new membrane, add matching ballast if required.
5) Leak check roof and drains
a) Spray or hose testing to simulate heavy rain per applicable ASTM standards.
i) Power plant service water is only available on the ground floor.
ii) The contractor will need to provide the means to provide adequate pressure and volume for testing.
5.0 Environmental Protection
The contractor shall comply with all federal, state, and local laws, regulations, and standards. All environmental protection matters shall be coordinated with the Contracting Officer or Contracting Officer's Representative.
6.0 Period of Performance and Hours of Operation
PERIOD OF PERFORMANCE: To allow adequate time for the submittal process, (final) payment, and sufficient time for actual onsite work, the overall period of performance is One Hundred Twenty (120) calendar days after issuance of the Notice to Proceed, with actual onsite work estimated between September 2024 and October 2024 (or sooner), before seasonal winter weather. (Note: The Notice to Proceed will be issued after a Certificate of Liability Insurance is received and accepted/approved by the Contracting Officer).
HOURS OF OPERATION: Government personnel at Alcova Power Plant work Monday- Thursday 7:00 AM-5:30 PM (local time zone). While the microwave transmitter is powered down, the plant is staffed by power plant personnel. The contractor shall perform work within the normal duty hours of the power plant personnel.
7.0 Schedule
The contractor shall submit a detailed schedule for the procurement of materials, removal of the existing roof membrane, installation and testing for leaks of the new roof membrane to the Contracting Officer Representative within 20 days after award.
8.0 Known Hazards and Restricted Areas
Alcova Power Plant is a high voltage generation plant with an adjoining switchyard. The high voltage transmission lines pose significant hazards to workers within safe distance requirements, (10 feet). High winds are common at the Alcova Power Plant, whereby attention to safety to prevent equipment or material from accidental contact with lines is required. Access to roof that is clear of the switchyard is available on the south and west side of the power plant through an
PWS-3
approximately 10' wide access gate. (See Figure 2).
A microwave transmitter is located on the roof. The transmitter must be powered down when personnel are between the transmitter and the reflector. The Contractor is responsible for coordinating with the Contracting Officer’s Representative (COR) and/or power plant supervisor at least 48 hours in advance of starting work or resuming suspended work. The clearance must be removed (microwave powered up) no later than 5:00 PM (local time zone) each day to establish normal communication with Reclamation’s control center.
Access to the power plant must be maintained and free of debris. If there is a risk of items or material falling on normal entrances, either approved guarding must be installed at the contractor’s expense, or a dedicated safety monitor must be provided by the contractor.
Emergency access to the power plant roll door, located near the parking lot, must be readily available in case of a fire or accident in the facility. To protect all personnel in the area, the Contractor is responsible for marking safe entryways and providing a safety observer when utilizing lifting equipment and removing material from roof.
Periodic overhead crane operation occurs throughout the day; therefore, all personnel shall be briefed to watch for crane operation and comply with the crane operator’s instructions.
Alcova Power Plant is a restricted access area. A government escort is always required within the power plant. The government will flag an access path to the roof hatch; however, this does not waive the requirement that a government escort is required.
9.0 Safety and Health
The Alcova Power Plant is in a remote area. The contractor is responsible for providing sanitary porta-john and wash station for their employees. Regular maintenance and removal of portable restroom facilities is the responsibility of the contractor. All restroom facilities must be removed from the site within 48 hours of completion of work unless arrangements are made with plant supervisor due to limited delivery/pick up times. Use of plant restroom is prohibited due to restricted access inside power plant.
Cell service is limited in the area. An emergency phone with call procedures is located near the roll-up door. The contractor shall notify the onsite government representative of any injuries and if first aid assistance is required. Due to the remote location, ambulance response can take in excess of 30 minutes. A Life flight landing area is located across the street in the public park.
Coordinates for emergency services are posted near the phone. The government denies responsibility for costs for emergency services, including life flight, for contractor employees.
All workers working near the edge of the roof must be tied off to a fall arrest system. No fall arrest system is installed on the roof. The contractor is required to supply a fall arrest system or equipment that meets OSHA requirements for protecting workers from fall hazards.
Operation of any plant switches, breakers, GFCls or equipment is NOT permitted by contractor employees. The Contracting Officer’s Representative or Reclamation’s Power Plant Supervisor will be responsible for notifying power plant personnel to operate any switches, breakers, tripped
PWS-4
Solicitation No. 140R6024Q0073 Amendment No. 0001
GFCls or equipment belonging to the government.
The contractor shall comply with the Occupational Safety and Health Administration's (OSHA) rules and regulations and Reclamation's Safety and Health Standards. The contractor shall also submit a safety plan in accordance with Reclamation's Safety and Health Standards at http://www.usbr.gov/safety/rshs/index.html. The safety and health standards include, but are not limited to, the following:
a. A high degree of safety and health standards shall always be exercised.
b. The contractor shall use extra caution when operating vehicles.
c. The contractor shall operate vehicles at or below the posted speed limits.
d. The onsite contractor/subcontractor personnel shall be certified in First Aid and
Cardiopulmonary Resuscitation (CPR). Certification of First Aid and CPR of onsite contractor/subcontractor personnel shall be submitted to the COR.
e. Approved first aid kits shall be carried in all vehicles.
f. The contractor shall be responsible for supplying personal protective equipment for all the employees.
g. The contractor shall keep the premises free from debris and accumulated waste.
h. Any vandalism, security, safety, or health issues shall be reported within 24 hours to the COR. Any crimes against property or people, or need for emergency services, shall first be reported to the appropriate County Sheriff's Office or emergency medical provider. If possible, also provide the COR any information pertaining to the condition, time, date, place, and description of damages, witnesses, suspects, or other information.
The contractor shall report to the Contracting Officer (CO), by telephone or email, any near miss or accident(s) involving injury, death, damage to Government property, or accidental loss of Government property resulting from the activities of the contractor, their subcontractors, their agents, or their employees. A report shall be forwarded to the CO within two (2) working days after the date of the accident. All accident records required by the Occupational Safety and Health Act shall be maintained in accordance with OSHA guidelines. In addition, the contractor shall cooperate and provide data to follow-up investigation(s) by Reclamation of an accident.
10.0 STOP WORK Policy
Because the power plant and work area must always be safe, all Bureau of Reclamation employees and all contractor employees have the right and responsibility to call for a STOP WORK at any time they observe a safety hazard. When workers are notified that a STOP WORK has been called all Reclamation power plant personnel and contractor employees will place work in a safe condition and stop all work in and around the plant until a resolution of the safety hazard is determined. No work may resume until the contractor’s onsite project manager, designated power plant supervisor, and Contracting Officer’s Representative agree to a safe procedure. Notification of STOP WORK can be made by voice, whistle, horn, radio, or other acceptable means to accommodate personnel who are deaf, hard of hearing, or have a speech disability. All personnel in and near the facility will be notified quickly that work is to stop. Adherence to this policy is mandatory for the safety of personnel and equipment.
PWS-5
Solicitation No. 140R6024Q0073 Amendment No. 0001
11.0 Contractor Quality Control Plan (QCP)
The contractor shall develop and maintain a Quality Control Plan. The contractor is responsible for the management and quality control to meet industry standards for the replacement of the roof membrane.
The Government will monitor the contractor's performance. The project work is subject to Government inspection by the Contracting Officer’s Representative (COR) at any time.
The Government's Quality Assurance program is not a substitute for the contractor's Quality Control Plan (QCP). Unacceptable work will require the task to be re-performed without additional expense to the Government. The Government reserves the right to utilize any method of inspection.
12.0 Security Requirements
All contractor employees must be U.S. citizens or have a valid Immigrant Visa Number, Permanent Resident Card, or Resident Alien Card authorizing them to work in the U.S. The contractor shall abide by all Federal, State, and Local laws pertaining to hiring and assigning tasks to personnel.
In accordance wi th WBR 1452.237-80 Security Requirements- Bureau of Reclamation, the contractor shall provide a listing of all personnel performing work under the contract prior to performance. Copies of state issued licenses that pertain to work related tasks may be required. The contractor shall notify the Contracting Officer or the Contracting Officer’s Representative in writing of any personnel change to this list prior to the implementation of such change(s). Trucks, vehicles, and personnel will be licensed, insured, and certified as required by the appropriate governing agencies.
All personnel employed by the contractor or any representative of the contractor entering the Government installation shall abide by all security regulations of the installation.
13.0 Government Furnished Equipment – Information
POWER/ELECTRICAL SUPPLY: The government will provide limited 120V AC power for convenience at ground level. Power plant provided power at ground level may not be extended to the roof due to excessive distance. Extension cords and equipment attached to the plant power is subject to inspection by government employees. Items determined to be in poor condition, lacking required safety guards, or other deficiencies will not be permitted to be attached to government furnished power. No power is available on the roof. If power is needed on the roof, the contractor must supply a portable generator and all necessary cords. No government tools or materials are provided for use by the contractor. The government does not assume responsibility for providing or maintaining electrical power for contractor.
CRANE AND CRANE OPERATOR: The government will provide an overhead crane and crane operator for the contractor’s inspection of the interior areas, such as the roof drains. The contractor must arrange use of the overhead crane and crane operator with the power plant supervisor. Compliance with the power plant fall protection program is required if the
PWS-6
contractor utilizes the government furnished overhead crane and (government) crane operator during contractor inspection(s). Only authorized (government) power plant personnel may operate the crane.
14.0 Contractor Furnished Supplies
The contractor shall provide all labor, equipment, materials, supplies, and permits (if applicable) necessary to meet the requirements of the purchase order. The contractor shall provide sanitary porta-john(s) and wash station(s) for their employees.
15.0 Project Deliverables
The Contractor shall sweep ballast to the side, remove existing membrane, install new recycled 60-mil EPDM single-ply membrane roof in accordance with the manufacturer's specifications, sweep ballast back over new membrane, install all necessary flashings, fasteners, plates, adhesives, caulking, sealants, and termination bars, flashing of all roof penetrations, and fabrication and installation of new metal roof edging in a color chosen by the COR. The Contractor shall also provide a 20 Year Membrane Only Manufacturer's Warranty.
16.0 Performance Standards
The designated Contracting Officer Representative (COR) will document acceptable and unacceptable contract performance. The following table summarizes the tasks, the performance standard, monitoring method, and disincentives/incentives for performance standards.
Task
Description
Performance
Standard
Method of
Monitoring Disincentive Incentive
Condition Spray or hose testing to simulate heavy rain per applicable ASTM standards.
100% Inspection
Re-work at contractor's expense
Exceptional contractor performance will be documented.
17.0 Required Submittals
The contractor shall provide submittals in accordance with the submittal table. The Government has 10 days to review and approve each submittal or request a revision to the submittal. Note: The submittal submission and review/approval process are inclusive in the Period of Performance.
*RSN – Required Submittal Number
*CO – Contracting Officer
*COR – Contracting Officer’s Representative
PWS-7
Solicitation No. 140R6024Q0073 Amendment No. 0001
SUBMITTAL TABLE
*RSN
Clause Or Section Title
Submittals Required Due date or delivery time
Electronic Copies to be submitted (via email):
*CO *COR
1 1452.228-70 Liability Insurance Certificate
Within ten (10) calendar days after award
2 (PWS) 10.0
Security Requirements & and
WBR.1452.237-80
ALT III
List of all contractor and subcontractor employees performing work under this purchase order with supporting documentation
Within ten (10) calendar days after award
3 (PWS) 9.0 Safety & Health &
WBR 1452.223-81
Safety Plan Fourteen (14) calendar days after award
4 (PWS) 7.0
Schedule
Schedule of onsite construction work
Within Twenty
(20) calendar days after award
5 (PWS) 9.0 Safety & Health
First Aid & CPR Certifications of Onsite Personnel
Within Twenty
(20) calendar days after award
6 (PWS) 4.0(D)(3) Color samples for the new metal roof edging
Prior to installation
7 Payrolls and Basic Records 52.222-8
Certified Payroll(s) Weekly for each week of contract performance encrypted encrypted
8 (PWS) 15 Manufacturer’s 20-year (Membrane) Warranty
Prior to Final Payment
1 1
9 Release of Claims 1452.204-70
Release of Claims
(DI-137)
After completion of work and final cleanup and prior to final payment
1 1
PWS-8
RESPONSES TO QUESTIONS – FOR INFORMATIONAL PURPOSES ONLY:
1) Question: I am verifying replacement of the EDM roof only requires a single layer of isoboard, and not two.
Response: Please refer to Paragraph 4.0 of the Performance Work Statement within the solicitation, which states to "Replace the roof membrane with Recycled 60-mil EPDM single-ply membrane."
2) Question: Are tapered insulation crickets desired for this project to provide positive drainage?
Response: Please refer to revised Paragraph 4.0 (D)(2) of the Performance Work Statement (PWS): Ensure positive drainage, whereby all water flows on the roof, to the drains to avoid future problems.
3) Question: Is anything more than water testing the drains required as part of the primary work to the drains? (The drains appear to be fine).
Response: No, flow test to ensure drains are not restricted.
4) Question: Is a new roof membrane needed, or will insulated crickets resolve all of the current roof membrane issues?
Response: A new roof membrane is needed.
5) Question: How tall is the building?
Response: The building is approximately 60 feet tall.