Emergency_Generator_Site_Visit_QNA_0002.pdf
PDF 678 KB Posted
- Solicitation number
- 140R3026Q0071
About this file
This is a Questions and Answers document from an Emergency Generator Site Visit addressing contractor requirements and operational constraints for maintenance and load bank testing of six emergency generators located at Bureau of Reclamation (BOR) facilities in Nevada and Arizona.
The document identifies six generators requiring maintenance and testing: an HIMOINSA unit at the NV SRF Building, a 1250 KW ONAN at the NV Visitor Center, a KATO LITE at NV Lower Portal Road, a 35 KW ONAN portable unit in Arizona, and KOHLER units at both NV and AZ Gantry Crane locations. Key operational constraints include a 75-foot maximum estimated cable length requirement for load bank testing, a 20-ton vehicle weight limit and 9-foot width restriction for accessing Generators 3-6, and personnel escort requirements by BOR staff members. Access to the SRF Building generator may be impacted by construction removing temporary buildings, though an alternative road directly above the generator will remain available. Contractors are permitted to utilize existing load banks on-site rather than providing their own equipment. The document includes photographs of the Automatic Transfer Switch (ASCO) systems located above the portal gate, showing the ASCO Series 300 Automatic Transfer Switch units and internal wiring configurations that were not visible during the site visit.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Emergency Generator Site Visit QNA
1. What are the Generator Serial Numbers?
NV SRF Building: HIMOINSA (HFW-290-T6) NV Visitor Center: 1250 KW ONAN (1250DFLC75207L) NV Lower Portal Road: KATO LITE (L10FJW4) AZ Portable Unit: 35 KW ONAN (DGBB-5006900) NV Gantry Crane: KOHLER (80ROZ271) AZ Gantry Crane: KOHLER (80ROZ271)
2. What Equipment Accessibility and Estimated Load Bank Cable Lengths are required for testing?
Estimated to be 75 feet or less
3. Are there any site access restrictions that could impact maintenance or load bank testing activities?
For Generators 3 – 6 the maximum vehicle weight to access this units is 20 tons and maximum width is 9 feet
4. Will personnel be escorted or provided badges to do maintenance?
Personnel will be escorted by a BOR staff member
5. When testing at the SRF Building, will contractors be able to access the dirt road to get to the generator?
Construction to remove temporary buildings on the SRF dirt road would potentially block access, however road directly above the generator will be available to access.
6. Will the contractor be able to use the present load banks already present for testing or need to provide their own?
Contractors will be able to use the present load banks for testing.
7. Provided are the pictures of the ATS above the portal gate not shown on the site visit: