C5_4_Attach_5_-_REVISED_PWS_Breakers_Rewire_(12_14_23)_0002.pdf

PDF 2 MB Posted

Attached to
Rewire 3 Circuit Breaker Panels for Reclamation
Solicitation number
140R2024Q0019
Issued by

About this file

This performance work statement outlines rewire services for three 480V/1600Amp circuit breakers at the Folsom Power Plant D2A electrical panel. The Bureau of Reclamation's Central California Area Office purchased three replacement SIEMENS RL-1600 circuit breakers that need to be rewired to match the existing breakers based on provided drawings. Services include rewiring the agency-supplied units to match customer breakers and diagrams, removing UV circuitry, performing preventative maintenance, cleaning, testing, and providing a written condition report. The period of performance is six months from purchase order receipt. Work will be performed at the contractor's facility, who will receive the breakers from the agency within three weeks of award and return the rewired units once completed. Quality assurance will be conducted through government review of all work prior to invoice approval.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Performance Work Statement Folsom Power Plant D2A Circuit Breakers Rewire

REVISED: December 14, 2023

1.0 Scope

There are three 480V/1600Amp SIEMENS circuit breakers at Folsom Power Plant D2A electrical panel.

(See drawing #485-D—353 and Figure 1 and 2). The Bureau of Reclamation (BOR) Central California Area Office (CCAO) purchased three RL-1600 SIEMENS breakers (see Figure 3-6). The new replacements need to be rewired to match the existing breakers base on drawing # 485-D-2139.

• Services to rewire CCAO supplied units from WD 18-738-602-445 to Customers existing Breaker WD 18-738-602-445 and Trip

• Wiring Diagram 18-738-600-401

• Pinning out each breaker individually.

• Creating wiring diagrams without UV circuit.

• Removing UV.

• PM, Clean and Test

• Provide a written report on the condition.

2.0 Period of Performance

Rewire services are to be completed within 6 months (180 days) after the receipt of the Purchase Order.

3.0 Place of Performance

Contractor’s shop/ work site. Reclamation will send the breakers to the contractor’s facility. Contractor to return rewired breakers to Reclamation once work is completed. Breakers will be sent to the contractor within three (3) weeks of Purchase Order being awarded.

Bureau of Reclamation Central California Area Office 7794 Folsom Dam Road Folsom, CA 95630-1799

4.0 Quality Assurance Surveillance Plan

The Quality Assurance Surveillance Plan is one evaluation method the government uses to perform surveillance to determine whether the Contractor meets the standards of performance as defined in the PWS. The absence of a QASP for any contract requirement, however, shall not detract from its enforceability or limit the rights or remedies of the government under any other provision of the contract in determining the quality of the Contractor performance.

5.0 Performance Requirements Summary Table

Performance Requirement Acceptable Quality Level

Means of Measurement

Contractor shall comply with the Performance Work Statement

All agreed upon work is performed to an acceptable level as stated in the performance work statement and in conjunction with applicable federal, state, or local regulations.

Government representative review of 100% of the work completed as stated in the invoice prior to approving invoice.

Attachment A

Figure 1- Folsom Power plant D2A panel existing breaker name plate

Figure 2- Folsom Power Plant D2A panel existing breaker side photo

Figure 3- New breaker name plate

Figure 4- New Breaker side photo

Figure 5- New Breaker purchase date

Figure 6- New Breaker rear side