Price_Schedule_-_Asbestos_Abatement.xlsx
XLSX spreadsheet 31 KB Posted
- Attached to
- Asbestos Abatement @ INDU
- Solicitation number
- 140P6425Q0056
About this file
The document is a Price Schedule for an Asbestos Abatement project at Indiana Dunes National Park for the U.S. Department of Interior National Park Service. The price schedule is a blank template with line items for mobilization/demobilization, removal and disposal of floor tiles and black mastic, broken down into materials, equipment, and labor categories. The associated federal contract opportunity (Solicitation Number 140P6425Q0056) is a small business set-aside project with a value under $25,000, seeking a contractor to remove and dispose of floor tiles and black mastic at the park location in Chesterton, IN.
Key contract details include a firm-fixed price contract type, Construction Wage Rate Requirements for Porter County, IN, and evaluation criteria of price, technical merit, and prior experience. Potential contractors must have a Unique Entity Identifier (UEI) number, be registered and active in the System for Award Management (SAM), and have completed Online Representations and Certifications. The NAICS Code is 562910 with a size standard of $25 million. The point of contact is Craig D Bryant, Contracting Officer, who can be reached at craig_bryant@nps.gov or 330-524-8442.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Indiana Dunes National Park | |
| U.S. Department of Interior | |
| National Park Service | 64 W Dunes Hwy |
Chesterton, IN 46304
PROJECT: Asbestos Abatement
PRICE SCHEDULE
Construction Items Unit Quantity Price/ Unit Subtotal
| Mobilization/Demobilization | ||||
| - Mob/Demob Costs | LS | 1 | $ - 0 | $ - 0 |
Remove and properly dispose of the floor tiles/black mastic and all associated work/items as outlined in the project specifications
| - Materials | LS | 1 | $ - 0 | $ - 0 |
| - Equipment | LS | 1 | $ - 0 | $ - 0 |
| - Labor | LS | 1 | $ - 0 | $ - 0 |
Subtotal $ - 0
| Overhead | % | $ - 0 |
| Profit | % | $ - 0 |
| Bonds | % | $ - 0 |
| Grand Total | $ - 0 |
| ** It is the responsibility of the contractor to verify all the quantities/measurements and to provide a price that will cover the completion of the entire project for this firm fixed price contract. ** |
Printed: &D &T &Z&F image1.png