Solicitation No.: 140R3019R0016 USGS Building 500

Attachment 1

SPECIFICATIONS

This page left intentionally blank

Bid Documents

Specifications

Bureau of Reclamation

Building 500 Renovation l R16PC00076

March 22, 2019 tsk

Building 500 Renovation TITLE PAGE March 22, 2019 Page 1

SPECIFICATIONS

FOR

U.S. Department of the Interior

Bureau of Reclamation

Lower Colorado Region

Building 500 Renovation l R16PC00076

PREPARED BY

Tate Snyder Kimsey Architects, AIA 314 South Water Street Henderson, Nevada, 89015

DATE

March 22, 2019

Building 500 Renovation TABLE OF CONTENTS March 22, 2019 Page 1

U.S. Department of the Interior Bureau of Reclamation

Lower Colorado Region

BUILDING 500 RENOVATION

Boulder City, Nevada

SPECIFICATION

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 10 00 Summary of Work 01 23 00 Alternates 01 25 00 Product Substitutions 01 26 13 Request for Information (RFI) 01 29 73 Schedule of Values 01 31 00 Coordination and Meetings 01 32 16 Progress Schedule 01 33 00 Submittal Procedures 01 35 16 Alteration Project Procedures 01 40 00 Quality Requirements 01 50 00 Construction Facilities and Temporary Controls 01 60 00 Product Requirements 01 73 00 Execution 01 74 19 Construction and Demolition Waste Management 01 77 00 Closeout Procedures 01 78 00 Closeout Submittals 01 91 13 General Commissioning Requirements

DIVISION 02 - EXISTING CONDITIONS

02 41 19 Selective Building Demolition

DIVISION 05 – METALS

05 12 00 Structural Steel Framing 05 54 00 Cold Formed Metal Framing 05 50 00 Metal Fabrications

DIVISION 06 - WOOD, PLASTICS AND, COMPOSITES

06 11 00 Framing and Sheathing 06 41 00 Architectural Wood Casework

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 21 00 Thermal Insulation 07 54 19 Thermoplastic Membrane Roofing 07 72 33 Roof Hatches 07 84 00 Firestopping 07 92 00 Joint Sealants

DIVISION 08 - OPENINGS

08 12 13 Hollow Metal Frames 08 14 16 Flush Wood Doors 08 31 00 Access Doors

March 22, 2019 Page 2

08 51 13 Aluminum Windows 08 62 00 Unit Skylights 08 71 00 Door Hardware 08 80 00 Glazing

DIVISION 09 - FINISHES

09 21 16 Gypsum Board Assemblies 09 51 00 Suspended Acoustical Ceilings 09 65 00 Resilient Flooring & Base 09 67 23 Resinous Flooring 09 68 00 Carpet 09 77 10 Fiber Reinforced Laminate Panels (FRL) 09 91 00 Painting

DIVISION 10 - SPECIALTIES

10 14 00 Signage 10 44 00 Fire Extinguishers and Cabinets

DIVISION 21 – FIRE SUPPRESSION

21 13 13 Wet-Pipe Sprinkler Systems

DIVISION 22 - PLUMBING

22 01 00 Basic Plumbing Requirements 22 05 00 Common Work Results for Plumbing 22 05 23 General Duty Valves for Plumbing Piping 22 05 29 Hangers and Supports for Plumbing Piping and Equipment 22 05 53 Identification for Plumbing Piping and Equipment 22 07 00 Plumbing Insulation 22 11 16 Domestic Water Piping 22 11 19 Domestic Water Piping Specialties 22 13 16 Sanitary Waste and Vent Piping 22 13 19 Sanitary Waste Piping Specialties 22 40 00 Plumbing Fixtures

DIVISION 23 - HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)

23 01 00 Basic HVAC Requirements 23 05 00 Common Work Results for HVAC 23 05 13 Common Motor Requirements for HVAC Equipment 23 05 19 Meters and Gages for HVAC Piping 23 05 23 General-Duty Valves for HVAC Piping 23 05 29 Hangers and Supports for HVAC Piping and Equipment 23 05 48 Vibration and Isolation Controls for HVAC Piping and Equipment 23 05 49 Seismic Bracing for Mechanical Systems 23 05 53 Identification for HVAC Piping and Equipment 23 05 93 Testing, Adjusting and Balancing for HVAC 23 07 00 HVAC Insulation 23 08 00 Commissioning of HVAC 23 09 00 Instrumentation and Control for HVAC 23 23 00 Refrigerant Piping 23 31 13 Metal Ducts 23 33 00 Air Duct Accessories 23 34 23 HVAC Power Ventilators 23 37 13 Diffusers, Registers and Grilles 23 41 00 Particulate Air Filtration 23 62 00 Packaged Rooftop Gas Heat Electric Cooling Units 23 81 19 Split System/Self-Contained Air Conditioning Units 23 82 39 Unit Heaters

March 22, 2019 Page 3

DIVISION 26 - ELECTRICAL

26 01 00 Basic Electrical Requirements 26 05 10 Electrical Demolition 26 05 19 Low-Voltage Electrical Power Conductors and Cables 26 05 26 Grounding and Bonding for Electrical Systems 26 05 29 Hangers and Supports for Electrical Systems 26 05 33 Raceways and Boxes for Electrical Systems 26 05 44 Sleeves and Sleeve Seals for Electrical Raceways and Cabling 26 05 48 Vibration and Seismic Controls for Electrical Systems 26 05 53 Identification for Electrical Systems 26 05 72 Short-Circuit Study 26 05 73 Coordination Study 26 05 74 Arc-Flash Study Analysis 26 08 00 Commissioning of Electrical Systems 26 09 23 Lighting Control Devices 26 12 19 Pad-Mounted, Liquid-Filled, Medium-Voltage Transformers 26 24 13 Switchboards 26 24 16 Panelboards 26 27 13 Electricity Metering 26 27 26 Wiring Devices 26 28 13 Fuses 26 51 19 LED Interior Lighting 26 56 19 LED Exterior Lighting

DIVISION 27 - COMMUNICATIONS

27 00 00 Communications General Requirements 27 05 28 Pathways for Communications Systems 27 11 00 Communications Equipment Room Fittings 27 15 00 Communications Horizontal Cabling

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 31 11 Digital, Addressable Fire-Alarm System

DIVISION 31 – EARTHWORK

31 23 16.26 Rock Caliche Removal 31 23 17 Trenching 31 23 23 Backfilling

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 01 16 Asphalt Paving 32 17 23 Pavement Markings

DIVISION 33 – UTILITIES

33 11 00 Water Systems 33 13 00 Disinfection of Water Systems

END OF TABLE OF CONTENTS

Building 500 Renovation SUMMARY OF WORK March 22, 2019 01 10 00 Page 1

SECTION 01 10 00

SUMMARY OF WORK

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Contract Description.

B. Contractor's Use of Site

C. Specification Conventions.

1.2 CONTRACT DESCRIPTION

A. The project includes the renovation of a roughly 14,520 square feet free standing single story building for the Bureau of Reclamation, 1200 Park Street, Boulder City, Nevada 89005. The renovated building will house USGS Administrative offices, storage, and restrooms.

B. As noted on the drawings and specified herein, the project generally includes work entire Building 500, roofing upgrade, mechanical unit replacement and electrical upgrades.

C. The entire building will be vacated for the duration of construction.

D. Contract: Perform Work under a single prime, lump sum contract, including labor, equipment, materials, and services required for the completion of the project.

1.3 CONTRACTOR'S USE OF SITE

A. Limit use of site to allow work by public utilities and use of existing adjacent facilities by the public.

B. Construction operations shall be limited to areas noted on drawings.

C. Maintain fire lanes required by local Fire Department and other access routes required.

D. Allow Government to perform Work by Others.

E. Maintain emergency exits from existing building during construction.

F. Utility Outages and Shutdown: Provide three (3) days notice of scheduled shutdowns and immediate notification of unscheduled utility interruptions to site.

G. Provide temporary construction fence to enclose each portion of Work for the protection of personnel using the facility.

H. The existing site and parking lots are off limits for any staging, storage of materials, contractor's parking and any other activities related to the Project except those areas noted on the drawings.

I. Submit a coordination plan for all Work for review and approval by the Contracting Officer (CO).

J. In cooperation with the appropriate trades, General Contractor shall prepare and submit a phasing plan for the Mechanical, Electrical and Plumbing work for review and approval by the CO prior to start of Work.

Building 500 Renovation SUMMARY OF WORK March 22, 2019 01 10 00 Page 2

K. Coordinate this Work so as not to interfere with the operation of the existing site and facility.

L. Abide by additional access restrictions in specific areas during specific times noted in Work Sequence and Milestone portion of this Section.

1.4 SPECIFICATION CONVENTIONS

A. These specifications are written in imperative mood and streamlined form. This imperative language is directed to the Contractor, unless specifically noted otherwise. The words “shall be” are included by inference where a colon (:) is used within sentences or phrases.

PART 2 - PRODUCTS - Not Used

PART 3 - EXECUTION - Not Used

END OF SECTION

Building 500 Renovation ALTERNATES March 22, 2019 01 23 00 Page 1

SECTION 01 23 00

ALTERNATES

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Submission procedures for Alternate items of Work as included in this Section.

B. Documentation of changes to Contract Sum and Contract Time

1.2 REQUIREMENTS

A. Alternates quoted on Bid Forms will be reviewed and accepted or rejected at Owner’s option.

B. Accepted alternates will be identified in the awarded contract.

C. Coordinate related Work and modify surrounding Work to integrate the Work of each alternate.

1.3 SELECTION AND AWARD OF ALTERNATES

A. Indicate lump sum for alternates, described below and list each alternate in the Bid Form Document.

B. The successful Bidder will be determined on base bid sum, including none or any combination of Alternates, whichever is in the best interest of the Owner.

1.4 SCHEDULE OF ALTERNATES

A. The alternates described below shall include the cost of all labor, materials, supervision and equipment required to accomplish the work as indicated in the plans and specifications.

B. Additive Alternate No. 500-1: Translucent Skylights, Flashing and Opening Reinforcement.

1. Base Bid Item: Provide roof to match project requirements in space of skylights.

2. Alternate Bid Item: Provide unit skylights specified in Section 08 62 00 in locations shown on drawings.

C. Additive Alternate No. 500-2: Window Opening as shown on drawings.

1. Base Bid Item: No additional work required under this Alternate.

2. Alternate Bid Item: Provide new aluminum windows as specified in Section 08 51 13 and shown on drawings. Patch, flash, and finish to match adjacent wall finish.

D. Additive Alternate No. 500-3: Exterior Painting of Building.

1. Base Bid Item: No additional work required under this Alternate.

2. Alternate Bid Item: Prepare surfaces and paint exterior of building as shown on drawings and specified in Section 09 91 00 - Painting.

Building 500 Renovation ALTERNATES March 22, 2019 01 23 00 Page 2

PART 2 - PRODUCTS – Not Used

PART 3 - EXECUTION – Not Used

Building 500 Renovation PRODUCT SUBSTITUTIONS March 22, 2019 01 25 00 Page 1

SECTION 01 25 00

PRODUCT SUBSTITUTIONS

1.1 SECTION INCLUDES

A. Contractor’s selection of products

B. Requests for substitution of products

1.2 SELECTION OF PRODUCTS

A. For products specified by naming only one manufacturer, that manufacturer is to be included in the base bid.

B. For products specified by naming more than one manufacturer, any of the listed manufacturers of that section may be used in the base bid.

C. When product or manufacturer’s names are not specifically specified, provide products, materials, or systems in strict accord with performance requirements and install such products in strict accordance with the material manufacturer’s recommendations.

D. "Or Equal"

1. Where the phrase “or equal” or “or approved equal” occurs in the project manual, do not assume that the products, materials, or system will be approved as equal until the item has been specifically so approved for this work by the CO.

2. Approval or rejection of a request for an “or equal” will be based on the recommendation of the Contracting Officer’s Representative (COR) as concurred by the CO, to the adaptability, durability, and quality compared to the specified or noted items.

3. The decision of the CO shall be final.

E. Subsequent request for Substitutions will be considered in case of product unavailability.

1. Submit a letter to this effect written by the manufacturer. If, in the opinion of the CO, any product specified cannot be delivered during the progress of the Work.

2. Approval, or rejection, of a request for a “Substitution” will be based on the recommendation of the Engineer as concurred by the CO to adaptability, durability, and quality compared to the specified or noted items.

3. For accepted products, submit shop drawings, product data, and samples under provisions of Division 1.

Building 500 Renovation REQUEST FOR INFORMATION March 22, 2019 01 26 13 Page 1

SECTION 01 26 13

REQUEST FOR INFORMATION (RFI)

1.1 SECTION INCLUDES

A. Administrative requirements for Request for Information.

1.2 CONTRACTOR’S REQUEST FOR INFORMATION

A. When the Contractor is unable to determine the material, process or system to be installed, a clarification shall be requested through the Contracting Officer’s Representative (COR).

B. All RFIs shall be originated by the Contractor.

1. RFIs from subcontractors or material suppliers shall be submitted through, reviewed by, and signed by the Contractor prior to submittal to the COR.

2. RFIs sent by a subcontractor or material supplier directly to the COR’s consultants shall not be accepted and will be returned unanswered.

C. Contractor shall carefully study the Contract Documents to assure that the requested information is not available therein. RFIs which request information available in the Contract Documents will be deemed “frivolous”.

D. In cases where RFIs are issued to request clarification of coordination issues, for example, pipe and duct routing, clearances, specific locations of work shown diagrammatically and similar items the Contractor shall fully lay out a suggested solution using drawings or sketches drawn to scale and submit same with the RFI. RFIs which fail to include a suggested solution will be returned unanswered with a requirement that the Contractor submit a complete request.

E. RFIs shall not be used for the following purposes:

1. To request approval of submittals.

2. To request approval of substitutions.

3. To request changes which entail additional cost or credit.

4. To request methods of performing work different than those shown or specified.

F. Frivolous RFIs: RFIs that request information that is clearly shown on the Contract Documents may be returned unanswered.

G. RFIs shall be submitted in a format acceptable to the CO. This format shall be utilized throughout the course of the Work.

H. The Contractor shall prepare and maintain a log of RFIs. Upon request by the CO or COR, the Contractor shall furnish copies of the log showing outstanding RFIs. The Contractor shall note unanswered RFIs in the log.

1.3 CO/COR RESPONSE TO RFIs

A. Contractor shall allow 14 days for the COR’s review and response time for RFIs, after receipt at CO’s office. However, the COR will endeavor to respond in less time. If additional time is required beyond the 14 days allowed, the COR will notify the Contractor in writing.

Building 500 Renovation REQUEST FOR INFORMATION March 22, 2019 01 26 13 Page 2

B. Responses from the CO will not change any requirement of the Contract Documents unless so noted by the CO in the response to the RFI.

1. In the event the Contractor believes that a response to a RFI will cause a change to the requirements of the Contract Documents, the Contractor shall immediately give written notice to the CO stating that the Contractor considers the response to be a Change Order.

2. Answered RFIs shall not be construed as approval to perform extra work.

PART 2 - PRODUCTS

NOT USED

PART 3 - EXECUTION

NOT USED

Building 500 Renovation SCHEDULE OF VALUES March 22, 2019 01 29 73 Page 1

SECTION 01 29 73

SCHEDULE OF VALUES

1.1 SECTION INCLUDES

A. Format

B. Schedule of Values

C. Updating Schedule of Values

D. Submittals

1.2 FORMAT

A. The Schedule of Values shall be submitted on the AIA Form G703 or Contractor's electronic media driven form in the same format as the AIA forms will be considered.

B. The Schedule of Values shall separate values of the work by phases and by CSI Division and Section as applicable. Use the Specifications Table of Contents as a guide to establish the format for the Schedule of Values.

C. Coordinate preparation of the Schedule of Values with preparation of the Contractor’s

Construction Schedule and the Contract Cost Breakdown.

1.3 SCHEDULE OF VALUES

A. The Contractor shall submit a detailed Schedule of Values. The approved Schedule of Values shall be used as a basis for reviewing the Contractor’s Applications for Payment.

B. The Schedule of Values shall separate values of the work by phases and by CSI Division and Section as applicable, aggregating the total Contract Sum, divided so as to facilitate payments to subcontractors and materials suppliers in accordance with the project requirements.

C. Each item in the Schedule of Values shall be complete, including its total cost and its proper share of overhead and profit.

D. Provide a breakdown of the Contract Sum in sufficient detail to facilitate continued evaluation of Applications for Payment and progress reports. Break principal subcontract amounts down into several line items. Round amounts off to the nearest whole dollar; the total shall equal the Contract Sum.

E. For each part of the Work where an Application for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed, provide separate line items on the Schedule of Values for cost of the materials, and for subsequent installation costs for the materials.

1.4 UPDATING SCHEDULE OF VALUES

A. Update and resubmit the Schedule of Values when Contract Change Orders result in a change in the total Contract Sum.

Building 500 Renovation SCHEDULE OF VALUES March 22, 2019 01 29 73 Page 2

1.5 SUBMITTALS

A. Submit Schedule of Values to Contracting Officer (CO) for approval at the preconstruction meeting.

B. After review by CO, revise and resubmit, if required, within ten (10) days after the preconstruction meeting, incorporating all comments from the joint review.

PART 2 - PRODUCTS

Not Used

Not Used

Building 500 Renovation COORDINATION AND MEETINGS March 22, 2019 01 31 00 Page 1

SECTION 01 31 00

COORDINATION AND MEETINGS

1.1 SECTION INCLUDES

A. Coordination and project conditions.

B. Site mobilization meeting.

C. Progress meetings.

D. Pre-installation meetings.

1.2 COORDINATION AND PROJECT CONDITIONS

A. Coordinate scheduling, submittals, and Work of various sections of Contract Specifications to ensure efficient and orderly sequence of installation of interdependent construction elements.

B. Verify utility requirements and characteristics of operating equipment are compatible with building utilities. Coordinate work of various sections having interdependent responsibilities for installing, connecting to, and placing in service, operating equipment.

C. Coordinate space requirements, supports, and installation of mechanical and electrical work indicated diagrammatically on Drawings. Follow routing shown for pipes, ducts, and conduit, as closely as practicable; place runs parallel with lines of building. Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs.

D. In finished areas except as otherwise indicated, conceal pipes, ducts, and wiring within construction. Coordinate locations of fixtures and outlets with finish elements.

E. Coordinate completion and clean-up of work of separate sections in preparation for Substantial Completion.

F. After Owner occupancy of premises, coordinate access to site for correction of defective work and work not in accordance with Contract Documents, to minimize disruption of Owner's activities.

1.3 SITE MOBILIZATION MEETING

A. CO will schedule meeting at Project site prior to Contractor occupancy.

B. Attendance Required: CO, COR, soils testing agency, Contractor, Contractor's Superintendent, and earthwork and other major Subcontractors.

C. Agenda:

1. Use of premises by Owner and Contractor.

2. Government’s requirements.

3. Construction facilities and controls.

4. Temporary utilities.

5. Survey and building layout.

6. Security and housekeeping procedures.

7. Schedules.

March 22, 2019 01 31 00 Page 2

8. Application for payment procedures.

9. Procedures for testing.

10. Procedures for maintaining record documents.

11. Requirements for start-up of equipment.

12. Inspection and acceptance of equipment put into service during construction period.

D. CO will record minutes and distribute copies.

1.4 PROGRESS MEETINGS

A. Schedule and administer meetings throughout progress of the Work at maximum bi-monthly intervals.

B. Make arrangements for meetings, prepare agenda with copies for participants, preside at meetings.

C. Attendance Required: Job superintendent, major subcontractors and suppliers, Contracting Officer or Contracting Officers Representation (COR).

D. Agenda:

1. Review minutes of previous meetings.

2. Review of Work progress.

3. Field observations, problems, and decisions.

4. Identification of problems impeding planned progress.

5. Review of submittals schedule and status of submittals.

6. Review of off-site fabrication and delivery schedules.

7. Maintenance of progress schedule.

8. Corrective measures to regain projected schedules.

9. Planned progress during succeeding work period.

10. Coordination of projected progress.

11. Maintenance of quality and work standards.

12. Effect of proposed changes on progress schedule and coordination.

13. Other business relating to Work.

E. Record minutes and distribute copies.

1.5 PRE-INSTALLATION MEETINGS

A. When required in individual specification sections, convene pre-installation meetings at Project site prior to commencing work of specific section.

B. Require attendance of parties directly affecting, or affected by, Work of specific section.

C. Notify CO/COR five (5) days in advance of meeting date.

D. Prepare agenda and preside at meeting:

1. Review conditions of installation, preparation and installation procedures.

2. Review coordination with related work.

E. Record minutes and distribute copies.

PART 2 - PRODUCTS

March 22, 2019 01 31 00 Page 3

Building 500 Renovation PROGRESS SCHEDULE March 22, 2019 01 32 16 Page 1

SECTION 01 32 16

PROGRESS SCHEDULE

1.1 SECTION INCLUDES

A. Format.

B. Content.

C. Revisions to schedules.

D. Submittals.

1.2 RELATED SECTIONS

A. Section 01 10 00 - Summary of Work.

B. Section 01 26 00 - Change Order Procedures.

C. Section 01 29 73 - Schedule of Values

D. Section 01 29 76 - Applications for Payment.

E. Section 01 33 00 - Submittal Procedures.

1.3 FORMAT

A. Prepare schedule as a horizontal bar chart with separate bar for each major portion of Work or operation, or a computer generated network analysis using the critical path method, identifying first work day of each week.

B. Sequence of Listings: The chronological order of the start of each item of Work.

C. Scale and Spacing: To provide space for notations and revisions.

1.4 CONTENT

A. Show complete sequence of construction by activity, with dates for beginning and completion of each element of construction.

B. Identify each item by specification section number.

C. Identify work of logically grouped activities.

D. Show accumulated percentage of completion of each item, and total percentage of Work completed, as of the first day of each month.

E. Provide separate schedule of submittal dates for shop drawings, product data, and samples.

F. Coordinate content with schedule of values specified in Section 01 29 73.

Building 500 Renovation PROGRESS SCHEDULE March 22, 2019 01 32 16 Page 2

1.5 REVISIONS TO SCHEDULES

A. Indicate progress of each activity to date of submittal, and projected completion date of each activity.

B. Identify activities modified since previous submittal, major changes in scope, and other identifiable changes.

1.6 SUBMITTALS

A. Submit preliminary outline Schedules at the time of the Preconstruction Meeting for coordination with Contracting Officer (CO)’s requirements.

B. After review, submit detailed schedules within 15 days modified to accommodate revisions recommended by CO.

C. Submit revised Progress Schedules with each Application for Payment.

1.7 DISTRIBUTION

A. Distribute copies of reviewed schedules to Project site file, Subcontractors, suppliers, and other concerned parties.

B. Instruct recipients to promptly report, in writing, problems anticipated by projections indicated in schedules.

Building 500 Renovation SUBMITTAL PROCEDURES March 22, 2019 01 33 00 Page 1

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Submittal schedule

B. Format

C. Contractor's Actions

D. Contracting Officers Representative (COR) Actions

E. Product data.

F. Shop drawings.

G. Samples.

H. Manufacturer's instructions.

1.2 SUBMITTAL SCHEDULE

A. Within 30 days after date of Notice to Proceed, submit a Submittal Schedule showing the Specification reference of the submittal, the type of submittal such as shop drawings, samples, product data, and the proposed submittal date coordinated with and reflecting the requirements of the Progress Schedule.

B. All submittals to be delivered to the Contracting Officers Representative (COR) within 60 calendar days after the Pre-Construction Conference. Coordinate submission of related items.

C. Within 15 days after date of Notice to Proceed, submit list of major products proposed for use, with name of manufacturer, trade name, and model number of each product.

D. For products specified only by reference standards, give manufacturer, trade name, model or catalog designation, and reference standards.

1.3 FORMAT

A. Transmit each submittal on a form approved by the COR.

B. Each transmittal form shall include the Contract Number and Title.

C. Number transmittal forms with the Specification Section number for the submittal followed by a dash and sequential number for that specification number.

D. Mark revised submittals with original number and sequential alphabetic suffix and identify as a re-submittal. All requirements for submittals apply to re-submittals.

E. Identify Project, Contractor, subcontractor and supplier; pertinent drawing and detail number, and specification section number, appropriate to each submittal.

March 22, 2019 01 33 00 Page 2

F. Submittals shall be prepared in English.

1.4 CONTRACTORS ACTIONS

A. No portion of the Work which requires a submittal shall be commenced until the submission has been reviewed and returned as approved or noted by the COR.

B. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of products required, field dimensions, adjacent construction work, and coordination of information is in accordance with requirements of the Work and Contract Documents.

C. Contractor shall not use or allow to be used any Contract Document as a submittal.

D. Schedule submittals for allowance of full review period by the COR and to expedite the Work of the Project. Deliver to COR at business address or in electronic format. Coordinate submission of related items.

E. Identify variations from Contract Documents and product or system limitations which may be detrimental to successful performance of completed Work.

F. Allow space on submittals for Contractor and reviewing entity review stamps.

G. When revised for resubmission, identify changes made since previous submission.

H. Distribute copies of reviewed submittals as appropriate. Instruct parties to promptly report inability to comply with requirements.

I. Maintain one set of accepted submittals for delivery to the COR upon completion of the project.

1.5 CONTRACTING OFFICERS REPRESENTATIVE (COR) ACTIONS

A. Contracting Officers Representative (COR) will review shop drawings, product data, and samples. COR with return submittals to the Contractor.

B. Contractor is to schedule his submittals so that the COR has fourteen (14) calendar days after receipt at COR’s office to review them.

C. Should more time be required for evaluation, coordination, and review, the Contractor will be so notified.

D. Extension of review time shall not constitute a basis to automatically extend the Contract Time.

E. The Contractor shall make any corrections required by the COR and, if resubmittal is required, shall resubmit the required number of corrected copies of shop drawings or new samples.

F. The Contractor shall direct specific attention in writing or on resubmitted shop drawings to revisions other than the correction required by the COR on previous submissions.

G. Submittals not requested will not be recognized or processed.

1.6 PRODUCT DATA

A. Submit one electronic copy in Adobe PDF format of each sheet. COR will return one copy to Contractor for printing and distribution.

March 22, 2019 01 33 00 Page 3

B. Submit Product Data to COR for review for limited purpose of checking for conformance with information given and design concept expressed in Contract Documents.

C. Submit only pages, which are pertinent.

1. Mark each copy of standard printed data to identify pertinent products, referenced to

Specification Section and Article number. Mark item to be furnished in a manner that will photocopy (no highlighter).

2. Show reference standards, performance characteristics, and capacities; wiring and piping diagrams and controls; component parts; finishes; dimensions; and required clearances.

D. Modify manufacturer’s standard schematic drawings and diagrams to supplement standard information and to provide information specifically applicable to the Work. Delete information not applicable.

1.7 SHOP DRAWINGS

A. Submit one electronic copy in Adobe PDF format of each sheet. COR will return one copy to Contractor for printing and distribution.

B. Present in a clear and thorough manner.

C. Title each drawing with Contract Number and Project name. Identify each element of drawings by reference to sheet number and detail, schedule, or room number of Contract Documents.

1. Identify field dimensions; show relation to adjacent or critical features or work or products.

2. Unless otherwise specifically directed by the COR, make all shop drawings accurate to a scale sufficiently large to show all pertinent features of the item and its methods of connection to the Work.

3. Indicate special utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.

D. When required by individual specification sections, provide shop drawings signed and sealed by professional engineer responsible for designing components shown on shop drawings.

1. Include signed and sealed calculations to support design.

2. Submit drawings and calculations in form suitable for submission to and approval by authorities having jurisdiction.

3. Make revisions and provide additional information when required by authorities having jurisdiction.

1.8 SAMPLES

A. Submit required Samples to COR for review for limited purpose of checking for conformance with information given and design concept expressed in Contract Documents.

B. Samples for Selection as Specified in Product Sections:

1. Submit to COR for color, or finish selection.

2. Submit samples of finishes as required by the individual sections of these specifications.

C. Submit samples to illustrate functional characteristics of Products, with integral parts and attachment devices. Coordinate sample submittals for interfacing work.

D. Include identification on each sample with full Contract Number and Project Name.

E. Submit number of samples specified in individual specification sections.

March 22, 2019 01 33 00 Page 4

F. One set of approved samples shall be maintained at the Project Site which will serve as the standard by which all representative Work performed will be judged.

G. Reviewed samples which may be used in the Work are indicated in individual specification sections.

1.9 MANUFACTURER'S INSTRUCTIONS

A. When specified in individual specification sections, submit printed instructions for delivery, storage, assembly, installation, start-up, adjusting, and finishing, to COR in quantities specified for Product Data.

B. Indicate special procedures, perimeter conditions requiring special attention, and special environmental criteria required for application or installation.

PART 2 - PRODUCTS

Not Used

PART 3 - EXECUTION

Building 500 Renovation ALTERATION PROJECT PROCEDURES March 22, 2019 01 35 16 Page 1

SECTION 01 35 16

ALTERATION OF EXISTING CONSTRUCTION

1.1 SECTION INCLUDES

A. Products and installation for patching and extending Work.

B. Transition and adjustments.

C. Repair of damaged surfaces, finishes, and cleaning.

PART 2 - PRODUCTS

2.1 PRODUCTS FOR PATCHING AND EXTENDING WORK

A. New Materials: As specified in product sections; match existing Products and work for patching and extending work.

B. Type and Quality of Existing Products: Determine by inspecting and testing products where necessary, referring to existing work as a standard.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify that demolition is complete and areas are ready for installation of new work.

B. Coordinate work of this section with requirements of Section 01 73 00 - Execution and Section 02

41 19 - Selective Building Demolition.

3.2 PREPARATION

A. Cut, move, or remove items as necessary for access to alterations and renovation work. Replace and restore at completion.

B. Remove unsuitable material not marked for salvage, such as corroded metals, and deteriorated masonry and concrete. Replace materials as specified for finished work.

C. Remove debris and abandoned items from area and from concealed spaces.

D. Prepare surface and remove surface finishes to provide for proper installation of new work and finishes.

E. Close openings in exterior surfaces to protect existing work from weather and extremes of temperature, humidity, and rodents. Insulate ductwork and piping to prevent condensation in exposed areas.

3.3 INSTALLATION

A. Coordinate work of alterations and renovations with new construction.

Building 500 Renovation ALTERATION PROJECT PROCEDURES March 22, 2019 01 35 16 Page 2

B. Remove, cut, and patch Work in a manner to minimize damage and to provide a means of restoring products and finishes to specified condition.

C. Refinish visible existing surfaces to remain in renovated rooms and spaces, to specified condition for each material, with a neat transition to adjacent finishes.

D. Recover and refinish work that exposes mechanical and electrical work exposed accidently during the work.

E. Install products as specified in individual sections.

3.4 TRANSITIONS

A. Where new work abuts or aligns with existing, perform a smooth and even transition. Patch work to match existing adjacent Work in texture and appearance.

B. When finished surfaces are cut so that a smooth transition with new work is not possible, terminate existing surface along a straight line at a natural line of division and make recommendation to Contracting Officer’s Representative (COR).

3.5 ADJUSTMENTS

A. Where removal of partitions or walls results in adjacent spaces becoming one, rework floors, walls, and ceilings to a smooth plane without breaks, steps, or bulkheads.

B. Where a change of plane of 1/4 inch or more occurs, request instructions from the CO.

C. Trim existing doors as necessary to clear new floor finish. Refinish trim as required.

3.6 REPAIR OF DAMAGED SURFACES

A. Patch or replace portions of existing surfaces which are damaged, lifted, discolored, or showing other imperfections.

B. Repair substrate prior to patching finish.

3.7 FINISHES

A. Finish surfaces as specified in individual product sections.

B. Finish patches to produce uniform finish and texture over entire area. When finish cannot be matched, refinish entire surface to nearest intersections.

3.8 CLEANING

A. In addition to cleaning of this project, clean Owner occupied areas of work immediately adjacent to renovation area and any other Owner occupied areas affected by renovation work.

Building 500 Renovation QUALITY REQUIREMENTS March 22, 2019 01 40 00 Page 1

SECTION 01 40 00

QUALITY REQUIREMENTS

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. References.

B. Quality control and control of installation.

C. Tolerances.

D. Labeling.

E. Mock-up requirements.

F. Design data and calculations.

G. Test reports and certifications.

H. Manufacturer's installation instructions.

I. Manufacturer's field services.

J. Testing and inspection services.

1.2 REFERENCES

A. For products or workmanship specified by association, trade, or other consensus standards, comply with requirements of standard, except when more rigid requirements are specified or are required by applicable codes.

B. Conform to reference standard by date of issue current on date of Contract Documents except where specific date is established by code.

C. Obtain copies of standards where required by product specification sections.

D. When specified reference standards conflict with Contract Documents, request clarification from Contracting Officer (CO) before proceeding.

1.3 QUALITY CONTROL AND CONTROL OF INSTALLATION

A. Monitor quality control over suppliers, manufacturers, products, services, site conditions, and workmanship, to produce work of specified quality.

B. Comply with manufacturers' instructions, including each step in sequence.

C. When manufacturers' instructions conflict with Contract Documents, request clarification from COR before proceeding.

D. Comply with specified standards as minimum quality for the Work except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.

March 22, 2019 01 40 00 Page 2

E. Perform Work by persons qualified to produce required and specified quality.

F. Verify field measurements are as indicated on Shop Drawings or as instructed by manufacturer.

G. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, or disfigurement.

1.4 TOLERANCES

A. Monitor fabrication and installation tolerance control of products. Do not permit tolerances to accumulate.

B. Comply with manufacturers' tolerances. When manufacturers' tolerances conflict with Contract Documents, request clarification from COR before proceeding.

C. Adjust products to appropriate dimensions; position before securing products in place.

1.5 LABELING

A. Attach label from agency approved by authority having jurisdiction for products, assemblies, and systems required to be labeled by applicable code.

B. Label Information: Include manufacturer's or fabricator's identification, approved agency identification, and the following information, as applicable, on each label.

1. Model number.

2. Serial number.

3. Performance characteristics.

1.6 MOCKUPS

A. Definition:

1. Mockups are field samples constructed, applied, or assembled at the project site for review by the COR that illustrate materials, equipment, or workmanship.

2. Approved mockups establish the standard of quality by which the Work will be judged.

B. Construct, apply, or assemble specified items, with related attachment and anchorage devices, flashings, seals, and finishes.

C. Perform work in accordance with applicable specifications sections.

D. Erect at project site at location acceptable to COR. Protect from damage.

E. Removal:

1. Mockups may remain as part of the Work only when so designated in individual specification sections.

2. Do not remove mockups until removal is approved by COR or upon Final Completion.

3. Where mockup is not permitted to remain as part of the Work, clear area after removal of mockup has been approved by COR.

1.7 DESIGN DATA AND CALCULATIONS

A. When specified in individual specification Sections, require material or Product suppliers or manufacturers to provide design data and calculations.

B. Accuracy of design data and calculations is the responsibility of the Contractor.

March 22, 2019 01 40 00 Page 3

C. When so specified, prepare design data and calculations under the direction of a professional engineer licensed in the state in which the Project is located. Affix engineer’s seal to submittals.

1.8 TEST REPORTS AND CERTIFICATIONS

A. When specified in individual specification sections, require material or product suppliers or manufacturers to provide test reports and manufacturers’ certifications.

B. Indicate that material or product conforms to or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.

C. Submittals may be recent or previous test results on material or product, but must be acceptable to (COR).

1.9 MANUFACTURERS' FIELD SERVICES

A. When specified in individual specification sections, require material or product suppliers or manufacturers to provide qualified staff personnel to observe site conditions, conditions of surfaces and installation, quality of workmanship, start-up of equipment, test, adjust and balance of equipment and commissioning as applicable, and to initiate instructions when necessary.

B. Report observations and site decisions or instructions given to applicators or installers that are supplemental or contrary to manufacturers' written instructions.

1.10 MANUFACTURER'S INSTALLATION INSTRUCTIONS

A. When Contract Documents require that products be installed in accordance with manufacturer's instructions:

1. Submit manufacturer's most recent printed instructions for delivery, storage, assembly, installation, start-up, adjusting, and finishing, as applicable.

a. Submit in quantities specified for Product Data.

b. Indicate special procedures, perimeter conditions requiring special attention, and special environmental criteria required for application or installation.

c. Identify conflicts between manufacturers' instructions and requirements of

Contract Documents.

2. Perform installation of products to comply with requirements of manufacturer's instructions.

3. If installation cannot be performed in accordance with manufacturer's instructions, notify

CO and await instructions.

1.11 TESTING AND INSPECTION SERVICES

A. Contractor shall employ and pay for specified services of an independent firm to perform testing and inspection.

B. The independent firm will perform tests, inspections and other services specified in individual specification sections and required by International Building Code.

1. Laboratory: Authorized to operate in State of Nevada.

2. Laboratory Staff: Maintain full time registered Engineer on staff to review services.

3. Testing Equipment: Calibrated at reasonable intervals with devices of an accuracy traceable to National Bureau of Standards or accepted values of natural physical constants.

C. Testing, inspections and source quality control may occur on or off project site.

March 22, 2019 01 40 00 Page 4

D. Reports will be submitted by independent firm to CO and COR, Contractor, and authority having jurisdiction, indicating observations and results of tests and indicating compliance or non-compliance with Contract Documents.

1. Submit final report indicating correction of work previously reported as non-compliant.

E. Cooperate with independent firm; furnish samples of materials, design mix, equipment, tools, storage, safe access, and assistance by incidental labor as requested.

1. Notify COR and independent firm 2 working days prior to expected time for operations requiring services.

2. Make arrangements with independent firm and pay for additional samples and tests required for Contractor's use.

F. Testing and employment of testing agency or laboratory shall not relieve Contractor of obligation to perform Work in accordance with requirements of the Contract Documents.

G. Re-testing or re-inspection required because of non-conformance to specified requirements shall be performed by same independent firm as requested by the COR. The Contractor shall be responsible for any and all costs for re-testing or re-inspection.

H. Agency Responsibilities:

1. Test samples of mixes submitted by Contractor.

2. Provide qualified personnel at site. Cooperate with COR and Contractor in performance of services.

3. Perform specified sampling and testing of products in accordance with specified standards.

4. Ascertain compliance of materials and mixes with requirements of Contract Documents.

5. Promptly notify COR and Contractor of observed irregularities or non-conformance of

Work or products.

6. Perform additional tests required by COR.

I. Agency Reports: After each test, promptly submit report to COR, Contractor, and authority having jurisdiction. When requested by COR, provide interpretation of test results. Include the following:

1. Date issued.

2. Project title and number.

3. Name of inspector.

4. Date and time of sampling or inspection.

5. Identification of product and specifications section.

6. Location in Project.

7. Type of inspection or test.

8. Date of test.

9. Results of tests.

10. Conformance with Contract Documents.

J. Limits on Testing Authority:

1. Agency or laboratory may not release, revoke, alter, or enlarge on requirements of

Contract Documents.

2. Agency or laboratory may not approve or accept any portion of the Work.

3. Agency or laboratory may not assume duties of Contractor.

4. Agency or laboratory has no authority to stop the Work.

March 22, 2019 01 40 00 Page 5

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify existing site conditions and substrate surfaces are acceptable for subsequent work.

Beginning new work means acceptance of existing conditions.

B. Verify existing substrate is capable of structural support or attachment of new work being applied or attached.

C. Examine and verify specific conditions described in individual specification sections.

D. Verify utility services are available, of correct characteristics, and in correct locations.

3.2 PREPARATION

A. Clean substrate surfaces prior to applying next material or substance.

B. Seal cracks or openings of substrate prior to applying next material or substance.

C. Apply manufacturer required or recommended substrate primer, sealer, or conditioner prior to applying new material or substance in contact or bond.

Building 500 Renovation CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS March 22, 2019 01500 Page 1

SECTION 01 50 00

CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

1.1 SECTION INCLUDES

A. Temporary Utilities: Electricity, lighting, ventilation, telephone service, water, and sanitary facilities.

B. Temporary Controls: Barriers, enclosures and fencing, protection of the Work, and water control.

C. Construction Facilities: Parking, progress cleaning and temporary field offices and storage.

1.2 TEMPORARY ELECTRICITY

A. Cost: By Government, connect to Government's existing power service where designated on the drawings.

B. Do no disrupt Government's need for continuous service.

C. Provide power outlets for construction operations, with branch wiring and distribution boxes located as required.

D. Provide separate generators or other power source for equipment with special power require-ments not available from the Government's existing service.

1.3 TEMPORARY LIGHTING FOR CONSTRUCTION PURPOSES

A. Provide and maintain lighting for construction operations.

B. Provide branch wiring from power source to distribution boxes with lighting conductors, pigtails, and lamps as required.

C. Maintain lighting and provide routine repairs.

D. Permanent building lighting may be utilized during construction.

1.4 TEMPORARY VENTILATION

A. Ventilate enclosed areas to assist cure of materials, to dissipate humidity, and to prevent accumulation of dust, fumes, vapors, or gases.

1.5 TELEPHONE SERVICE

A. Provide, maintain and pay for telephone service to field office at time of project mobilization.

B. Provide, maintain and pay for separate DSL service to field office at time of project mobilization.

1.6 FACSIMILE SERVICE

A. Provide, maintain and pay for facsimile service and a dedicated telephone line to field office at time of project mobilization. Service shall include constant paper and toner supplies.

March 22, 2019 01500 Page 2

1.7 TEMPORARY WATER SERVICE

A. Connect to existing water source for construction operations.

B. Do no disrupt Government's need for continuous service.

1.8 TEMPORARY SANITARY FACILITIES

A. Provide and maintain required facilities and enclosures.

B. Use of existing facilities is allowed subject to approval of Government.

1.9 BARRIERS AND TRAFFIC SIGNAGE

A. Provide barriers to prevent unauthorized entry to construction areas to allow for Government's use of site, and to protect existing facilities and adjacent properties from damage from construction operations.

B. Provide barricades and covered walkways required by governing authorities for public rights-of-way and for access to existing building.

C. Protect non-owned vehicular traffic, stored materials, site, and structures from damage.

D. Provide temporary traffic control signs to direct construction traffic, staff traffic and public traffic to designated areas during the course of construction.

E. Design, location, layout and construction of all barricades and cover walkways shall be approved by the CO prior to construction.

1.10 EXTERIOR ENCLOSURES

A. Provide temporary weather tight closure of exterior openings in existing buildings to provide acceptable working conditions and protection for Products and to prevent entry of unauthorized persons.

B. Provide access doors with self-closing hardware and locks.

1.11 INTERIOR ENCLOSURES

A. Provide temporary partitions and ceilings as required to prevent damage to existing materials and equipment.

1.12 PROTECTION OF INSTALLED WORK

A. Protect installed work and provide special protection where specified in individual specification sections.

B. Provide temporary and removable protection for installed products. Control activity in immediate work area to prevent damage.

C. Provide protective coverings at walls, projections, jambs, sills, and soffits of openings.

D. Protect finished floors, stairs, and other surfaces from traffic, dirt, wear, damage, or movement of heavy objects, by protecting with durable sheet materials.

March 22, 2019 01500 Page 3

1.13 SECURITY

A. Provide security and facilities to protect Work, existing facilities, and Government's operations from unauthorized entry, vandalism, or theft.

B. Coordinate with Government’s security operations and programs.

1.14 PARKING

A. Coordinate temporary parking areas to accommodate construction personnel with Government.

B. Do not allow vehicle parking in existing parking for facility staff and public without Government’s permission.

1.15 FIELD OFFICES

A. Contractor shall set up a field office within the facility renovation area.

1.16 PROGRESS CLEANING AND WASTE REMOVAL

A. Maintain areas free of waste materials, debris, and rubbish. Maintain site in a clean and orderly condition.

B. Remove debris and rubbish from…