Statement of Work Summary

This is a Statement of Work (SOW) for elevator inspection, preventive maintenance, and repair services at Boston National Historical Park (BOST), issued by the National Park Service with an effective date of October 27, 2026. The contract is structured as a Base Year plus two Option Years, with five Contract Line Items (CLINs) per performance period: four Firm-Fixed-Price (FFP) CLINs (one per elevator) and one Time & Materials (T&M) CLIN set at $20,000.00 annually for unscheduled and emergency repairs across all four elevators.

The scope covers four passenger elevators at three locations: Marine Barracks (Kone Eco-System traction elevator requiring annual independent certification), Bunker Hill Museum (US Electric Motors traction elevator requiring Massachusetts State inspection), and USS Constitution Museum Buildings 22 and 28 (both Montgomery/Kone hydraulic elevators with inspection requirements to be confirmed via site survey). Each FFP CLIN requires twelve monthly preventive maintenance visits plus one annual certification per elevator, with the contractor providing all labor, tools, materials, and consumables. The contractor must submit written PM reports within five business days of each visit, obtain required Massachusetts elevator licenses and permits, provide 24/7 service capability with a single telephone contact, and maintain detailed maintenance logs. Unscheduled repairs require prior written Contracting Officer's Representative (COR) approval, with emergency responses required within one hour of notification. T&M work is billed at fully burdened hourly rates (regular, after-hours/overtime, and holiday categories to be proposed by offeror) plus materials with a 15% mark-up cap, with invoices due within seven calendar days of work completion. All work must comply with ASME A17.1/A17.3, Massachusetts regulations (520 CMR), OSHA standards, and National Electrical Code requirements.

View the file

Other files

File Type Posted
B03_Attachment_2_-_SCA_Wage_Determination_2015-4047.pdf PDF
Sol_140PP027Q0052.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Elevator Inspection, Preventive Maintenance & Repair Services

Boston National Historical Park (BOST) – National Parks of Boston

PMIS ________ PEPC ________

PROJECT SCOPE & SPECIFICATIONS

NATIONAL PARK SERVICE

October 27, 2026

BOST Elevators – Statement of Work | Page 2

Table of Contents

Section 1.0 Background Section 2.0 Scope Section 3.0 Objectives Section 4.0 Tasks Section 5.0 Delivery of Work Section 6.0 Government-Furnished Property Section 7.0 Security Section 8.0 Place of Performance Section 9.0 Restrictions Section 10.0 Safety Section 11.0 Definitions Section 12.0 Unscheduled Repair Request Form Section 13.0 Preventive Maintenance Task Matrix Section 14.0 Period of Performance & Pricing Schedule Section 15.0 Payment, Warranty & Point of Contact

SECTION 1.0 BACKGROUND

1.1 Boston National Historical Park (BOST), part of the National Parks of Boston, preserves and interprets sites associated with the American Revolution and the nation’s naval history, including the Bunker Hill Monument and Museum and the Charlestown Navy Yard, home of USS Constitution. The Park has four (4) elevators at three (3) locations, as indicated in this SOW.

This is a Federal service contract structured as a Base Year with two (2) Option Years, with five

(5) Contract Line Items (CLINs) per performance period:

• CLINs 00010, 00020, 00030 and 00040 are the Base Year Firm-Fixed-Price (FFP) CLINs — one (1) CLIN per elevator (Elevator Inventory A, B, C and D). Each CLIN is a single annual price covering twelve (12) monthly Preventive Maintenance (PM) visits and one (1) Annual Certification for that elevator.

• CLIN 00050 is the Base Year Time & Materials (T&M) CLIN for unscheduled and emergency repairs for all elevators, set at $20,000.00.

• CLINs 00060, 00070, 00080 and 00090 are the Option Year 1 FFP CLINs (one per elevator), and CLIN 00100 is the Option Year 1 T&M CLIN for all elevators, set at $20,000.00.

• CLINs 00110, 00120, 00130 and 00140 are the Option Year 2 FFP CLINs (one per elevator), and CLIN 00150 is the Option Year 2 T&M CLIN for all elevators, set at $20,000.00.

Purpose of Contract:

1.2 To provide monthly elevator preventive maintenance, inspections and testing; one (1) annual certification and/or Massachusetts State inspection per elevator per year; and unscheduled and emergency repairs, according to the Safety Code for Elevators and Escalators (ASME A17.1), the Safety Code for Existing Elevators and Escalators (ASME A17.3), and Massachusetts elevator regulations (520 CMR). The inspections, testing and repairs are to ensure that the elevators are in good working order and safe for public and employee use.

BOST Elevators – Statement of Work | Page 3

1.3 Firm-Fixed-Price (FFP) will consist of: Regularly Scheduled Preventive Maintenance, Inspection and Testing (one visit per elevator per month, twelve per year) and the Annual Certification for each elevator, maintaining the elevator equipment in good working order to the standards referenced in Sections 1.2, 10.0 and 11.0 and as described in this statement of work.

The Contractor shall propose one (1) all-inclusive annual FFP price per elevator per performance period that combines all twelve (12) PM visits and the Annual Certification.

1.4 Time & Material Unscheduled Repairs (T&M). The Contractor shall provide for the repair of the elevators according to Section 4.3 and the standards referenced in Sections 1.2, 10.0 and

11.0. There is one (1) T&M CLIN per performance period covering all elevators.

All scheduled maintenance, inspections and repairs as described in this section will pertain to the locations listed below. Any repair not included in the standard PM requires prior written COR approval. Unscheduled maintenance shall not exceed a yearly dollar amount of $20,000 and will be billed at the awarded fully burdened hourly rates plus materials. ($20,000 per contract year, cumulative, not per occurrence.) The yearly dollar amounts shall not be rolled over to the next year. Hourly rates shall be indicated for regular hours, after hours/overtime (including weekends), and holidays (see Section 4.6).

A. Marine Barracks Elevator – See Section 2.0 below 21 2nd Ave, Boston, MA 02129-4543 – CLIN 00010, CLIN 00060, CLIN 00110

B. Bunker Hill Museum Elevator – See Section 2.0 below 43 Monument Square, Charlestown, MA 02129 – CLIN 00020, CLIN 00070, CLIN 00120

C. USS Constitution Museum – Bldg. 22 Elevator – See Section 2.0 below Bldg. 22, First Ave, Boston, MA 02129 – CLIN 00030, CLIN 00080, CLIN 00130

D. USS Constitution Museum – Bldg. 28 Elevator – See Section 2.0 below Bldg. 28, First Ave, Boston, MA 02129 – CLIN 00040, CLIN 00090, CLIN 00140

All Elevators (A–D) – Unscheduled & Emergency Repairs (T&M) – CLIN 00050, CLIN

00100, CLIN 00150

The above sites are typically occupied by staff and are open to the public. Service and maintenance scheduling shall be coordinated in advance with the COR during regular working hours of 7:00 am to 4:30 pm, Monday through Friday, excluding Federal holidays.

SECTION 2.0 SCOPE

2.1 The elevators covered under this contract vary in type, age and use. A detailed PM task matrix is provided in Section 13.0 to clarify preventive maintenance expectations. The equipment and locations are described as follows:

Elevator and Equipment Inventory

A. Marine Barracks – 21 2nd Ave, Boston, MA 02129-4543

• Passenger Elevator – Traction

• Manufacturer: Kone · Make: Eco-System · Model: Micro Processor

• Serial Number: FR-1

• Inspection: Will NOT require Massachusetts State Inspection. WILL REQUIRE

Annual Independent Certification.

BOST Elevators – Statement of Work | Page 4

• CLINs: 00010 / 00060 / 00110 (FFP)

B. Bunker Hill Museum – 43 Monument Square, Charlestown, MA 02129

• Passenger Elevator – Traction

• Manufacturer: US Electric Motors · Make: K09-J207-M · Model: EZ40S1HZ

• Serial Number: 1-P-12291

• Inspection: WILL REQUIRE Massachusetts State Inspection.

• CLINs: 00020 / 00070 / 00120 (FFP)

C. USS Constitution Museum – Bldg. 22, First Ave, Boston, MA 02129

• Hydraulic Passenger Elevator

• Manufacturer: Montgomery/Kone · Device ID: 1P2218

• Installed: 3/11/1995 · Landings: 3 · Capacity: 4,500 lbs

• Inspection: TBD — to be confirmed via site survey (Massachusetts State Inspection, Annual Independent Certification, or both).

• CLINs: 00030 / 00080 / 00130 (FFP)

D. USS Constitution Museum – Bldg. 28, First Ave, Boston, MA 02129

• Hydraulic Passenger Elevator

• Manufacturer: Montgomery/Kone · Device ID: 1P9437

• Installed: 3/1/1995 · Landings: 2 · Capacity: 4,000 lbs

• Inspection: TBD — to be confirmed via site survey (Massachusetts State Inspection, Annual Independent Certification, or both).

• CLINs: 00040 / 00090 / 00140 (FFP)

All four (4) elevators are covered under the T&M CLIN for unscheduled and emergency repairs (CLINs 00050 / 00100 / 00150). Offerors shall price the annual certification for Elevators C and D based on the requirement confirmed at the site survey; if the confirmed requirement changes after award, it will be addressed under Section 15.4 (Change Management).

2.2 Additional Elevators Added During the Contract Period. The Government may, at its discretion, identify additional elevators for coverage under this contract after award (for example, elevators at other NPS/BOST locations not identified in this SOW). No work on, and no costs for, any additional elevator shall be performed or incurred prior to execution of a bilateral contract modification adding that elevator to the contract. For any additional elevator, the Contractor shall provide, within ten (10) business days of the Government’s written request:

• A proposed annual FFP price covering twelve (12) monthly PM visits and one (1) Annual Certification, consistent with the FFP CLIN structure in Section 14.0, reflecting the applicable inspection requirement (Massachusetts State Inspection, Annual Independent Certification, or both); and

BOST Elevators – Statement of Work | Page 5

• Confirmation that the additional elevator will be covered under the existing T&M CLIN at the labor rates already established for the applicable performance period, with no separate T&M rate required.

Proposed pricing is subject to review, negotiation and acceptance by the Contracting Officer and shall be incorporated only via a signed bilateral modification, which will assign the additional elevator its own CLIN(s).

SECTION 3.0 OBJECTIVES

3.1 The Contractor shall provide monthly equipment evaluation, preventive maintenance, inspection and testing; one (1) annual certification and/or Massachusetts State inspection per elevator; and unscheduled service repairs necessary to maintain the elevators in good working order (as defined in Section 11.0). The Contractor shall maintain a cumulative maintenance log for each elevator of all monthly visits, annual certifications and repairs, and shall submit an annual summary report of all twelve (12) PM visits per elevator to the COR at the end of each contract year, detailing work performed, parts replaced, and any deviations from standard maintenance.

SECTION 4.0 TASKS

4.1 Tasks: Preventive Maintenance (FFP) [Reference: See PM Task Matrix in Section 13.0]

1. The Contractor shall provide Preventive Maintenance (PM) including all labor, travel, tools, equipment and consumables for one (1) complete PM visit per elevator each calendar month — twelve (12) visits per elevator per contract year — coordinated in advance with the COR.

2. Each monthly PM visit shall include: inspection, lubrication, adjustment and calibration of all mechanical and electrical components; inspection, testing and adjustment of landing doors, sills and frames at each floor level; safety system checks and testing, including emergency systems, brakes and door operations;

electrical wiring, control panel and safety system inspections; and verification of compliance with all applicable building codes and elevator safety regulations.

3. PM visits shall not be combined, deferred or skipped without prior written COR approval; any approved deferral must be made up within the same contract year.

4. The Contractor shall submit a written PM report to the COR within five (5) business days of each monthly visit and shall update the maintenance log for that elevator following each visit.

5. All work shall be performed by qualified, licensed and certified elevator technicians.

The Contractor shall provide proof that mechanics are currently licensed in the Commonwealth of Massachusetts to work on elevators.

6. The Contractor shall provide 24-hour, seven-day-a-week service capability for all properties pertaining to this contract and shall maintain a single telephone number for receipt of service calls.

7. The Contractor shall obtain all necessary permits and licenses prior to commencement of any work, and shall provide proof of required insurance to the Contracting Officer after award.

BOST Elevators – Statement of Work | Page 6

4.2 Details of Annual Certification (FFP)

One (1) certification/inspection event per elevator per contract year is included in each elevator’s FFP CLIN: Annual Independent Certification for the Marine Barracks Elevator;

Massachusetts State Inspection for the Bunker Hill Museum Elevator; and the requirement confirmed via site survey for the USS Constitution Museum Bldg. 22 and Bldg. 28 Elevators.

The Contractor shall be responsible for:

1. Scheduling, coordination and completion of the required annual certification / inspection, including all associated testing and inspector fees.

2. Preparation and submission of all associated certification and/or inspection documentation to the COR and applicable authorities.

3. Coordination with the applicable State inspector or third-party certifying entity.

4. Remediation of any minor deficiencies identified during the certification, where within the FFP scope.

5. Replacing the old inspection tag within each elevator with an updated inspection tag showing dates of compliance (within 24 hours of the inspection).

6. Providing a written quote to the COR within 24 hours for repairs resulting from inspection findings outside of the FFP requirement.

4.3 Unscheduled Repair Procedures (Service Calls) – Time and Materials (for items not included in the Preventive Maintenance component of the contract) The Contractor is to perform all work necessary to restore inoperable or damaged equipment and systems to normal function, provided the total cost does not exceed the annual $20,000 T&M amount for the performance period (cumulative across all four elevators, not per occurrence). All T&M work requires prior written approval from the COR before work may commence; work performed without COR authorization will not be reimbursed. The Contractor shall submit a written scope of work and cost estimate — including labor hours by rate category and an itemized materials list — to the COR for review and approval prior to commencing work, within the timeframe required by Section 4.5. Emergency conditions posing an immediate safety risk must be reported to the COR by phone immediately, followed by written documentation within one (1) business day. If the confirmed annual inspection requirement for an USS Constitution Museum elevator is not covered within its FFP CLIN, that inspection may be charged against the T&M CLIN with COR approval.

THE CONTRACTING OFFICER IS THE ONLY PERSON AUTHORIZED TO APPROVE ANY

WORK EXCEEDING $20,000 IN A PERFORMANCE PERIOD.

4.4 Service Call Reception:

During regular working hours (as defined in Section 11.0), the COR will notify the Contractor via telephone or email of all service calls and will then provide an Unscheduled Repair Request Form, as shown in Section 12.0, which shall be completed by the Contractor and signed by the COR to authorize the work described. After regular working hours, including weekends and holidays, the COR will contact the Contractor by telephone, verbally identify the issue, and follow up with the Unscheduled Repair Request Form. Service calls shall be considered “received” on the date and time the call is placed by the COR.

4.5 Service Call Response, Quote and Invoice Timeframes:

The following timeframes apply to all work performed under this contract and are in addition to any other deadline stated elsewhere in this SOW:

BOST Elevators – Statement of Work | Page 7

• 4.5.1 Emergency Service Calls: The Contractor shall respond to an emergency repair call within one (1) hour of notification from the COR, and work until the issue is resolved or remediated to a non-emergency condition.

• 4.5.2 Repair Quotes: The Contractor shall submit a written quote and cost estimate for the required repair to the COR within twenty-four (24) hours of the Contractor’s on-site inspection of the reported issue.

• 4.5.3 Invoicing: The Contractor shall submit invoices for all completed work — whether billed under an FFP CLIN or the T&M CLIN — within seven (7) calendar days of completion of that work.

4.6 Labor Rates:

Labor rates applicable to the Unscheduled Repair Time and Materials CLINs: the fully burdened labor rates below are applicable to work orders authorized under this contract. The rates include all direct labor and indirect costs applicable to that direct labor (such as fringe benefits, overhead, G&A, driving to and from job site, vehicle wear and tearr, etc.) and profit. Rates shall, at a minimum, meet the applicable Service Contract Act wage determination. No rate categories other than those listed below will be recognized for payment.

Rate Category Hours Covered Base Year ($/hr)

Option Year 1 ($/hr)

Option Year 2 ($/hr)

Regular Hours 7:00 AM – 4:30 PM, Monday–Friday (non-holiday) $________ $________ $________

After Hours / Overtime 4:30 PM – 7:00 AM; all day Saturday & Sunday $________ $________ $________

Holiday Hours All Federal Holidays (midnight to midnight) $________ $________ $________

4.7 Material Costs and Mark-Up:

• Material mark-up is capped at 15% above the Contractor’s actual invoice cost.

No exceptions will be made.

• The Contractor shall provide the COR with itemized quotes and vendor receipts for all materials used on T&M repairs. Receipts and supporting documentation must be submitted with each invoice; invoices lacking documentation will not be processed for payment.

• No mark-up will be allowed on materials for which receipts are not provided.

4.8 Performance Penalties for Non-Compliance:

The Contractor is subject to deductions from amounts otherwise payable and/or other remedies available to the Government if it fails to meet the timeframes in Section 4.5. The Government may withhold or delay acceptance of the applicable PM report, quote or invoice; assess a deduction from the amount otherwise payable for the affected service period; and document the failure as a performance deficiency affecting the Contractor’s rating under Section 5.3 for: (1) failure to respond to an emergency repair call within one (1) hour; (2) failure to submit a written repair quote within twenty-four (24) hours of inspection; or (3) failure to submit an invoice within seven (7) calendar days of completion of the applicable work. Repeated or uncured failures may result in further remedies under the terms of the contract, up to and including termination for default.

BOST Elevators – Statement of Work | Page 8

SECTION 5.0 DELIVERY OF WORK

5.1 All inspections, testing and work performed on the elevator equipment shall comply with ASME A17.1 / A17.3, Massachusetts elevator regulations (520 CMR), OSHA standards, the National Electrical Code, and manufacturer specifications.

5.2 Inspection, Test Results and Work Performed (Deliverables):

Monthly PM (per elevator, per month)

• Written PM report within five (5) business days of each visit documenting work performed, observations and corrective actions.

• Updated maintenance log entry following each visit; documentation of parts replaced, adjusted or recommended for future replacement.

• Annual summary of all twelve (12) PM visits, submitted at the end of each contract year.

Annual Certification (per elevator, per year)

• Massachusetts State Inspection certificate (Bunker Hill Museum Elevator); Annual

Independent Certification documentation (Marine Barracks Elevator); applicable certification/inspection documentation for USS Constitution Museum Bldg. 22 and Bldg. 28 Elevators.

• Copies of all certification documentation submitted to regulatory authorities; updated inspection tag posted in each elevator within 24 hours of inspection.

• Written quote within 24 hours for repairs resulting from inspection findings outside of the FFP requirement.

T&M Repairs

• Written cost estimate and scope of work submitted to the COR prior to each repair.

• Itemized invoice detailing labor hours by technician, date and rate category (regular / after-hours / holiday), with vendor receipts for all materials.

• Repair completion report describing diagnostic findings, work performed and parts replaced; emergency response logs for any after-hours or holiday calls.

5.3 Acceptance Criteria. Work will be considered complete and acceptable when: all twelve

(12) monthly PM visits per elevator are completed on the agreed schedule; all mechanical, electrical and safety systems function correctly as demonstrated during each monthly inspection; all required inspections and certifications have been completed and certificates provided to the COR; all reports, logs and deliverables have been submitted on time and accepted; no outstanding defects or deficiencies remain unresolved at the close of each service period; and the COR has documented in writing that the work has been performed at a fully successful level.

SECTION 6.0 GOVERNMENT FURNISHED PROPERTY

6.1 The Government will furnish no materials, tools or equipment. All materials and tools are Contractor furnished from outside the park. No on-site storage is available to the Contractor at any work location; the Contractor is responsible for all material logistics.

BOST Elevators – Statement of Work | Page 9

SECTION 7.0 SECURITY

7.1 Prior to starting work on any elevator, the Contractor shall contact the COR to coordinate site access. All scheduled monthly PM visits and annual inspections shall be coordinated in advance with the COR to avoid conflicts with NPS operations and public programming.

7.2 Contractor personnel shall comply with all NPS and BOST site-specific security and access requirements at each location, including partner-operated facilities (USS Constitution Museum).

SECTION 8.0 PLACE OF PERFORMANCE

8.1 CONTRACTOR’S USE OF PREMISES:

1. Work will be performed at the four (4) elevator locations listed in Sections 1.0 and 2.0

(Charlestown, MA).

2. The Contractor is responsible for all parking arrangements and costs at all work sites. Vehicles shall be parked so as not to block fire lanes or visitor traffic.

3. Awardees are welcome to use restroom facilities at most NPS park buildings; access will be made available upon request.

4. All work shall be completed in such a way as to create no damage and to protect the surrounding property, exhibits and historic fabric.

SECTION 9.0 RESTRICTIONS

9.1 No on-site storage is available to the Contractor at any work location.

9.2 All work must be coordinated in advance with the COR to avoid conflicts with NPS operations and public programming. The sites are staffed and open to the public; work shall be arranged so as not to interfere with the conduct of Government business or visitor use.

9.3 No T&M work may begin without prior written authorization from the COR. The COR does not have authority to authorize changes to contract scope or price.

9.4 Monthly PM visits must be completed within the applicable calendar month and may not be carried over to the following month without prior written COR approval. All work must be completed within the period of performance unless mutually agreed otherwise in writing by the Contracting Officer.

9.5 Confidentiality. Both parties shall maintain the confidentiality of all proprietary or sensitive information disclosed in connection with this contract and shall not disclose such information to third parties without the prior written consent of the disclosing party, except as required by law or regulation.

SECTION 10.0 SAFETY

10.1 All work shall be performed according to the safety guidelines of the following:

• Safety Code for Elevators and Escalators (ASME A17.1) / Safety Code for Existing Elevators and Escalators (ASME A17.3), or equivalent.

• Massachusetts State elevator inspection and certification requirements (520 CMR).

• Occupational Safety and Health Administration (OSHA) regulations.

• Applicable Federal, State and local building codes and regulations.

BOST Elevators – Statement of Work | Page 10

• Manufacturer specifications and maintenance guidelines.

• NPS and BOST site-specific safety rules and access requirements, and any other standards specified by the COR or required by regulatory authorities.

SECTION 11.0 DEFINITIONS

Emergency Service Call: A service request requiring a Contractor response within one (1) hour of notification from the COR in order to address passenger entrapment, life-safety conditions, or prevent damage to equipment.

Repair Quote: A written scope of work and cost estimate, including labor hours by rate category and an itemized materials list, submitted to the COR within twenty-four (24) hours of the Contractor’s on-site inspection.

Contracting Officer (CO): The only Government official authorized to make changes to contract scope or price, and to approve T&M work exceeding $20,000 in a performance period.

Contracting Officer’s Representative (COR): The Government’s authorized representative and the primary point of contact for scheduling, acceptance of deliverables, and written authorization of unscheduled repair work under this contract.

Traction Elevator: An elevator in which the car is raised and lowered by hoist ropes driven by a traction machine.

Hydraulic Elevator: An elevator system operated by hydraulic fluid under pressure to raise and lower the car.

Preventive Maintenance (PM): Scheduled monthly maintenance, inspection and testing performed to reduce the likelihood of equipment failure and ensure safe and reliable operation.

Annual Certification: The one (1) annual Massachusetts State Inspection and/or Annual Independent Certification required for each elevator, including associated testing, documentation and posting of an updated inspection tag.

Downtime: The total period during which an elevator is inoperable or otherwise unavailable for use.

11.1 Working Hours:

• Regular Hours: Monday through Friday, 7:00 AM to 4:30 PM, excluding Federal holidays.

• After Hours / Overtime: 4:30 PM to 7:00 AM Monday through Friday, and all day

Saturday and Sunday.

• Holiday Hours: All Federal holidays (24 hours, midnight to midnight).

BOST Elevators – Statement of Work | Page 11

SECTION 12.0 UNSCHEDULED REPAIR REQUEST FORM

I. Service Request (Call) Authorization

Date & Time of Notification: ______________________

Call the COR upon arrival for sign-in and site access.

Equipment and Location: __________________________________

Contract Line Item #: ____________________

[ ] Emergency [ ] Routine Description of Problem / Status / Comments:

COR or Designated Representative Signature and Date: ____________________

TO BE COMPLETED BY CONTRACTOR AS APPLICABLE

II. Cost and Price Estimates

Attach detailed estimates (labor hours by rate category and itemized material costs) as required by Sections 4.3 and 4.5 of this Statement of Work. Quote due within 24 hours of on-site inspection.

III. Service Call Reporting (Use Attachments as Necessary)

Date & Time of Response (Arrival): ____________________

Date & Time Work Commenced: ____________________

Date & Time Work Completed: ____________________

Individual(s) Performing Service: ______________________________________

Work Performed: _______________________________________________________

Number of Hours Expended by Rate Category (Regular / After Hours / Holiday):

Material Cost (attach vendor receipts; mark-up not to exceed 15%): ______________

Work Complete: [ ] Yes [ ] No

IV. Government Comments: ______________________________________________

COR or Designated Signature and Date: ______________________________

BOST Elevators – Statement of Work | Page 12

SECTION 13.0 PREVENTIVE MAINTENANCE TASK MATRIX

13.1 General Requirements

The Contractor shall furnish all labor, supervision, tools, materials, equipment and incidentals necessary to perform preventive maintenance (PM) services for all covered elevators in accordance with this contract, applicable Federal, State and local codes, and manufacturer recommendations. All PM services shall be performed by qualified and properly licensed personnel. Work shall be performed in a manner that ensures safe, reliable and continuous operation of the equipment.

13.2 Preventive Maintenance Tasks

The Contractor shall perform the tasks identified in the table below at the frequencies indicated, for each elevator. Failure to perform required PM tasks in accordance with this section may be considered nonconforming performance.

Task Frequency Responsible Party Documentation Required

Inspect, lubricate, adjust and calibrate all mechanical and electrical components (machine / pump unit, guide rails, governor, controller)

Monthly Contractor Electronic maintenance log and PM report submitted to the COR

Inspect, test and adjust landing doors, sills and frames at each floor level Monthly Contractor Electronic maintenance log and

PM report submitted to the COR Safety system checks and testing, including emergency systems, brakes and door operations

Monthly Contractor Electronic maintenance log and PM report submitted to the COR

Electrical wiring, control panel and safety system inspections Monthly Contractor Electronic maintenance log and

PM report submitted to the COR Verify compliance with applicable building codes and elevator safety regulations

Monthly Contractor Electronic maintenance log and PM report submitted to the COR

Annual Independent Certification – Marine Barracks Elevator Annually Contractor

Certification documentation submitted to the COR; updated tag posted

Massachusetts State Inspection – Bunker Hill Museum Elevator Annually Contractor

State inspection certificate submitted to the COR; updated tag posted

Annual certification / inspection (as confirmed) – USS Constitution Museum Bldg. 22 & Bldg. 28 Elevators

Annually Contractor Certification / inspection documentation submitted to the COR; updated tag posted

Annual summary of all twelve (12) PM visits per elevator Annually Contractor Annual summary report submitted to the COR

13.3 Documentation and Records

The Contractor shall maintain complete and accurate records of all preventive maintenance activities, inspections and tests performed under this contract for the duration of the contract. All documentation shall be submitted to the COR in electronic format unless otherwise directed.

Maintenance records shall include, at a minimum:

BOST Elevators – Statement of Work | Page 13

• Date and time of service

• Description of work performed

• Identification of equipment serviced

• Name and qualification of technician performing the work

• Notation of deficiencies identified, and corrective actions taken or recommended

SECTION 14.0 PERIOD OF PERFORMANCE & PRICING SCHEDULE

14.1 Period of Performance

Period Duration Base Year Begins on the date of contract award and continues for twelve (12) months.

Option Year 1 Begins immediately upon expiration of the Base Year and continues for twelve (12) months — exercisable at the Government’s discretion.

Option Year 2 Begins immediately upon expiration of Option Year 1 and continues for twelve (12) months — exercisable at the Government’s discretion.

Option years will be exercised only if: (1) funds are available and appropriated, and (2) the Contractor’s performance has been rated at a fully successful level or higher for the preceding period of performance. All period-of-performance dates are keyed to the date of contract award.

14.2 Pricing Instructions

• Each performance period contains five (5) CLINs: four (4) FFP CLINs (one per elevator) and one (1) T&M CLIN covering all elevators.

• For each FFP CLIN the offeror shall enter one (1) annual firm-fixed price for that elevator that combines all twelve (12) monthly PM visits and the one (1) Annual Certification (Unit = YR, Qty = 1). The price shall be fully burdened and all-inclusive of labor, travel, tools, equipment, consumables, inspection/certification fees, overhead, G&A and profit. No additional charges or supplemental invoices will be accepted for services covered under any FFP CLIN.

• The T&M CLIN in each period is a set amount of $20,000.00 for all elevators and is pre-filled; offerors do not price it. Offerors shall provide fully burdened hourly rates in Section 4.6, which will be used to bill actual work against the T&M amount.

BOST Elevators – Statement of Work | Page 14

SECTION 15.0 PAYMENT, WARRANTY & POINT OF CONTACT

15.1 FFP Payments (CLINs 00010–00040, 00060–00090, 00110–00140). Each elevator’s annual FFP price shall be invoiced in twelve (12) equal monthly installments (1/12 of the annual CLIN price), payable upon completion of that month’s PM visit and acceptance of the PM report by the COR. One (1) invoice per elevator per month shall be submitted, referencing the applicable CLIN, elevator location, performance period and month of service. The final (twelfth) installment for each elevator will not be paid until the Annual Certification for that elevator has been completed and the certificate or inspection documentation accepted by the COR. No payment will be made for a PM visit that has not been documented by an accepted PM report.

15.2 T&M Payments (CLINs 00050, 00100, 00150). Payment shall be based on actual hours expended at the applicable approved rate category and actual material costs plus the allowable mark-up (not to exceed 15%), up to the $20,000.00 amount per performance period. All invoices must include the description of work performed and the COR written authorization reference;

labor hours by technician name, date and rate category; an itemized list of materials with unit and total costs; and vendor receipts for all materials. The Contractor shall submit invoices within seven (7) calendar days of completing the applicable work. The Government shall process payment in accordance with the Prompt Payment Act.

15.3 Warranty. The Contractor warrants that all work performed under this contract will be free from defects in materials and workmanship, comply with all applicable codes, standards and regulations, meet the performance specifications agreed upon by both parties, and be covered under a one (1) year replacement warranty. Equipment warranties provided by manufacturers shall be passed through to the Government and documented as part of project deliverables.

15.4 Change Management. Any changes to this Statement of Work, PM schedule, performance schedule or deliverables must be documented through a formal bilateral modification between the Contractor and the Contracting Officer. Changes to any FFP CLIN will be implemented only upon execution of a written contract modification signed by both parties.

Finalization of the TBD inspection requirements for the USS Constitution Museum elevators shall follow this same process if it results in a change to CLIN scope or price.

15.5 Point of Contact – Contracting Officer’s Representative (COR / NPS POC) Role Contact

Name TBD at time of award Phone TBD at time of award Email TBD at time of award

SECTION 1.00BACKGROUND
SECTION 2.00SCOPE
SECTION 3.00OBJECTIVES
SECTION 4.00TASKS
4.1 Tasks: Preventive Maintenance (FFP) [Reference: See PM Task Matrix in Section 13.0]
4.2 Details of Annual Certification (FFP)
4.3 Unscheduled Repair Procedures (Service Calls) – Time and Materials (for items not included in the Preventive Maintenance component of the contract)
4.4 Service Call Reception:
4.5 Service Call Response, Quote and Invoice Timeframes:
4.6 Labor Rates:
4.7 Material Costs and Mark-Up:
4.8 Performance Penalties for Non-Compliance:
SECTION 5.00DELIVERY OF WORK
SECTION 6.00GOVERNMENT FURNISHED PROPERTY
SECTION 7.00SECURITY
SECTION 8.00PLACE OF PERFORMANCE
SECTION 9.00RESTRICTIONS
SECTION 10.00SAFETY
SECTION 11.00DEFINITIONS
SECTION 12.00UNSCHEDULED REPAIR REQUEST FORM
SECTION 13.00PREVENTIVE MAINTENANCE TASK MATRIX
SECTION 14.00PERIOD OF PERFORMANCE & PRICING SCHEDULE
SECTION 15.00PAYMENT, WARRANTY & POINT OF CONTACT