This is a Statement of Work (SOW) for the replacement of a water supply and return line at the WEAR Maintenance Shop in Kotzebue, Alaska. The project involves installing a new water line to address a critical failure in the existing copper supply line, which is causing water leakage and operational disruptions. The contractor will be responsible for site assessment, excavation, installation of the new water supply and return line, and restoration of the work area, with all work to be completed by September 30, 2025.

The solicitation (No. 140P9725R0004) is issued by the Department of the Interior National Park Service Alaska Region, with the project located at 297 Mission Street in Kotzebue. The contractor must use materials compatible with local public works department recommendations, obtain necessary site access passes, and provide a detailed completion report including as-built drawings and warranties. The government will provide worksite access and infrastructure information, and no special security clearance is required for the project.

View the file

Other files for this federal contract opportunity

Other files attached to REPLACE WATER LINE MAINT SHOP 297F, newest first.
File Type Posted
Sol_140P9725R0004_Amd_0003.pdf PDF
Sol_140P9725R0004_Amd_0002.pdf PDF
Sol_140P9725R0004_Amd_0001.pdf PDF
As-Built_Drawing_0001.pdf PDF
Specifications.docx DOCX document
Sol_140P9725R0004.pdf PDF
Wage_Determination.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Background This project involves the installation of a new water supply and return line for the WEAR Maintenance Shop to address a critical failure in the existing copper supply line. The current copper line has developed a significant break, causing water leakage and discharge into the building, creating operational disruptions and potential structural damage. The water supply is being shut off until the new line can be installed. This work is necessary to restore reliable water access for essential maintenance operations. The installation will be performed by an outside contractor with the necessary expertise during the summer of FY25.

· Purpose/relationship to other projects: The installation of the new water supply line is critical for the operational efficiency of the WEAR Maintenance Shop, which requires reliable water access to maintain tools and equipment used in park maintenance activities.

· Statutory/regulatory foundation: The work will be conducted in compliance with applicable federal, state, and local regulations relevant to construction and public works projects.

· Background materials: The existing condition of the current copper water supply line has been documented, indicating the failure points and the necessity for a complete replacement.

Objectives

· Goals and objectives of the contract effort: The contractor will install a new water supply and return line, ensuring that all work meets safety and quality standards as specified by the National Park Service and relevant regulations.

· Intended use of the results or end products: The new water supply line will provide reliable water access for maintenance operations at the WEAR Maintenance Shop, facilitating efficient and effective work practices.

Scope

The scope of this contract encompasses the installation of a new water supply and return line for the WEAR Maintenance Shop. The work includes excavation, installation of the new line, connection to existing systems, testing for functionality, and restoration of the work area to original conditions.

Tasks

3.1. Task Areas

· Task 3.1.1: Site Assessment

· Task 3.1.2: Excavation and Preparation

· Task 3.1.3: Installation of New Water Supply and Return Line

· Task 3.1.4: Restoration and Cleanup

3.1.1 Task 1 – Site Assessment

· The contractor shall assess the current water supply line condition and prepare a site plan for the new installation, documenting existing conditions and identifying any potential complications.

3.1.2 Task 2 – Excavation and Preparation

· The contractor shall perform excavation for the installation of the new water supply and return line while protecting existing utilities and structures.

3.1.3 Task 3 – Installation of New Water Supply and Return Line

· The contractor shall install the new water supply and return line using durable, quality materials that meet all relevant standards.

3.1.4 Task 4 – Restoration and Cleanup

· The contractor shall restore the area affected by construction, including backfilling the excavation site and ensuring the work location is clean and orderly upon completion.

Delivery

· Deliverables:

· Completed installation of the new water supply and return line.

· A detailed report on the installation process and any variations from planned specifications.

· Delivery time: The contractor shall complete the installation by October FY25.

· Delivery location: The installation work will occur at the WEAR Maintenance Shop (DQ Shop).

· Supporting documentation: The contractor shall provide a completion report, including as-built drawings, warranties for materials and workmanship, and any manuals for maintenance.

· Additional information: The contractor shall schedule a final walkthrough with the designated park representative to confirm project completion.

Government-Furnished Property, Material, Equipment, or Information (GFP, GFM, GFE, GFI)

The government will provide access to the worksite and existing infrastructure information as necessary for the contractor to perform their work effectively.

Security Considerations

· Special pass or identification requirements: The contractor must obtain the necessary site access passes for all personnel working on the project.

· Special security clearance requirements: No special security clearance is required for this project.

Travel

The contractor shall arrange and bear all costs associated with travel to and from the project site.

Special Material Requirements and Considerations

The contractor must use materials that are compatible with the recommended material from the local city public works department.

Other Unique Requirements

The contractor shall follow all safety regulations and best practices while performing excavation and construction activities to minimize risk to personnel and the site.

Place of Performance

The work will be performed at the WEAR Maintenance Shop located at 297 Mission street Kotzebue Alaska 99752.

Period of Performance

The contractor shall complete all work within the summer of FY25, with the project expected to be concluded by September 30, 2025.

[Disclaimer: This template is strictly for support purposes; it may not be applicable to all acquisitions and its precision and thoroughness are not assured. Contract Specialists should consult relevant regulations and/or Department or Bureau policies for amplifying details and guidance.] image1.png