B09_-_Amendment_0002_-_Questions_and_Answers_0002.pdf
PDF 124 KB Posted
- Attached to
- WHIS FUEL BREAK RX FY24 Federal contract opportunity
- Solicitation number
- 140PS124R0007
About this file
This document contains Questions and Answers (Q&A) regarding Solicitation/Request for Proposals (RFP) No. 140PS124R0007, Amendment 0002 for the Whiskeytown National Recreation Area - Hand Thinning and Hand Piling Hazardous Fuels Project.
The key details are:
- The Government will supply 4 mil plastic and/or wax paper for the project.
- The contractor is responsible for any permitting and coordination with power companies for work around power lines, erosion control, and developing a safety plan appropriate for the required work.
- The full solicitation has been posted as of July 31, 2024, with a pre-proposal meeting scheduled for August 20, 2024.
- The contracting agency is the Department of the Interior National Park Service.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140PS124R0007_Amd_0002.pdf | ||
| Sol_140PS124R0007_Amd_0001.pdf | ||
| B08_-_Attachment_3_-_Limitations_on_Subcontracting_compliance_worksheet.xlsx | XLSX spreadsheet | |
| Sol_140PS124R0007.pdf | ||
| B08_-_Attachment_2_-_SCA_Wage_Determination_1977-0727_-_Rev_73.pdf | ||
| B08_-_Attachment_4_-_Proposal_Submission_Package_-_140PS124R0007.docx | DOCX document | |
| B08_-_Attachment_1_-_Map_-_Treatment_Areas_1-4_.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation 140PS124R0007 – Amendment 0002
RFP
QUESTIONS & ANSWERS REGARDING:
SOLICITATION/REQUEST FOR PROPOSALS NO. 120PS124R0007
Amendment 0002
Whiskeytown National Recreation Area – Hand Thinning and Hand Piling Hazardous Fuels
Project
(AMENDMENT 0002)
QUESTIONS RECEIVED AS OF 08/26/2024:
1. Question: Who is providing the 4 mil plastic or one sided kraft wax paper for the project?
ANSWER: The Government will supply 4 mil plastic and/or wax paper for this project. See Section
D.42 – Government Furnished Property/Information.
2. Question: We've identified some concerns related to the presence of power lines in the area that will require careful management and permitting. Specifically, we are keen to understand how you plan to address the key challenges surrounding access, erosion control, and working near the utility infrastructure.
Could you provide any guidance on how we should navigate these issues or any specific measures you recommend we take to ensure compliance and safety during the project?
ANSWER: The contractor is responsible for any permitting and coordination with power companies for work around power lines if applicable. Erosion control is a the responsibility of the contractor, and addressed in Section D.20 – Landscape Preservation.
The contractor is responsible for their own safety, and should prepare a plan that is appropriate for all the work required by this solicitation. (see Sections D.6, D.10, D.11, D.25, and D.35).