Riprap SOW
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P8318Q0085_Amd_0001.pdf | ||
| Sol_140P8318Q0085.pdf | ||
| Rock_Delivery_Vicinity_Map.docx | DOCX document | |
| Bid_sheet-R9455180062.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Furnish & Deliver Rock 140P8318Q0085
White River Campground Road – Supply & Deliver Rock Mount Rainier National Park
SCOPE
The requirement is to supply and deliver Riprap rock to sites along the White River Campground road. Multiple deliveries between 9/17/2018 and 10/19/2018 will be required and must be coordinated with the point-of-contact (POC) on award. Park employees will be doing the rock placement.
Rock sizes are as follows:
Class 5 Riprap (Five-man rock) – 365 tons Class 4 Riprap (Four-man rock) – 1215 tons Class 2-3 Riprap (Two to Three man rock) – 850 tons
PROJECT LOCATION
White River Campground Road is located approximately 44 miles south of Enumclaw, WA and approximately 6 miles west of the intersection of SR 410 and Sunrise Park Road. The rock delivery locations are within the wide pullouts on the south side of the White River Campground Road approximately 0.5 to 0.65 miles beyond the junction with the Sunrise Road. Park employees will be doing the rock placement.
SPECIFICATIONS
Riprap rock shall be hard, durable, angular rock that is resistant to weathering and water action and free of organic or other unsuitable material. Rock shall be free of overburden, spoil, shale, and organic material. Do not use shale, rock with shale seams, or other fissile of fissured rock that may break into smaller pieces in the process of handling and placing.
The Contractor is required to provide materials free of noxious weeds. The term “noxious weed” includes all plant species that have been declared noxious in the jurisdiction (Federal, State, and county) where the material source is located, but also includes all plant species on the Washington State Noxious Weed List and Pierce County Noxious Weed List.
HAULING RESTRICTIONS
No deliveries shall take place on holidays or weekends without prior approval of the Contracting Officer. Period of Performance is anticipated to be Sept 17 through Oct 19, 2018, Monday through Thursday, 6 am to 5:00 pm. Traffic control will be provided by NPS employees during the rock delivery.
Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent.
MEASUREMENT AND INVOICING
Each truckload of materials shall be accompanied by a delivery ticket showing the date, product, weight (as determined by a certified scale), and delivery location. Invoices shall summarize deliveries by product and be supported by signed delivery tickets. Payment will be based on actual quantity delivered. Payment will be by EFT, direct deposit. Partial payments for items delivered will be allowed.