Sol_140P8524Q0065_Amd_0001.pdf
PDF 139 KB Posted
- Solicitation number
- 140P8524Q0065
About this file
This document is an amendment to Solicitation Number 140P8524Q0065 for the Big Oak Flat Road and Pohono Bridge Road Striping project in Mariposa County, California.
The key details are:
- The Statement of Work has been revised, with changes to the work location and maps.
- The prevailing wage determination has been updated to CA20240018, dated July 5, 2024.
- The request for quotes (RFQ) due date has been extended to July 19, 2024 at 2:00 PM PT.
- The government provided responses to 9 contractor questions, covering topics such as debris removal, staging areas, vegetation overgrowth, hash area striping, work hours, traffic control, and paint specifications.
The solicitation is issued by the Department of the Interior, National Park Service. Responses are due by the revised deadline of July 19, 2024.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140P8524Q0065 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
PPO
San Francisco CA 94104 Suite 500 333 Bush Street
DOI, NPS, PWR - SF/SEA MABO
PPO
San Francisco CA 94104 Suite 500 333 Bush Street
NPS, PWR - SF/SEA MABO
07/11/20240001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
06/14/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Timothy Modjeski
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
140P8524Q0065 Amendment 0001
The purpose of this amendment is to revise specification and answer contractor questions.
A. Replace the original Statement of Work with the attached revised Statement of Work in its entirety.
a. Summary of changes: The work location and maps have been added to the original Statement of Work
B. Replace the original wage determination with the attached wage determination, CA20240018, dated July 5, 2024, it its entirety.
C. The RFQ due date has been extended and the solicitation now reads quotes are due on July 19, 2024, at 1400 PT.
D. Below are the answers to contractor questions.
Question 1: Will the government sweep prior to striping activities for removal of excessive debris?
NPS Response: No, sweeping costs should be included in estimate.
Question 2: Can the government provide the staging location for materials?
NPS Response: A staging area will be provided to the awardee. The staging area location will be released at pre-construction meeting.
Question 3: Is there any overgrowth of vegetation that will need to be removed prior to shoulder striping?
NPS Response: No, all overgrowth will be removed by NPS prior to the contract work performance.
Question 4: Will any hash areas need to be striped?
NPS Response: The hash areas will not be painted.
Question 5: The Solicitation states that the working hours are from 7am to 4pm and the Statement of Work states that the working hours will be 8pm to 6am. What working hours is the contractor to follow?
NPS Response: This work will need to be performed at night 8 PM to 6 AM.
140P8524Q0065 Amendment 0001
Question 6: Will the government require a prewarning vehicle ahead of the striping operation? The contractor will be responsible for traffic control to avoid tracking and therefore a prewarning vehicle is not necessary.
NPS Response: The contractor will be responsible for traffic control to avoid tracking and therefore a prewarning vehicle is not necessary.
Question 7: For the Centerline Broken Marking (White or Yellow), The quantities provided do they include the gaps in the skip line?
NPS Response: Yes, the quantities provided include the gaps in the skip line.
Question 8: Will there be any new asphalt surfaces that will require two coats of paint?
NPS Response: No, there will not be any new surfaces requiring two coats of paint.
Question 9: What type of waterborne paint is required, Type B or C ?
NPS Response: Type B is preferable due to the dry times being faster, but waterborne paint is acceptable.