This is a Statement of Work for fire suppression bottle services at Davis Dam under a Blanket Purchase Agreement (BPA). The work requires testing, refilling, or replacing CO2 50-pound bottles from a 96-bottle fire suppression system in compliance with NFPA, Federal, and State codes. The contractor must service 20 bottles annually across five fiscal years (FY2027 through FY2031), with each bottle receiving hydrostatic testing and/or servicing as needed.

The contractor is responsible for delivering serviced bottles that meet system specifications, including proper valving to match the existing system at Davis Dam. All bottles must be weighed and marked at the time of service, with documentation provided for verification. Exchange bottles are acceptable if they possess compatible valving. A critical requirement is that removal and installation of bottles on the active suppression system will be performed exclusively by Davis Dam employees; the contractor's role is limited to testing, refilling, or replacing the bottles and providing the required inspections and documentation before bottles are returned to service or held as spares.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 1 - Statement of Work

Fire Suppression Bottles at Davis Dam - BPA

Attachment 1 - Statement of Work

Fire Suppression Bottles at Davis Dam

1.1 Description of the Work

Davis Dam has a CO2 50lb. bottles fire suppression system. The 96-each bottles must be tested, refilled or replaced at various dates throughout the year. According to NFPA, Federal and State codes.

Removal and installation of 50lb bottles will ONLY! Be done by Davis Dam Employees, taking extra care since we have an aging system and replacement parts are very difficult to get.

Notes:

Testing, refill or replace.

FY2027 - 20 each will need service

FY2028 - 20 each will need service

FY2029 - 20 each will need service

FY2030 - 20 each will need service

FY2031 - 20 each will need service

After the testing, refill or service of the 50lb fire suppression bottles the following inspections/documentation will be performed and provided:

1. All Hydro and or serviced bottles will be weighed and marked at time of service and again by Davis Dam employees to verify before being put in service or as spares.

2. Exchange bottles are acceptable if they have the proper valving to match the

System at the Davis Dam facility.

3. Bottle removal and instillation on active suppression system will be performed by

Davis Dam Employees ONLY!