A02_11__NCAO_Lead_Paint_Removal_Statement_of_Work_1.pdf
PDF 2 MB Posted
- Attached to
- NCAO Spring Creek Powerplant Lead Paint Removal
- Solicitation number
- 140R2024Q0029
About this file
This statement of work is for lead paint removal services at the Spring Creek Powerplant in California. The Bureau of Reclamation is seeking to remove lead paint from metal surfaces totaling approximately 956 square feet on generation Unit 1. Key requirements include containment of dust and debris, lead testing before and after removal, employing removal techniques to avoid damage to underlying metal, and proper disposal of all waste. The performance period is 14 calendar days between April 15 and May 15, 2024. Required submittals such as safety plans and waste disposal plans are due within 14 days of notice to proceed. Mandatory inspections include work area preparation, abatement completion, final cleaning, and clearance sampling.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Spring Creek Powerplant, Trinity River Division, Central Valley Project, California Unit 1 Lead Paint Removal - NCAO .
STATEMENT OF WORK
Spring Creek Powerplant Lead Paint Removal Northern California Area Office
Bureau of Reclamation
1. BACKGROUND/PROJECT CONDITIONS
1.1. Background: Spring Creek Powerplant is located along Iron Mountain Mine Road. 1 mile north of Keswick, CA. The powerplant has two 70 MW generation units. Unit 1 will undergo refurbishment in the spring of 2024. The Unit will be disassembled so that a major component, the turbine, can be replaced. Several interior metal surfaces of the unit must be machined or piping modifications done in order to accept the new turbine and systems. These surfaces are coated with lead paint, which must be removed prior to machining.
1.2. Access. The painted surfaces are available for work only after Unit disassembly.
Scaffolding and/or ladders may be required to reach surfaces. Contractor to verify from plans and at pre-construction site visit.
1.3. Testing. The paint has been tested for lead or other contaminants. Contractor shall assume that all paint subject to this work contains lead.
2. SCOPE OF WORK
2.1. Contractor shall
2.1.1. Prevent contamination from dust and debris generated by paint removal activities by providing containment immediately around the work area,
2.1.2. Hold point for Contractor once Containment is built for BOR to perform a base line lead survey of work area prior to any paint removal.
2.1.3. remove paint from metal surfaces designated by the government. The major surfaces are circular, with approximate painted areas as follows:
Location Area (ft2)
Turbine Pit and Unit barrel 278
Draft Tube 264
Servo Alcoves 340
Oil Pump Alcove 74
Total Surface Area is Approx 956
The surfaces are mostly vertical; however, some are horizontal, others angled.
Exhibit 1 is a sectional elevation of the turbine with the paint removal areas highlighted. Contractor to verify from plans and at pre-construction site visit.
2.1.4. employ paint removal techniques that avoid unduly damaging the underlying metal.
2.1.5. properly dispose of all removed paint, blast media if used
2.1.6. vacuum and wipe down all surfaces inside the containment area to remove all particulate matter generated by paint removal activities.
2.1.7. Hold point for Contractor while BOR conduct a post paint removal lead contamination survey. This will be compared to pre paint removal survey.
2.1.8. Remove Containment once lead survey is complete and passes industry standards for lead dust.
2.2. Critical Work. Time is of the essence. Paint removal lies on the critical path of the overall refurbishment of Unit 1. Refurbishment work on Unit 1 cannot proceed until the work area is free of paint and cleaned of contaminant surface particles. Contractor needs to remove paint in approximately 1 week's time once containment is set and pre work lead survey is completed.
3. ADMINISTRATIVE INFORMATION
3.1. This part covers the basics of day-to-day operations and normal hours of work.
3.2. Place of Performance: The work to be performed under this contract shall be performed at
Sprint Creek Powerplant, 11757 Iron Mountain Road, Redding CA 96003
3.3. Period of Performance: The performance period for this shall be 14 calendar days.
Project duration includes mobilization, demo and disposal. Start Date can be anywhere between 4/15/24 and 5/15/24 depending on how long it takes Government to disassemble unit. Contractor has 1 week to mobilize once start date is confirmed by Government.
3.4. Hours of Operations: The Contractor is responsible for conducting business, between the hours of 7:00 am-5:00 pm Pacific Standard Time, Monday thru Friday. The Offeror shall, at all times, maintain an adequate workforce for the uninterrupted performance of all tasks defined within this Statement of Work when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential.
3.5. Definitions: The follow acronyms, terms, and wording will be used throughout this
Statement of work.
NCAO – Northern California Area Office
CO – Contracting Officer
COR – Contracting Officers Representative
Offeror – Prime Contractor
OGR – Onsite Government Representative
RSHS – Reclamation Safety and Health Standards
3.6. Post Award Meeting: A brief post award meeting will be held prior to commencement of work. The Contractor shall meet with the designated Bureau of Reclamation Field
Engineer and or Onsite Government Representative. The post award meeting shall provide the Contractor an opportunity to discuss and outline both the safety and work plans, ask any questions relative to the project and to review the proposed time schedule.
3.7. Security: The Contractor shall be responsible for safeguarding all Government equipment, information, and property provided for contractor use. At the close of each work period, Government facilities, equipment, and materials shall be secured.
3.7.1. All vehicles entering the worksite may be subject to search by government security forces.
3.7.2. The Contractor shall maintain a current and updated list of authorized persons, including subcontractors, and provide a copy to the COR.
3.7.2.1. Submit RSN-1: List of Employees
3.7.2.1.1. Country of citizenship.
3.7.2.1.2. Duration and frequency on site.
3.7.2.1.3. Company affiliation and title/classification.
4. COMPLETION REQUIREMENTS: The Contractor’s schedule and plan of work may differ from the order of items described below except where specified.
4.1. Site Cleanup:
4.1.1. Remove all construction waste/debris for recycle/disposal at appropriate facilities.
4.2. Final Acceptance Inspection of All Items:
4.2.1. Review completion of work with OGR.
4.2.2. Make any corrective actions determined as required during Final Acceptance
Inspection.
4.2.3. Final Inspection may uncover items not discovered during previous inspections.
Contractor shall correct all pertinent items upon discovery.
5. GENERAL REQUIREMENTS
5.1. Cleanup and Disposal of Waste Material: The Contractor shall be responsible for all waste materials or rubbish generated by their work.
5.2. Waste Characterization, Handling and Disposal Plan. Provide this plan in accordance with paragraph 6.5.3.
5.3. Safety and Health:
5.3.1. Do not allow Contractor employees (including subcontractors), Government personnel, or the Public to be exposed to, or work under, conditions which are unsanitary, physically hazardous, or a potential exposure danger to their health or safety during performance of the contract.
5.3.2. Since this project will involve removal of lead material, ensure contractor employees (including their subcontractors) and government personnel on site in the vicinity are protected from exposure to these compounds during the removal and disposal process.
5.3.3. The minimum work crew at any time on the construction site shall consist of no less than two people and shall be in accordance with other contractual obligations.
5.4. When violations of safety and health requirements contained in these specifications or referenced standards are called to the Contractor’s attention by the CO, COR, or the OGR, immediately correct the condition to which attention has been directed.
5.4.1. When the Contractor fails or refuses to promptly correct a compliance directive, the CO or the COR may issue an order to stop all or any part of the work.
5.4.1.1. When satisfactory corrective action is taken, an order to resume work will be issued.
5.4.1.2. The Contractor shall not be entitled to extension of time, nor to claim for damage or to additional compensation by reason of either the directive or the stop order.
5.4.1.3. Failure of the CO, COR, or the OGR to order discontinuance of any or all of the Contractor’s operations shall not relieve the Contractor of the responsibility for the safety of personnel and property.
5.4.2. Maintain an accurate record of, and report to the COR in the manner prescribed by the CO for all near misses, accidents or incidents, occupational diseases, traumatic injury, cases of death to Contractor employees (including subcontractors), Government personnel, or the Public, and any property damage occurring during the performance of work under this contract.
5.4.3. The rights and remedies of the Government provided in this section are in addition to any other rights and remedies provided by law or under this contract.
5.4.4. In the event there is a conflict between requirements contained in the Reclamation
Safety and Health Standards (RSHS), specification paragraphs, Contractor’s approved Safety Program, referenced safety and health codes, and standards, or the
U.S. Department of Labor Construction Safety and Health Standards, promulgated under Section 107 of the Contract Work Hours and Safety Standards Act (40
U.S.C. 327 et seq.), as amended, the more protective requirement having jurisdiction shall prevail.
5.5. First Aid and Communication:
5.5.1. Provide first-aid kits in accordance with Reclamation RSHS Section 5.
5.5.2. Make first aid and communication services available for providing emergency aid to employees and subcontractor employees.
5.6. Contractor's Onsite Safety Personnel:
5.6.1. Maintain records to comply with all applicable portions of CA Dept of Health, OSHA and EPA requirements, and other requirements of this specification.
5.6.2. Ensure Contractor (and or subcontractor) personnel are currently licensed and registered with the State of California and have necessary training and personnel to perform lead work and abatement under the laws and regulations of Title 17 of the
California Code of Regulations as a certified lead worker.
5.6.2.1. Contractor must demonstrate that they have (or will have) a sufficient number of skilled trades and licensed abatement workers who have successfully completed EPA model curriculum training in lead-based paint abatement, so as to be able to complete all aspects of work covered.
5.6.2.2. Contractor shall specify an on-site supervisor/competent person who is fully qualified in all aspects of lead abatement practices and procedures and meets all EPA/OSHA supervisor/competent person requirements.
5.6.3. Contractor shall ensure they have a respiratory protection program and current fit testing for all personnel and are providing medical examinations as per 29
CFR1926.58 and 1926.62 in addition the contractors physician shall perform an evaluation of each workers ability to work in heat stress environments.
5.6.4. Contractor to perform air monitoring and sampling in accordance with California
CCR for ensuring compliance and providing copies of these reports upon request to the COR.
5.6.4.1. Personal air sampling (OSHA required monitoring) activities must be conducted by the Contractor or his duly authorized representative during lead-based paint abatement work or any other work involving lead containing materials. The results of such sampling shall be posted, provided to individual workers within the OSHA required timeframe, and provided to the COR upon request within 24 hours after Contractor receipt of results.
Contractor must ensure analytical result receipt no later than 5 calendar days after sample collection.
5.6.4.2. The Contractor's air sample testing lab shall be an independent third party and shall be a successful participant in the National Lead Laboratory
Accreditation Program (NLLAP). Air sample analyses will be by NIOSH
Method 7082.
5.6.4.3. Air samples shall be taken for the duration of the work shift or for a minimum of seven hours at the Contractor's expense. Personal samples must also be taken every time there is a change in the removal operation, either in terms of the location, the type of work, method of abatement, method of engineering control, change in the personnel completing abatement or other change in abatement process that might affect the exposure to lead of the workers. Sampling will be used to determine eight-hour Time-Weighted
Averages (TWA). Personal air sampling will be conducted as outlined in
NIOSH Method 7082 and OSHA Standard 29 CFR 1926.62. The laboratory results of the air sampling will determine the degree of respiratory protection and decontamination required, subject to the regulations. It will also help determine other safety requirements for the workers, as well as the engineering controls that are required. It will help evaluate the effectiveness of engineering controls and worker protection measures. All air sampling will be solely at the Contractor's expense.
5.6.4.4. Air sampling results shall be submitted to individual workers and the COR upon request available at the job site in written form no more than 5 days after the completion of a sampling cycle. The reporting document shall list each sample's result, sampling time and date, personnel's name who were monitored and their social security number, flow rate, cassette size, analysts' name, laboratory name and laboratory's NLLAP accreditation number, certificate copy. The document shall include an interpretation of the results.
All air samples analysis results shall be reported in gg/m.
5.6.4.5. Air Monitoring Frequency. The air monitoring frequency for Contractor operations shall at least be established in accordance with the requirements set forth in 29 CFR 1926.62.
5.7. Temporary Utilities: Applies to utilities available for use by the contractor.
5.7.1. Electricity.
5.7.1.1. Contractor shall coordinate with OGR for use of facility electrical power.
If facility power is unavailable, contractor shall provide required electrical power for construction.
5.7.1.2. Remove temporary equipment and facilities upon completion of work.
5.7.2. Water.
5.7.2.1. Government shall provide water required for construction purposes.
Contractor shall provide backflow preventer at point of connection.
Location to be coordinated with the OGR.
5.7.2.2. Provide means of conveying water to points of use.
5.7.2.3. Remove temporary equipment and facilities upon completion of work.
5.8. Vehicular Access and Parking:
5.8.1. Onsite parking is available for contractor use.
5.8.2. Promptly repair ruts, broken pavement, potholes, low areas with standing water, and other deficiencies caused by contractor (or subcontractor) to maintain road surfacing and drainage in original or specified condition.
5.9. Protection of Existing Installations:
5.9.1. Provide protection for personnel and existing facilities from harm due to the
Contractor's operations. Protection shall be subject to approval of the
Government.
5.9.2. Arrange protective installations to permit operation of existing equipment and facilities by the Government while work is in progress.
5.9.3. Do not discharge anything but clear water into onsite drainage system.
5.9.4. Repair, at Contractor's expense, damage to existing installations due to
Contractor's operations or Contractor's failure to provide proper protection. At the
Government's option, damage may be repaired by the Government, and the
Contractor will be back charged repair costs.
5.10. Protection of Existing Utilities:
5.10.1. Dust Abatement:
5.10.1.1. Provide dust control and abatement as required during construction to keep emissions at or below required air quality levels.
5.10.1.2. Prevent, control; and abate dust pollution during performance of work to prevent dust nuisance or damage to persons or property.
5.10.1.3. Contractor shall be responsible for damages resulting from dust originating from Contractor operations in accordance with clause at
FAR 52.236-7 "Permits and Responsibilities".
5.10.2. Noise Control:
5.10.2.1. Comply with all applicable Federal laws and regulations, and with applicable requirements of RSHS regarding the prevention, control, and abatement of harmful noise levels.
5.11. Hazardous Materials and Wastes: Remove and dispose of all hazardous materials and waste products encountered during construction.
5.11.1. Provide Waste Characterization, Handling Disposal Plan.
5.11.2. Hazardous waste shall be disposed of at a facility properly licensed and permitted for disposal of hazardous materials
5.11.3. Upon transportation of hazardous waste for disposal coordinate with NCAO
Environmental Hazardous Material Specialist to be present while transportation services are picking up waste for disposal. NCAO Environmental Specialist will sign manifest and will track waste final disposal from that point on.
6. SUBMITTALS
6.1. The Contractor shall submit Required Submittal Notices (RSN) necessary to start work within 14 calendar days of the Notice to Proceed.
6.2. The Government will review the Required Submittal Notices within 14 calendar days of official receipt.
6.2.1. Submittals will be returned as Approved, Conditionally Approved, or Not
Approved.
6.2.2. The Contractor shall resubmit Required Submittal Notices within 14 calendar days of receipt for Required Submittal Notices that are Conditionally Approved or Not
Approved.
6.2.3. The Government will review resubmitted Required Submittal Notices within 14 days of official receipt.
6.3. Address submittal to:
6.3.1. Email to: Contracting Officer and COR. Email addresses will be provided with
Notice to Proceed.
6.3.2. One hard copy to the Contracting Officer:
Bureau of Reclamation
California Great Basin Region, Attn: CGB-3800
Federal Office Building
2800 Cottage Way
Sacramento CA 95825-1898
One hard copy to the COR:
Bureau of Reclamation
Northern California Area Office, Attn: John Dotter
16349 Shasta Dam Blvd
Shasta Lake, CA 96019
6.4. Preparation:
6.4.1. Prepare in English.
6.4.2. Label with contract number and title, and RSN.
6.4.3. Measurement units: US Customary Units.
6.4.4. Sign and seal submittals requiring certification by a California registered professional.
6.4.5. Submittals must be reviewed by Contractor. Submittals without evidence of
Contractor's approval will be returned for resubmission.
6.4.6. Include the following information in transmittal letters:
6.4.6.1. Contract number and title.
6.4.6.2. RSN for each attached submittal.
6.4.6.3. Responsible code.
6.4.6.4. Identify submittal as initial or resubmittal.
6.4.7. More than one RSN may be submitted under a transmittal letter, provided the responsible code is the same.
6.4.8. Submittals not listed in this Statement of Work:
6.4.8.1. Submit in accordance with this section.
6.5. Submittal List and Requirements:
6.5.1. RSN-1, List of Employees:
6.5.1.1. Country of citizenship.
6.5.1.2. Duration and frequency on site.
6.5.1.3. Company affiliation and title/classification.
6.5.2. RSN-2, Safety Plan: Written Safety Program in accordance with Section 3 of the
RSHS.
6.5.2.1. Cover all aspects of on site and applicable off-site operations and activities associated with this contract.
6.5.2.2. Program shall follow the format of the outline in Appendix B of RSHS.
Submittal will not be accepted for review by the COR/OGR unless it addresses, in order, lettered and numbered per Appendix B, a narrative for each applicable item in the outline.
6.5.2.3. For items in the outline that do not apply to this contract write “Not
Applicable to Contract” next to the number/letter.
6.5.2.4. Provide a list of Job Hazard Analyses (JHA) – outlines of work safety regarding protective equipment to be used/ required for removal of hazardous material.
6.5.3. RSN-3, Waste Characterization, Handling Disposal Plan. Provide a waste characterization, handling and disposal plan for lead-containing hazardous material, plus any additional materials that must be disposed.
7. INSPECTIONS
7.1. The COR will make four (4) mandatory inspections during the abatement work. Each inspection must be requested by the Contractor to be performed by the COR. The COR must approve the inspected work before work may begin for the next phase of work.
Failure on the part of the Contractor to obtain the CORs approval before proceeding to the next phase is regarded as a violation of the contract. In the event of this occurring, the COR may recommend that all work be stopped until all required work is shown to be completed to the satisfaction of the COR. The four inspections are as follows:
7.1.1. Work area preparation completed - Contractor shall have all Pre-Abatement preparations of the work area completed and approved by the COR before proceeding to the next step.
7.1.2. Completion of lead-based paint abatement – Contractor shall have all abatement work completed, inspected, and approved before moving to the next step.
7.1.3. Completion of final cleaning inspection - Contractor shall have the final cleanup of all visible debris, waste, dust and residue approved before moving to the next step.
The Contractor shall perform final cleaning techniques of HEPA vacuuming, washing with lead removal agent, and HEPA vacuuming before requesting final clearance sampling. Final clearance sampling will not occur until all surfaces are completely dry.
7.1.4. Final Clearance Sampling. COR will perform final clearance wipe testing after final clean-up activities are completed and surfaces have been properly sealed with appropriate approved materials for the substrate. The Contractor shall notify the
COR. Representative at least 24 hours in advance of the need for clearance wipe sampling.
7.1.5. A final punch list inspection is also required after all work is completed.
8. EXECUTION
8.1. All damages to the structure or property occurring as a result of any and all contract work and/or sub-contractor work activities or actions shall be repaired or replaced at the
Contractor’s sole expense, to the satisfaction of the COR/OGR Representative with no additional cost to the COR/OGR Representative. The Contractor will not be allowed any additional time allowances or extensions for any such circumstance or event.
8.2. General Removal Procedures.
8.2.1. Abrasive Blasting-if using abrasive blasting NCAO strongly encourages the use of environmentally friendly products such as Clean Blast or like product.
8.2.2. Vapor Blasting-the use of vapor blasting is also encouraged as an option for abatement. All grey water must be contained and disposed of properly.
8.2.3. Chemical Removal- SDS sheets must be on site for COR to review upon request.
8.2.4. Laser Removal-ensure proper PPE is utilized
9. REFERENCES
9.1. Bureau of Reclamation Documents:
9.1.1. Reclamation Safety and Health Standards (RSHS) may be downloaded at www.usbr.gov/ssle/safety/RSHS/rshs.html.
9.2. Plans and photos of generation Unit 1, provided below.
http://www.usbr.gov/ssle/safety/RSHS/rshs.html
Exhibit 1: Turbine Section Elevation
Exhibit 2: Draft Tube Section Elevation
Photos: Areas where paint is to be removed (Examples from Unit 2 when disassembled)