This solicitation requests proposals to replace the fish screens at the Roza Diversion Dam. The Department of the Interior Bureau of Reclamation is seeking proposals to remove the existing screens and install new fish screens to prevent endangered fish species from being drawn into irrigation canals. Proposals are due by October 31, 2023, and the agency aims to award a contract by January 15, 2024. The successful offeror will be responsible for designing, fabricating, and installing new fish screens that meet the specifications in the solicitation documents. The agency expects the work to be completed by June 1, 2024.

View the file

Other files for this federal contract opportunity

Other files attached to Fish Screen Replacement - Roza Diversion Dam, newest first.
File Type Posted
Amendment_0004_0004.pdf PDF
Sol_140R1024R0001_Amd_0004.pdf PDF
Amendment_0003_0003.pdf PDF
Sol_140R1024R0001_Amd_0003.pdf PDF
Amendment_0002_0002.pdf PDF
Sol_140R1024R0001_Amd_0002.pdf PDF
Amendment_0001_0001.pdf PDF
Sol_140R1024R0001_Amd_0001.pdf PDF
1_OF_2_ROZA_FISH_SCREENS_FINAL_DESIGN_DRAWINGS.pdf PDF
2_OF_2_ROZA_FISH_SCREENS_FOR_INFORMATION_ONLY_DRAWINGS.pdf PDF
Sol_140R1024R0001.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. Department of the Interior SPECIFICATIONS Bureau of Reclamation Columbia Pacific Northwest Interior Region 9 Boise, Idaho August 2023

Solicitation No. 140R1024R0001

Fish Screen Replacement - Roza Diversion Dam

Yakima Project, Washington

This solicitation issued by Contracting Officer

Pacific Northwest Region Bureau of Reclamation

1150 North Curtis Road, Suite 100 Boise ID 83706-1234

Phone inquiries regarding this solicitation should be made to Regional Acquisition Management Officer

Telephone Number: (208) 378-5364

FISH SCREEN REPLACEMENT

Roza Diversion Dam Yakima, Washington

FOREWORD

Work is located at the Roza Diversion Dam approximately ten miles north of Yakima, Washington. Work is for replacing the existing fish screens. Principal components of the work include temporary isolation of the work area with sheet piling and bulkheads, dewatering, concrete demolition, cast-in-place concrete, fish screens, electrical systems, and miscellaneous metalwork.

PRE-OFFER SITE VISIT: SEE SECTION L FOR SITE VISIT INFORMATION.

ATTENDEES ARE TO PROVIDE AND WEAR SAFETY BOOTS, HARD HATS, AND

SAFETY VESTS.

FOR DATE AND PLACE OF OFFER OPENING, SEE "SOLICITATION, OFFER, AND

AWARD," STANDARD FORM 1442.

FOR INFORMATION REGARDING BUREAU OF RECLAMATION'S PUBLICATION

"RECLAMATION SAFETY AND HEALTH STANDARDS" INCLUDING REVISIONS

AT http://www.usbr.gov/safety/rshs/index.html) WHICH IS APPLICABLE TO WORK

UNDER THIS CONTRACT, SEE CLAUSE AT "WBR 1452.223-81 SAFETY AND

HEALTH."

140R1024R0001 Fish Screen Replacement – Roza Diversion Dam i

PART I THE SCHEDULE..................................................................................................... A-1

SECTION A SOLICITATION/CONTRACT FORM ........................................................ A-2

SECTION B SUPPLIES OR SERVICES AND PRICES/COSTS ..................................... B-1

SECTION C DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK ................ C-1

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 Summary of Work 01 12 40 Construction Sequencing 01 14 10 Use of Site 01 14 16 Washington State Requirements 01 14 20 Facility Operations and Conditions 01 29 00 Payment Procedures 01 31 19 Project Management and Coordination 01 31 30 Contract Document Management System 01 32 10 Construction Program 01 33 00 Submittals 01 35 10 Safety Data Sheets 01 35 20 Safety and Health 01 35 27 Underwater Work 01 35 30 Contractor's Onsite Safety Personnel 01 42 10 Reference Standards 01 46 00 Quality Procedures 01 46 20 Testing Agency Services 01 51 00 Temporary Utilities 01 52 10 Field Office 01 54 20 Use of Government Crane 01 55 00 Vehicular Access and Parking 01 55 10 Crossing Existing Bridges 01 55 12 Operating From Existing Gantry Deck 01 56 10 Protection of Existing Installations 01 56 15 Protection of Existing Utilities 01 57 20 Environmental Controls 01 57 30 Water Pollution Control 01 57 90 Preservation of Historical and Archeological Data 01 60 00 Product Requirements 01 71 20 Surveying 01 74 00 Cleaning and Waste Management 01 78 30 Project Record Documents

DIVISION 02 - EXISTING CONDITIONS

02 41 13 Selective Site Demolition ii

DIVISION 03 - CONCRETE

03 11 10 Concrete Forming 03 15 12 PVC Waterstop 03 15 14 PVC Retro-Fit Waterstop 03 20 00 Concrete Reinforcing 03 20 30 Post-Installed Adhesive Anchors 03 30 00 Cast-In-Place Concrete 03 37 26 Underwater Concrete 03 62 20 Nonshrink Grout for Equipment and Metalwork 03 63 00 Concrete Doweling for Tremie Concrete 03 81 10 Concrete Removal

DIVISION 05 - METALS

05 12 43 Structural Steel Framing for Cofferdam 05 45 20 Combination Channel Equipment Supports 05 50 00 Metal Fabrications

DIVISION 26 - ELECTRICAL

26 05 02 Basic Electrical Materials and Methods 26 05 10 Conductors and Cables 26 05 20 Grounding and Bonding 26 05 33 Electrical Conduit 26 05 90 Wiring Checkout and Tests 26 22 16 Transformer Load Center 26 27 30 Wiring Devices 26 28 30 Enclosed Circuit Breakers

DIVISION 31 - EARTHWORK

31 02 10 Water for Dust Abatement 31 03 33 Removal of Water 31 23 02 Compacting Earth Materials 31 23 11 Earthwork for Structures 31 23 39 Disposal of Excavated Materials 31 41 16 Sheet Piling

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

35 21 16 Hydraulic Bulkheads 35 21 17 Cofferdam End Returns 35 21 18 Cofferdam Closure Wall 35 21 42 Fish Screen Assemblies 35 22 10 Slide Gates 35 24 20 Screeding Sediment

DIVISION 51 - INFORMATION AVAILABLE TO CONTRACTOR

51 00 00 Information Available to Contractor 51 00 10 Photographs iii

51 32 20 Example Construction Sequence to Contractor

DIVISION 52 - DRAWINGS

52 00 00 Drawings

SECTION D PACKAGING AND MARKING .................................................................. D-1

SECTION E INPSECTION AND ACCEPTANCE ............................................................ E-1

E.1. 52.236-5 Material and Workmanship (Apr 1984) ..................................................... E-1

E.2. 52.246-12 Inspection of Construction (Aug 1996) .................................................... E-1

E.3. 52.246-21 Warranty of Construction (Mar 1994), Alternate I (Apr 1984) ................ E-1

SECTION F Section F Deliveries and Performance ........................................................... F-1

F.1. 52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984) ...... F-1

F.2. 52.211-12 Liquidated Damages - Construction (Sep 2000) ...................................... F-1

F.3. 52.211-13 Time Extensions (Sep 2000)..................................................................... F-1

F.4. 52.242-14 Suspension of Work (Apr 1984) ............................................................... F-1

SECTION G CONTRACT ADMINISTRATION .............................................................. G-1

G.1. Government Point of Contact ................................................................................... G-1

G.2. 1452.201-70 Authorities and Delegations (Sep 2011) .............................................. G-1

G.3. DOI-AAAP-0028 Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (April 2013) .............................................................................. G-1

G.4. WBR 1452.201-80 Contracting Officer's Representative's Authorities and Limitations -- Bureau of Reclamation (May 2018) ................................................................................ G-2

SECTION H SPECIAL CONTRACT REQUIREMENTS ................................................ H-1

H.1. Key Personnel Requirements – Bureau of Reclamation – C-PN Region (Feb 1995)….. .............................................................................................................................. H-1

H.2. DOI-AAAP-0050 Contractor Performance Assessment Reporting System (Dec 2015).. .................................................................................................................................. H-1

PART II CONTRACT CLAUSES .......................................................................................... I-1

SECTION I CONTRACT CLAUSES ................................................................................. I-1

I.1. 52.252-2 Clauses Incorporated by Reference (Feb 1998) .......................................... I-1

I.2. 52.202-1 Definitions (Jun 2020) ................................................................................. I-1

I.3. 52.203-3 Gratuities (Apr 1984)................................................................................... I-1

I.4. 52.203-5 Covenant Against Contingent Fees (May 2014) ......................................... I-1

I.5. 52.203-6 Restriction on Subcontractor Sales to the Government (Jun 2020) ............. I-1

I.6. 52.203-7 Anti-Kickback Procedures (Jun 2020) ........................................................ I-1 iv

I.7. 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (May 2014) .............................................................................................................. I-1

I.8. 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (May 2014) ..... I-1

I.9. 52.203-12 Limitations on Payments to Influence Certain Federal Actions (Jun 2020)… .................................................................................................................................. I-1

I.10. 52.203-13 Contractor Code of Business Ethics and Conduct (Nov 2021) ................. I-1

I.11. 52.203-14 Display of Hotline Poster(s) (Nov 2021) ................................................... I-1

I.12. 52.203-17 Contractor Employee Whistleblower Rights and Requirement to Inform Employees of Whistleblower Rights (Jun 2020) ................................................................... I-1

I.13. 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) ............................................................................................................ I-1

I.14. 1452.203-70 Restrictions on Endorsements – Department of Interior (Jul 1996) ...... I-1

I.15. 52.204-4 Printed or Copied Doubled-Sided on Postconsumer Fiber Content Paper (May 2011) ............................................................................................................................ I-1

I.16. DOI-AAAP-0081 Security Requirements: Facility Access Information Technology (Aug 2016) ............................................................................................................................. I-1

I.17. 52.204-9 Personal Identity Verification of Contractor Personnel (Jan 2011) ............ I-6

I.18. 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (Jun 2020) .............................................................................................................................. I-6

I.19. 52.204-12 Unique Entity Identifier Maintenance (Oct 2016) ..................................... I-6

I.20. 52.204-13 System for Award Management (Oct 2018) .............................................. I-6

I.21. 52.204-14 Service Contract Reporting Requirements (Oct 2016) .............................. I-6

I.22. 52.204-18 Commercial and Government Entity Code Maintenance (Aug 2020) ...... I-6

I.23. 52.204-19 Incorporation by Reference Representations and Certifications (Dec 2014).. .................................................................................................................................... I-6

I.24. 52.204-21 Basic Safeguarding of Covered Contractor Information Systems (Nov 2021).. .................................................................................................................................... I-6

I.25. 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (Nov 2021) ............ I-8

I.26. 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services and Equipment (Nov 2021) ................................................................ I-8

I.27. 52.204-27 Prohibition on a ByteDance Covered Application (Jun 2023) ................ I-11

I.28. 1452.204-70 Release of Claims – Department of Interior (Jul 1996) ....................... I-13

I.29. 52.209-6 Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Nov 2021) ...................... I-13 v

I.30. 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (Oct 2018)............................................................................................................... I-13

I.31. 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015).. .................................................................................................................................. I-13

I.32. 52.210-1 Market Research (Nov 2021) .................................................................... I-13

I.33. 52.215-2 Audit and Records – Negotiation (Jun 2020) ............................................ I-13

I.34. 52.215-8 Order of Precedence – Uniform Contract Format (Oct 1997) ................... I-13

I.35. 52.215-10 Price Reduction Defective Cost or Pricing Data (Aug 2011) .................. I-13

I.36. 52.215-12 Subcontractor Cost or Pricing Data (Jun 2020) ....................................... I-13

I.37. 1452.215-70 Examination of Records by the Department of Interior (Aug 1996) (Deviation) ........................................................................................................................... I-13

I.38. 52.215-21 Requirements for Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data – Modifications (Nov 2021) ....................................................................... I-13

I.39. WBR 1452.215-87 Incorporation of Technical Proposal -- Bureau of Reclamation (Mar 2021) ........................................................................................................................... I-13

I.40. 52.219-6 Notice of Total Small Business Set-Aside (Nov 2020) ............................. I-14

I.41. 52.219-8 Utilization of Small Business Concerns (Sep 2023) ................................. I-14

I.42. 52.219-14 Limitations on Subcontracting (Oct 2022) .............................................. I-14

I.43. 52.219-28 Post-Award small Business Program Representation (Sep 2023) ........... I-14

I.44. 52.222-3 Convict Labor (Jun 2003) .......................................................................... I-14

I.45. 52.222-4 Contract Work Hours and Safety Standards – Overtime Compensation (May 2018).. .................................................................................................................................. I-14

I.46. 52.222-6 Construction Wage Rate Requirements (Aug 2018) ................................. I-14

I.47. 52.222-7 Withholding of Funds (May 2014) ............................................................ I-14

I.48. 52.222-8 Payrolls and Basic Records (Jul 2021) ...................................................... I-14

I.49. 52.222-9 Apprentices and Trainees (Jul 2005) ......................................................... I-14

I.50. 52.222-10 Compliance with Copeland Act Requirements (Feb 1988) ..................... I-14

I.51. 52.222-11 Subcontracts (Labor Standards) (May 2014)........................................... I-14

I.52. 52.222-12 Contract Termination – Debarment (May 2014) ..................................... I-14

I.53. 52.222-13 Compliance with Construction Wage Rate Requirements and Relation Regulations (May 2014) ...................................................................................................... I-14

I.54. 52.222-14 Disputes Concerning Labor Standards (Feb 1988) .................................. I-14

I.55. 52.222-15 Certification of Eligibility (May 2014) ................................................... I-14 vi

I.56. 52.222-21 Prohibition of Segregated Facilities (Apr 2015) ...................................... I-14

I.57. 52.222-26 Equal Opportunity (Sep 2016) ................................................................. I-14

I.58. 52.222-27 Affirmative Action Compliance Requirements for Construction (Apr 2015).. .................................................................................................................................. I-14

I.59. 52.222-35 Equal Opportunity for Veterans (Jun 2020) ............................................ I-14

I.60. 52.222-36 Equal Opportunity for Workers with Disabilities (Jun 2020) ................. I-15

I.61. 52.222-37 Employment Reports on Veterans (Jun 2020) ......................................... I-16

I.62. 52.222-40 Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) ........................................................................................................................... I-16

I.63. 52.222-50 Combating Trafficking of Persons (Nov 2021) ....................................... I-16

I.64. 52.222-54 Employment Eligibility Verification (May 2022) ................................... I-16

I.65. 52.222-55 Minimum Wages Under Executive Order 13658 (Jan 2022) .................. I-16

I.66. 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022) .................... I-16

I.67. 52.223-3 Hazardous Material Identification and Material Safety Data (Feb 2021), Alternate I (Jan 1995) .......................................................................................................... I-16

I.68. 52.223-5 Pollution Prevention and Right-to-Know Information (May 2011) .......... I-16

I.69. 52.223-6 Drug Free Workplace (May 2001) ............................................................ I-16

I.70. 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (Jun 2020) ............................................................................................................................ I-16

I.71. 52.223-20 Aerosols (Jun 2016) ................................................................................. I-16

I.72. 52.223-21 Foams (Jun 2016) .................................................................................... I-16

I.73. WBR 1452.223-80 Asbestos Free Warranty – Bureau of Reclamation (Aug 2021) I-16 I.74. WBR 1452.223-81 Safety and Health -- Bureau of Reclamation (Oct 2022) .......... I-16

I.75. WBR 1452.223-82 Ensuring Adequate COVID-19 Safety Protocols in Federal buildings and Federally Controlled Facilities – Bureau of Reclamation (Nov 2022) ......... I-17

I.76. 52.225-11 Buy American-Construction Materials under Trade Agreements (Dec 2022).. .................................................................................................................................. I-17

I.77. 52.225-13 Restrictions on Certain Foreign Purchases (Feb 2021) ........................... I-25

I.78. 52.227-1 Authorization and Consent (Jun 2020) ...................................................... I-25

I.79. 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (Jun 2020).. .................................................................................................................................. I-25

I.80. 52.227-4 Patent Indemnity – Construction Contracts (Dec 2007) ............................ I-25

I.81. 52.227-17 Rights in Data – Special Works (Dec 2007)............................................ I-25 vii

I.82. 52.228-2 Additional Bond Security (Oct 1997) ........................................................ I-25

I.83. 52.228-5 Insurance – Work on a Government Installation (Jan 1997) ..................... I-25

I.84. 52.228-11 Pledges of Assets (Feb 2021) .................................................................. I-25

I.85. 52.228-12 Prospective Subcontractor Requests for Bonds (Dec 2022) .................... I-25

I.86. 52.228-14 Irrevocable Letter of Credit (Nov 2014) .................................................. I-25

I.87. 52.228-15 Performance and Payment Bonds – Construction (Jun 2020) ................. I-25

I.88. 1452.228-70 Liability Insurance – Department of Interior (Jul 1996) ..................... I-26

I.89. 52.229-3 Federal, State, and Local Taxes (Feb 2013) .............................................. I-27

I.90. 52.229-12 Tax on Certain Foreign Procurements (Feb 2021) .................................. I-27

I.91. Notice of Washington State Sales and Use Tax – Bureau of Reclamation – C-PN Region (Feb 1995) ............................................................................................................... I-27

I.92. 52.232-5 Payment Under Fixed-Price Construction Contracts (May 2014) ............. I-27

I.93. 52.232-17 Interest (May 2014) ................................................................................. I-27

I.94. 52.232-23 Assignment of Claims (May 2014) ......................................................... I-27

I.95. 52.232-27 Prompt Payment for Construction Contracts (Jan 2017) ......................... I-27

I.96. 52.232-33 Payment by Electronic Funds Transfer – System for Award Management (Oct 2018) ............................................................................................................................ I-27

I.97. 52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013) ..................... I-27

I.98. 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Mar 2023).. .................................................................................................................................. I-27

I.99. WBR 1452.232-80 Limitation of Funds -- Bureau of Reclamation ......................... I-27

I.100. WBR 1452.232-81 Payment for Mobilization and Preparatory Work -- Bureau of Reclamation (Mar 2022) ...................................................................................................... I-30

I.101. 52.233-1 Disputes (Mar 2014), Alternate I (Dec 1991)............................................ I-32

I.102. 52.233-3 Protest After Award (Aug 1996) ............................................................... I-32

I.103. 52.233-4 Applicable Law for Breach of Contract Claim (Oct 2004) ....................... I-32

I.104. 52.236-2 Differing Site Conditions (Apr 1984) ........................................................ I-32

I.105. 52.236-3 Site Investigation and Conditions Affecting Work (Apr 1984) ................ I-32

I.106. 52.236-5 Material and Workmanship (Apr 1984) .................................................... I-32

I.107. 52.236-6 Superintendence by the Contractor (Apr 1984) ......................................... I-32

I.108. 52.236-7 Permits and Responsibilities (Nov 1991) .................................................. I-32

I.109. 52.236-8 Other Contracts (Apr 1984) ....................................................................... I-32 viii

I.110. 52.236-9 Protecting Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Apr 1984) ................................................................................................... I-32

I.111. 52.236-10 Operation and Storage Areas (Apr 1984) ................................................ I-32

I.112. 52.236-11 Use and Possession Prior to Completion (Apr 1984) .............................. I-32

I.113. 52.236-12 Cleaning Up (Apr 1984) .......................................................................... I-32

I.114. 52.236-13 Accident Prevention (Nov 1991), Alternate I (Nov 1991) ...................... I-32

I.115. 52.236-14 Availability and Use of Utility Services (Apr 1984) ............................... I-32

I.116. 52.236-17 Layout of Work (Apr 1984)..................................................................... I-32

I.117. 52.236-21 Specifications and Drawings for Construction (Feb 1997), Alternate I (Apr 1984).. .................................................................................................................................. I-32

I.118. 52.236-26 Preconstruction Conference (Feb 1995) .................................................. I-32

I.119. WBR 1452.236-84 Preservation of Cultural Resources – Bureau of Reclamation (Mar 2022).. .................................................................................................................................. I-32

I.120. WBR 1452.237-80 Security Requirements – Bureau of Reclamation (Mar 2022) .. I-34 I.121. Implementation of Security Requirements – Construction Contract – Bureau of Reclamation – C-PN Region (Aug 2010) ............................................................................ I-46

I.122. 52.242-13 Bankruptcy (Jul 1995) ............................................................................. I-48

I.123. 52.243-4 Changes (Jun 2007) ................................................................................... I-48

I.124. 52.243-6 Change Order Accounting (Apr 1984) ...................................................... I-48

I.125. WBR 1452.243-80 Modification Proposals– Bureau of Reclamation (Mar 2022) Alt II (Mar 2022) ....................................................................................................................... I-48

I.126. 52.244-2 Subcontracts (Jun 2020) ............................................................................ I-49

I.127. 52.244-6 Subcontracts for Commercial Products and Commercial Services (Sep 2023).. .................................................................................................................................. I-49

I.128. 52.245-1 Government Property (Sep 2021) .............................................................. I-49

I.129. 52.245-9 Use and Charges (Apr 2012) ..................................................................... I-49

I.130. 52.248-3 Value Engineering – Construction (Oct 2020), Alternate I (Apr 1984) .... I-49

I.131. 52.249-2 Termination for Convenience of the Government (Fixed Price) (Apr 2012), Alternate I (Sep 1996) ......................................................................................................... I-49

I.132. 52.249-10 Default (Fixed-Price Construction) (Apr 1984) ...................................... I-49

I.133. 52.252-6 Authorized Deviation in Clauses (Nov 2020) ........................................... I-49

I.134. 52.253-1 Computer Generated Forms (Jan 1991)..................................................... I-49

I.135. Contract Document Management System (CDMS) -- CPN Region (Apr 2021) ...... I-49 ix

PART III LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS ................ J-1

SECTION J LIST OF ATTACHMENTS ........................................................................... J-1

J.1. Department of Labor, General Wage Decision No. WA20220049, dated August 25, 2023, 8 pages. ....................................................................................................................... J-1

J.2. Past Performance Questionnaire, 3 pages. ................................................................. J-1

J.3. Bid Bond, 2 pages. ..................................................................................................... J-1

J.4. Drawings, 160 pages. ................................................................................................. J-1

J.5. Categorical Exclusion Checklist, 18 pages. ............................................................... J-1

J.6. Determination of Nonsignificance (DNS) and Adoption of Existing Environmental Document (CATEGORICAL EXCLUSION), 3 pages. ....................................................... J-1

J.7. Inadvertent Discovery Plan, 12 pages. ....................................................................... J-1

J.8. Hydraulic Project Approval, 7 pages. ........................................................................ J-1

J.9. Hydraulic Project Approval; Minor Modification, 1 page. ........................................ J-1

J.10. Joint Aquatic Resources Permit Application (JARPA), 16 pages. ............................ J-1

J.11. JARPA, Attachment D, 2 pages. ................................................................................ J-1

J.12. 20230831-NWP-ModLtr-NWS-2022-958, 2pages.................................................... J-1

J.13. 20230831_PmtDrawings_RozaFishScreenReplacement, 12 pages. .......................... J-1

J.14. 20230301-NWP-VerifLtr-NWS-2022-958, 4 pages. ................................................. J-1

J.15. 2021-NWP07-Enclosure-20220511, 25 pages. .......................................................... J-1

J.16. 2021-NWP33-Enclosure-20220511, 26 pages. .......................................................... J-1

J.17. 20221215_CR_DAHP_RozaFishScreenReplacement, 1 page. ................................. J-1

J.18. 20221215-BiOp-NMFS, 11 pages. ............................................................................ J-1

J.19. 20221215_BA_NMFS_RozaFishScreenReplacementRevisedBA, 61 pages ............ J-1

J.20. 20221215-LOC-USFWS, 4 pages. ............................................................................ J-1

J.21. 20221215_BA_USFWS_RozaFishScreenReplacementBA, 68 pages. ..................... J-1

PART IV REPRESENTATIONS AND INSTRUCTIONS....................................................... K-1

SECTION K REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS

OF OFFERORS OR RESPONDENTS ................................................................................... K-1

K.1. 52.203-2 Certificate of Independent Price Determination (Apr 1985) ..................... K-1

K.2. 52.203-18 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements-Representation (Jan 2017) .............................. K-2

K.3. 52.204-8 Annual Representations and Certifications (Mar 2023) ............................ K-3 x

K.4. 52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment (Nov 2021) ................................................................ K-7

K.5. 52.204-26 Covered Telecommunications Equipment or Services-Representation (Oct 2020) .......................................................................................................................... K-10

K.6. 52.209-5 Certification Regarding Responsibility Matters (Aug 2020) .................. K-11

K.7. 52.209-7 Information Regarding Responsibility Matters (Oct 2018) ..................... K-11

K.8. 52.225-25 Prohibition on Contracting With Entities Engaging in Certain Activities or Transactions Relating to Iran—Representation and Certifications (Jun 2020) ................. K-12

K.9. 52.229-11 Tax on Certain Foreign Procurements – Notice and Representation (Jun 2020).. ................................................................................................................................ K-14

SECTION L INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS ......... L-1

L.1. 52.252-1 Solicitation Provisions Incorporated by Reference (Feb 1998) .................. L-1

L.2. 52.203-11 Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions (Sept 2007) ......................................................................................... L-1

L.3. 52.203-18 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements-Representation (Jan 2017) ............................... L-2

L.4. 52.204-7 System for Award Management (Oct 2018) ............................................... L-2

L.5. 52.204-16 Commercial and Government Entity Code Reporting (Aug 2020) .......... L-2

L.6. 52.211-1 Availability of Specifications Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29 (Sep 2023).. ................................................................................................................................... L-2

L.7. 52.211-2 Availability of Specifications, Standards, and Data Item Descriptions Listed in the Acquisition Streamlining and Standardization Information System (ASSIST) (Sep 2023).. ................................................................................................................................... L-2

L.8. 52.211-6 Brand Name or Equal (Aug 1999) .............................................................. L-2

L.9. 52.215-1 Instructions to Offerors – Competitive Acquisitions (Nov 2021) .............. L-2

L.10. 52.215-16 Facilities Capital Cost of Money (Jun 2003) ............................................ L-7

L.11. 52.215-20 Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data (Nov 2021) ........................................................................... L-7

L.12. 1452.215-71 Use and Disclosure of Proposal Information – Department of Interior (Apr 1984) ............................................................................................................................ L-7

L.13. WBR 1452.215-80 Source Selection Evaluation Procedures – Bureau of Reclamation (Mar 2021) ............................................................................................................................ L-7

L.14. WBR 1452.215-81 Proposal Instructions – Bureau of Reclamation (Mar 2021) ...... L-7 xi

L.15. Email Acknowledgement of Amendments, Modifications to Offers, and Withdrawals of Offers – C-PN Region (Apr 2022) ................................................................................. L-11

L.16. WBR 1452.215-86 Intent to Incorporate Technical Proposal -- Bureau of Reclamation (Mar 2021) .......................................................................................................................... L-12

L.17. 52.216-1 Type of Contract (Apr 1984) .................................................................... L-13

L.18. 52.222-5 Construction Wage Requirements – Secondary Site of Work (May 2014)….. ............................................................................................................................. L-13

L.19. 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction (Feb 1999) ..................................................... L-13

L.20. 52.222-56 Certification Regarding Trafficking in Persons Compliance Plan (Oct 2020).. ................................................................................................................................. L-14

L.21. Non-Discrimination Notice to U.S. DOI Contractors, Subcontractors, and Lessors – Bureau of Reclamation - C-PN Region (Jan 2000) ............................................................ L-14

L.22. 52.225-12 Notice of Buy American Requirement-Construction Materials Under Trade Agreements (May 2014) ..................................................................................................... L-15

L.23. 52.228-1 Bid Guarantee (Sept 1996) ....................................................................... L-16

L.24. Invoicing Projection Information – Bureau of Reclamation – C-PN Region (Mar 2002).. ................................................................................................................................. L-16

L.25. 1452.233-2 Service of Protest – Department of Interior (Deviation) (Jul 1996) ..... L-17

L.26. 52.236-27 Site Visit (Construction) (Feb 1995), Alternate I (Feb 1995) ................ L-17

L.27. Site Visit Attendance Restriction – Bureau of Reclamation – C-PN Northwest Region (May 2004) ......................................................................................................................... L-18

L.28. 52.236-28 Preparation of Offers – Construction (Oct 1997) ................................... L-18

L.29. WBR 1452.236-85 Instruction for Mobilization and Preparatory Work Schedule Line Item - Bureau of Reclamation (Mar 2022) ......................................................................... L-18

L.30. 52.252-5 Authorized Deviations in Provisions (Nov 2020) .................................... L-18

SECTION M EVALUATION FACTORS FOR AWARD ................................................ M-1

M.1. WBR 1452.215-84, Evaluation Factors for Award – Quality and Cost/Price Approximately Equal – Bureau of Reclamation (Mar 2021) ............................................. M-1

This page intentionally left blank.

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

Bureau of Reclamation

Pacific Northwest Region

See Administered By Office 98901

R13

CPN Acquisitions - CPN7200

1150 Curtis Rd, Ste 100 Boise, ID 83706

James Everett 2083785181

1x

140R1024R0001

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

FISH SCREEN REPLACEMENT, Roza Diversion Dam, Columbia-Pacific Northwest Region, Yakima, Washington

Estimated Magnitude: $15,000,000.00 to $30,000,000.00

NAICS 237990 Other Heavy and Civil Engineering Construction

Total Small Business Set-Aside, Size Standard $45m

Number of copies the contractor is required to return: One (1) electronic copy

(CD-ROM) must be compatible with Microsoft Office products and/or Adobe PDF.

Proposals submitted by email will not be accepted.

Questions will be accepted up to 7 calendar days after site visit. Questions shall be emailed to James Everett at jeverett@usbr.gov. Questions will be answered via an amendment to the solicitation.

11. The Contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 826 calendar days and complete it within ________________ ________________ calendar days after receiving

FAR 52.211-10

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 8/2014)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

11/16/2023

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

Bureau of Reclamation Pacific Northwest Region

Regional Office Acquisition Management Division

R10

1150 N. Curtis Road, Ste. 100

Boise ID 83706-1234

Colby Clifford

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 3304(a)

STANDARD FORM 1442 (REV. 8/2014) BACK

Continued...

Invoice Processing Platform System US Department of Treasury https://www.ipp.gov

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

140R1024R0001

00010 1 AURoza Diversion Dam Fish Screen Replacement

Price Schedule: CLINS 1 through 6

See the following continuation page(s).

Period of performance is 826 calendar days after issuance of the Notice to Proceed (NTP).

Product/Service Code: Y1PZ

Product/Service Description: CONSTRUCTION OF

OTHER NON-BUILDING FACILITIES

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Yakima Project, Washington Solicitation No. 140R1024R0001

Price Schedule B - 1

CONTINUATION OF

SECTION B – SUPPLIES OR SERVICES AND PRICES

Fish Screen Replacement – Roza Diversion Dam

Yakima Project

Kittitas County, Washington

B.1 PRICE SCHEDULE

(a) Offers will be considered for award on the following Price Schedule, but no offer will be considered for award on only a part of the Price Schedule.

(b) Offers are subject to the terms and conditions of this solicitation.

(c) See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory Work, for CLIN’s 1 and 2.

(d) Definitions:

(1) CLIN – Contract Line Item Number

PRICE SCHEDULE

CLIN Section Supplies or Services Quantity and Unit

Unit Price

Amount

1.

WBR

1452.23 2-81

Phase 1 Mobilization and Preparatory Work

For the lump sum of $

2.

WBR

1452.23 2-81

Phase 2 Mobilization and Preparatory Work

For the lump sum of $

3. 01 31 30 Contract Document Management System

For the lump sum of $

Price Schedule B - 2

PRICE SCHEDULE

CLIN Section Supplies or Services Quantity and Unit

Unit Price

Amount

4. 35 21 16 Procure and Assemble Temporary Bulkheads

For the lump sum of $

5. 35 21 42 Phase 1 Fish Screens For the lump sum of $

6. 35 21 42 Phase 2 Fish Screens For the lump sum of $

TOTAL FOR PRICE SCHEDULE $______________________

END OF SUPPLIES OR SERVICES AND PRICES

BENJAMIN TAYLOR Digitally signed by BENJAMIN TAYLOR Date: 2023.08.07 13:31:41 -06'00'

BYRON VAN ORDEN Digitally signed by BYRON VAN ORDEN Date: 2023.08.08 12:41:43 -06'00'

Signature Sheet/ Certification of Technical Specifications

Project Title: Fish Screen Replacement - Roza Diversion Dam

Region: Columbia Pacific Northwest Interior Region 9

Technical Specifications

Project Title: Fish Screen Replacement - Roza Diversion Dam

4. The person signing the specifications package for "Certified" shall have been in responsible charge of individual components of the overall design including developing or assembling the specifications. In cases where the designs described by the specifications meet the criteria for preparation by a registered engineer or architect, this person shall be registered with the applicable professional designation after their signature, such as P.E. for professional engineer or R.A. for registered architect. By this signature, this person is certifying the written specifications convey the design intent.

Certified: __________________________

Ronald J. Fehringer, P.E.

Task Order Manager

Jacobs Engineering Group

Section 01 35 27 – Underwater Work

Section 01 54 20 – Use of Government

Crane

Section 03 37 26 – Underwater Concrete

Section 03 63 00 – Concrete Doweling for

Tremie Concrete

Section 05 12 43 – Structural Steel

Framing for Cofferdam

Section 31 03 33 – Removal of Water

Section 31 41 16 – Sheet Piling

Section 35 21 16 – Hydraulic Bulkheads

Section 35 21 17 – Cofferdam End Returns

Section 35 21 18 – Cofferdam Closure Wall

Section 35 24 20 – Screeding Sediment

Section 51 00 10 – Photographs

Section 51 32 20 – Example Construction Sequence to Contractor

DIVISION 01 - GENERAL REQUIREMENTS

Summary of Work 01 11 00 - 1

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.01 LOCATION

A. Work is located at Roza Dam on the Yakima River, approximately 10 miles north of Yakima, Washington in Kittitas County.

1.02 PRINCIPAL COMPONENTS OF WORK

A. Care of River during construction, including installation and removal of temporary cofferdam and dewatering systems on the upstream and downstream sides of the intake structure to facilitate other work listed below.

B. Removal of obstructions, including but not limited to: metal trash rack, trash rake guide track, metal handrail.

C. Concrete sawcutting.

D. Concrete removal.

E. Drilling holes for anchor bars and epoxy grouting bars in place.

F. Structural concrete.

G. Metalwork, including:

1. Platforms.

2. Stairs.

3. Handrail.

4. Embedded plates.

H. Electrical and control system.

I. Designing, furnishing, installing fish screen assemblies.

1.03 SPECIFICATIONS REQUIREMENTS

A. Requirements in Division 1, General Requirements, apply to Divisions 2 through 52.

B. Imperative statements in these specifications are Contractor requirements, unless otherwise stated.

Summary of Work 01 11 00 - 2

C. Where specifications are written in streamlined form, words “shall be” are included by inference where a colon (:) is used within sentence or phrase.

1.04 DEFINITIONS

A. When specifications use a word or term defined in Federal Acquisition Regulations (FAR), definition of the word or term shall be in accordance with FAR sections in effect at the time solicitation was issued.

1.05 ACRONYMS

A. The following acronyms apply to specifications Divisions 1 through 52:

1. CO: Contracting Officer.

2. COR: Contracting Officer’s Representative.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION

Construction Sequencing 01 12 40 - 1

SECTION 01 12 40

CONSTRUCTION SEQUENCING

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in Price Schedule for other items of Work.

1.02 CONSTRUCTION PHASES

A. Construct the project in two phases over the course of two construction windows.

1. Phase 1 work will include all Work related to dewatering, demolishing, constructing, and commissioning of the replacement screens in Bay 1 and Bay 2.

2. Phase 2 work will include all Work related to dewatering, demolishing, constructing, and commissioning of the replacement screens in Bay 3, Bay 4, and Bay 5.

1.03 IN-WATER WORK SCHEDULE RESTRICTIONS

A. Perform in-water work during the following time periods:

1. 2024 In-Water Construction Window: October 1, 2024 through March 14, 2025.

2. 2025 In-Water Construction Window: October 1, 2025 through March 14, 2026.

B. The raising and lowering of installed fish screen assemblies is not considered in-water work.

1.04 RESERVOIR DRAWDOWNS DURING CONSTRUCTION

A. When required, request reservoir drawdowns. Comply with Section 01 14 20 – Facility Operations and Conditions.

1.05 INTERIM MILESTONES

A. Comply with specified interim milestones for construction activities.

B. Phase 1:

1. Isolate Bays 1 and 2 from the Yakima River, no later than November 10, 2024.

2. For each fish screen assembly, complete the Track Field Test as specified in

Section 35 21 42 – Fish Screen Assembly, no later than February 8, 2025

3. Remove temporary bulkheads and cut down sheet piles no later than March 11, 2025.

Construction Sequencing 01 12 40 - 2

4. For each fish screen assembly, complete the Fish Screen Assembly Field Performance Test as specified in Section 35 21 42 – Fish Screen Assembly, no later than March 29, 2025.

C. Phase 2:

1. Isolate Bays 3, 4, and 5 from the Yakima River, no later than November 10, 2025.

2. For each fish screen assembly, complete the Track Field Test as specified in

Section 35 21 42 – Fish Screen Assembly, no later than February 16, 2026

3. Remove temporary bulkheads and cut down sheet piles no later than March 11, 2026.

4. For each fish screen assembly, complete the Fish Screen Assembly Field

Performance Test as specified in Section 35 21 42 – Fish Screen Assembly, no later than March 29, 2026.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Yakima Project, Washington Solicitation No. 140R1024R000-

Use of Site 01 14 10 - 1

SECTION 01 14 10

USE OF SITE

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 REFERENCE STANDARDS

A. Bureau of Reclamation (USBR)

1. Cleaning Manual-2012 Inspection and Cleaning Manual for Equipment and Vehicles to Prevent the Spread of Invasive Species (Technical memorandum No. 86-68220-07-05) 2012 Edition Available online at:

http://www.usbr.gov/mussels/prevention

1.03 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 01 14 10-1, Land Use and Landscape Rehabilitation Plan:

1. For each Contractor use site on Government land.

a. Show use location and extent of impact. Uses include but are not limited to the following:

1) Buildings and service areas including offices, shops, warehouses, storage areas, fuel and oil storage areas, and fabrication yards.

2) Parking areas, temporary roads, and haul routes.

3) Utilities including air, power, and water lines; fire hydrants; and compressor station.

4) First-aid and medical facilities.

5) Concrete and aggregate plants. Show sizes, rated capacities, and general features of aggregate processing plant including transporting, storing, screening, and washing facilities; concrete batching and mixing plant; and concrete conveying, placing, and cooling plants.

Use of Site 01 14 10 - 2

6) Areas for processing, storing, and disposing of waste materials from construction operations.

7) Temporary fences.

b. Describe methods to preserve, protect, and repair, vegetation…