This document provides an amendment to a solicitation for the purchase of a small dredge. The amendment clarifies specifications for the dredge, including allowing a standard semi-trailer connection for transport and confirming that spuds would be an acceptable propulsion system. It also responds to questions from potential offerors by specifying that pipe floats are not required for the discharge pipe and no new questions will be accepted, only those pertaining to the amendment. The acknowledgement of this amendment must be received by the date and time for receipt of quotes, which remains May 12, 2023 at 2:00 p.m. Pacific Daylight Time. The solicitation is being issued by the U.S. Department of the Interior Bureau of Reclamation Lower Colorado Basin to purchase one small hydraulic dredge to assist with maintenance at the Havasu National Wildlife Refuge in Arizona.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140R3023Q0006_Amd_0005.pdf | ||
| 52_204_27_Jun_2023_0005.pdf | ||
| Sol_140R3023Q0006_Amd_0004.pdf | ||
| Sol_140R3023Q0006_Amd_0003.pdf | ||
| Sol_140R3023Q0006_Amd_0002.pdf | ||
| Revised_Attachment_1_-_Statement_of_Work_-_Dredge_0001.pdf | ||
| Sol_140R3023Q0006.pdf | ||
| 140R3023Q0006.pdf | ||
| Attachment_1_-_Statement_of_Work_-_Dredge.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140R3023Q0006 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
Boulder City NV 89005
R30
500 Fir Street Regional Office Lower Colorado Region Bureau of Reclamation
04/28/20230001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
04/13/2023
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Purpose of Amendment. The purpose of this Amendment 0001 is to provide questions and answers submitted in response to this solicitation and provide and updated Statement of
Work.
SEE FOLLOWING PAGE FOR DESCRIPTION OF AMENDMENT
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Nicholas Clements
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Solicitation No. 140R3023Q00006 Page 2 of 2 Amendment 0001
No new questions will be accepted. Only questions/clarifications pertaining to this Amendment will be accepted. Your questions must be submitted via email to Diane Rodriguez at DLRodriguez@usbr.gov by no later than 10:00 a.m. PD on May 2, 2023.
Receipt of Quotes. The date and time for receipt of quotes remains May 12, 20223 at 2:00 p.m. PD.
Acknowledgement. See block 11 of SF 30 of this amendment regarding how to acknowledge this amendment. The acknowledgement must be received at the place designated for receipt of quotes.
The following response are provided to questions submitted in response to this solicitation.
Question 1 - Part 2 Products
2.01 Dredge Salient Characteristics
• 1,000 feet of HDPE discharge pipe, diameter sized appropriately to match the dredge provided.
o The question would be, does this include pipe floats to float the pipe or is this only the discharge pipe? There is no mention of floats anywhere in the spec.
o Can you please amend the spec to clarify this?
Answer: Do not want pipe floats as the pipe that has been specified is fusible HDPE DR17 and not the quick connect floatable pipe.
Question 2 - Part 2 Products
2.01 Dredge Salient Characteristics
• The trailer is spec with a pintle hitch coupling. This is not what is supplied, the standard is a standard semi-trailer connection.
o Can you amend the spec to include the standard semi-trailer connection?
Answer: A standard semi-trailer connection is acceptable.
Question 3 - In the minimum requirements the specifications for the propulsion system appear to refer to a specific patented system. Can you tell me what if any other systems might be considered?
Spuds? Water jets? Any other?
Answer: Specification states:
Self-propulsion System and steering ¿ able to navigate and dredge in minimum 30 inches of water. (30¿ minimum draft)
Dredge shall be self-propelled (non-prop driven and clog free).
Propulsion system must be able to reach down to 22 ft. depth.
Shall be able to operate in self-propelled mode in up to 2.5 knot current.
Propulsion system must be dual speed.
Typically, the dredge would have some sort of arm/mechanism that would ride on the bottom of the riverbed and have some sort of mechanical propulsion system to move the dredge. Spuds would be acceptable as long as they have the means to move/propel the dredge efficiently.
Do not want a cable traversing dredge, and do not want a prop or water jet propelled dredge.
A. As a result of the above, this amendment revises the following.
1. Attachment 1 Statement of Work