This document contains an amendment to a solicitation for the Jamestown Dam Outlet Works Stilling Basin Concrete Floor Repairs project. The amendment provides additional details on the project scope and responses to questions from prospective offerors.
The project involves repairs to the concrete floor of the outlet works stilling basin at Jamestown Dam in North Dakota. Repairs include removing deteriorated concrete and installing new concrete. The amendment incorporates COVID-19 requirements and extends the proposal submission deadline to August 11, 2021. It also lists contractors who attended a pre-bid site visit and provides responses to questions on topics like the volume of available fill material, soil characteristics, removing an existing fence, unwatering the stilling basin, quality control requirements, and the extent of concrete removal and repairs. The document appears to be an on-site pre-bid amendment intended to provide additional information to offerors.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140R6021R0016_Amd_0001.pdf | ||
| Solicitation_No__140R6021R0016.pdf | ||
| Sol_140R6021R0016.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140R6021R0016 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
Billings MT 59107
R60
PO Box 36900 Regional Office Great Plains Region Bureau of Reclamation
07/30/20210001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
07/09/2021
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Jamestown Dam, Outlet Works Stilling Basin, Concrete Floor Repairs, Garrison Diversion Unit
-- Garrison Division, Jamestown, North Dakota
Please see the following pages to view this amendment in its entirety.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Darlene Dillon
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Solicitation No. 140R6021R0016 Amendment No. 0001
Description of Changes:
1) Compliance with all Federal requirements regarding COVID-19 is hereby incorporated.
Acknowledgment: See Block 11 above regarding acknowledgement by offerors to this amendment. The Government requires acknowledgement of this amendment at the place designated for receipt of bids. (Please See Block 19 of the Standard Form 1442).
Receipt of Proposals: The date and hour for receipt of proposals is August 11, 2021 at 1:00 PM (Mountain Daylight Time). Proposals and the bid bond are to be emailed to DDillon@usbr.gov.
Third Party: If you have provided a copy of this solicitation to another company or person, please forward this amendment accordingly.
The following listing of contractors and persons who attended the organized site visit, which took place July 21, 2021, at 10:00 AM (CDT), are provided to assist in facilitating coordination of sub-contractors and suppliers with those in attendance:
Shane Kurte Colleen Lund Brent Anderson
Scherbenske Inc.
Scherbenske Inc.
Structural colleen@scherbenskeinc.com colleen@scherbenskeinc.com contact information not available
For Informational Purposes: A list of questions from prospective contractors and their respective answers are attached for informational purposes only (on the following pages).
Jamestown Dam Outlet Works Stilling Basin Concrete Floor Repairs Solicitation No. 140R6021R0016
Responses to Attendee Questions
PRE-BID SITE VISIT
RESPONSES TO ATTENDEE QUESTIONS
Beginning at 10:00 a.m. on July 21, 2021, a pre-bid site visit was facilitated by Mr. Dustin Albright, Bureau of Reclamation. The site visit consisted of the attendees reviewing the staging area, anticipated cofferdam location and the stilling basin. The following are Reclamation’s responses to the questions presented at the pre-bid site visit and walk-thru:
Q. How much water will need to be removed or controlled from the stilling basin when you close the dam’s regulating gates?
A. The outlet works has an underdrain system that exists in 3 of the existing chute blocks.
During the 2018 stilling basin inspection, we measured approximately 22 gallons per minute combined discharge from these drains. In addition, approximately 1 gallon per minute leakage is possible through the dam’s regulating gates.
Q. How much volume of fill material is available in the Government’s borrow area?
A. 385 tons of fill material was purchased by the Government in the summer of 2018 and stockpiled in the borrow area as identified in Figure 1 (Construction Staging Area Map) of specification Section 51 00 00 – Information Available to Offerors. The exact volume of fill material remaining at the borrow area is unknown. Refer to specifications Section 31 52 00 – Cofferdam, Paragraph 1.02 G.
Q. What are the characteristics of the soil material in the Government’s stockpile?
A. Refer to specifications Section 31 52 00 – Cofferdam, Paragraph 1.02 G.
Q. Can the chain-link fence around the perimeter of the stilling basin walls be removed for access?
A. Yes. Refer to specifications Section 01 56 20 – Existing Fences.
Q. Is the bottom of the river clay material?
A. Refer to specifications Section 31 52 00 – Cofferdam, Paragraph 1.02 D.
Q. Who is the contact with the North Dakota Game and Fish Department for assistance with removal of fish from the stilling basin?
A. Refer to specifications Section 02 24 30 – Unwatering Stilling Basin, Paragraph 3.03 A.1.
Q. What are the 3 buried pipes discharging from the left riprap slope downstream of the stilling basin used for?
A. The 3 buried pipes collect and discharge surface runoff and groundwater from the slopes around the north and east side of the dam’s left abutment. Typical flows, as measured by Reclamation, range from 0 to 5 gallons per minute although flows may be higher during rain events. Refer to specifications Section 02 24 30 – Unwatering Stilling Basin, Paragraph 3.02.
Responses to Attendee Questions
Q. Is there a requirement for Quality Control on this project?
A. Yes. Refer to specifications Section 01 46 00 – Quality Procedures.
Q. Is there a requirement for Safety on this project?
A. Yes. Refer to specifications Section 01 35 20 – Safety and Health and Section 01 35
30 – Contractor’s Onsite Safety Personnel for safety requirements.
Q. If corroded reinforcing steel is encountered in the existing stilling basin concrete, what are the requirements?
A. Refer to specifications Section 03 81 10 – Concrete Removal, Paragraph 3.04 M.
Q. Will concrete removal be required below the existing reinforcing mat?
A. Refer to specifications Section 03 81 10 – Concrete Removal, Paragraph 3.04 A.
Q. Who is the owner of the overhead power lines crossing the James River near the stilling basin?
A. Northern Plains Electric Cooperative.
Q. What are the extents of the outlet works stilling basin concrete floor repairs?
A. Refer to Concrete Removal Plan (Drawing No. 769-603-60038) and Concrete Repair
Plan (Drawing No. 769-603-60040).
Q. What is the current water depth in the outlet works stilling basin?
A. At the time of the site visit, Reclamation was releasing 40 cubic feet per second and the water depth in the stilling basin was approximately 8.5 feet.
END OF RESPONSES TO ATTENDEE QUESTIONS
Responses to Questions Submitted Via Email
RESPONSES TO QUESTIONS SUBMITTED VIA EMAIL
Q. Do you have CAD files for this project we could look at?
A. CAD files will not be released prior to award of the contract. CAD files will only be released, upon request, to the contractor awarded the project.
Q. Looking for a mix design quote and they want to know the approximate yardage for the project. Do you have approximate yardage?
A. For repair quantities, refer to Section B of the Solicitation, Price Schedule table, CLIN No. 2 and CLIN No. 3.
END OF RESPONSES TO QUESTIONS SUBMITTED VIA EMAIL