This document is a Project Specifications document for the repair and replacement of the Beaver Creek Auto Gate at Wind Cave National Park in Hot Springs, South Dakota. The project involves removing the existing 33-year-old auto gate and constructing a new gate that is critical for resource management, specifically to maintain bison and elk herds within the park boundaries, prevent animal disease transmission, and restrict livestock from entering park lands.
The specifications detail comprehensive requirements for the contractor, including removing the existing steel auto gate and concrete support structures, fabricating a new 24-foot wide by 16-foot long auto gate rated for a minimum of 50,000 pounds, constructing new cast-in-place support structures, installing guardrails, and completing associated earthwork and road restoration. The project must adhere to South Dakota Department of Transportation (SDDOT) standards, with a 90-calendar day performance period. Additional requirements include maintaining project boundaries, protecting wildlife and vegetation, implementing erosion control, and coordinating with local county and park authorities for road closures and access management.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P6325B0006.pdf | ||
| Atch_2_DOL_Wage_Determination_SD20250032_1_3_25.pdf | ||
| Atch_3_Limitations_on_Subcontracting_Report.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Div. 1 V. 2023-11-11 Page | 1
Wind Cave National Park Hot Springs, South Dakota
Repair/Replace Beaver Creek Auto Gate RT 0203
PMIS 248088
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE
05/12/2025
Page | 2
TABLE OF CONTENTS
1) DIVISION 01 - GENERAL REQUIREMENTS
• Section 01 10 00 - Division 01 Short Form General Requirements
2) DIVISION 02 - EXISTING CONDITIONS
• Section 02 41 00 – Demolition
3) DIVISION 31 - EARTHWORK
• Section 31 23 00 – Earthwork
4) DIVISION 32 - EXTERIOR IMPROVEMENTS
• Section 32 15 40 – Crushed Stone Surfacing
• Section 32 91 13 – Topsoiling and Finished Grading
5) APPENDIX A - EXISTING CONDITIONS PHOTOS
6) APPENDIX B - APPLICATION FOR OCCUPANCY ON THE RIGHT OF WAY OF COUNTY
HIGHWAYS
7) APPENDIX C - GIS MAP OF BEAVER CREEK AUTO GATE (FOR OCCUPANCY APPLICTION)
8) APPENDIX D - ADJACENT LANDOWNER MAP
9) APPENDIX E - POINT OF CONTACT LIST (NOT COMPREHENSIVE)
10) APPENDIX F - CONSTRUCTION DRAWINGS
• Work Site Aerial Maps
• Plate 610.01 Cast-In-Place Cattle Guard Foundations
• Plate 610.03 Cattle Guard Grate and Wing
• Plate 630.20 Midwest Guardrail System
• Plate 630.82 Midwest Guardrail System (MGS) Trailing End Terminal
• Plate 630.99 Measuring Guardrail Height
• Plate 632.04 Type 2 Object Marker at Pipe Culverts, Box Culverts, and Cattle Passes (60” and
Greater Overall Width)
• Plate 632.40 Delineation of Guardrail
• Plate 634.29 Road Closed with Offsite Detour
• Recommended Road Closure Map
Page | 3
SECTION 01 10 00
DIVISION 1 SHORT FORM GENERAL REQUIREMENTS
PART 1 – GENERAL
ITEM 1 - DESCRIPTION OF WORK
1.1 Background: This auto gate is located on Wind Cave National Park West boundary fence dividing the National Park from Custer County. The auto gate is a critical part of the resource management program. It is necessary to preserve the integrity of the auto gate to maintain herds of bison and elk within the park at manageable levels, to reduce the potential for private herds of Bison and/or elk on adjacent lands to get into the park, to reduce the potential for the transfer of any animal diseases between the various herds, and to keep the park bison herd from straying or trespassing onto private and state land. The gate also plays a critical role in preventing domestic cattle and horses from grazing on park lands while maintaining vehicle access to/from the park.
This project will replace the auto gate on a routine schedule. The cycle to replace auto gates is 30 years, this gate has been in service for 33 years. This project provides cyclic maintenance that protects a major system/component, the Beaver Creek Road.
1.2 Work Covered by the Contract Documents:
A. Project Location: The location for this project is at Wind Cave National Park in Hot Springs, South Dakota. Park Headquarters is located at 26611 US Highway 385. The auto gate is located at the West Boundary fence on Custer County Road 391, also known as Beaver Creek Road. Map of location is included as Appendix A. Additional note for reference;
CC391/Beaver Creek Road is named Rankin Ridge Rd on included aerial maps.
B. All work shall conform to all additional specifications provided within this document.
C. Work consists of:
• All work shall conform to SDDOT standards as described. Standard Plates Index
• All aspects of removal and out-of-park disposal of existing steel auto gate and concrete support structures including existing guardrails.
• All aspects for the purchase/fabrication of new auto gate in accordance with SDDOT specifications provided in Appendix B. New auto gate shall be approximately 24 feet wide by 16 feet long and be load rated for a minimum of 50,000 pounds. Contractor is responsible for the proper manufacture of the new auto gate, including welding, load rating, coatings, and any/all associated/incurred shipping costs.
• SDDOT Standard Plate Number 610.03 allows for “Alternate design consideration”. This statement is not applicable within the scope of this contract and no alternate designs will be acceptable.
https://apps.sd.gov/HP20StandardPlates/
Page | 4
• All aspects for construction of new cast-in-place auto gate support structures in accordance with South Dakota State DOT specifications provided in Appendix C. Support structures shall be constructed in a manner to support the required load limit of 50,000 pounds.
• SDDOT Standard Plate Number 610.01 allows for “Alternate design consideration”. This statement is not applicable within the scope of this contract and no alternate designs will be acceptable.
• All aspects for the installation of new auto gate including new mounting materials, fasteners, and hardware.
• Contractor’s work shall include any/all earth work and excavation required for cast-in-place support structures and maintaining/creation to support drainage through auto gate location, required road removal/re-installation at auto gate edges, and road surface smoothing/grading and compaction in disturbed road locations within the project site. Any additional road materials required shall be ¾ or 1 inch road base similar in color, size, and consistence of existing road surface.
• Contractor is responsible for any permits for earth or road work, including SD Stormwater and Custer County Right-of-Way, including application, approval, and any/all costs incurred.
Consent of adjacent landowners will be required for any access beyond the right-of-way. See Appendices B and E for required forms and point of contact information. This is not a comprehensive list and additional forms, permissions, and POCs may be required and shall be the responsibility of the contractor.
• Final construction elevations shall reflect preconstruction slope and elevation consistent with existing drainage through auto gate and project location. Use of waddles or riprap for erosion and drainage control may be authorized with government approval.
• Preconstruction elevations shall be documented and submitted to COR prior to any ground disturbance and post construction elevations shall be documented and submitted to COR prior to final inspection. Contactor shall provide for 2 (minimum) topographical surveys of construction location/disturbed areas as previously stated.
• Installation of new guardrail sections and object/traffic markers on both edges/directions of new auto gate shall be required and shall meet SDDOT specifications and requirements. See Appendix F.
• Guardrails shall be constructed of a single section per side using W-beam rail. Ends of the guardrail shall be tapered away from road edge using MGS Trailing End Terminals (Appendix F) or equivalent. Guardrails shall be mounted at standard height (Appendix F) to the ends of new cast-in-place foundations similar to current construction.
• Contractor shall be responsible for all road closure coordination with park and county offices as required. All traffic signage/control for closures/detours are the responsibility of the contractor. Suggested detour/traffic plan is included as Appendix F. Road closures and traffic detours will be in accordance with SDDOT requirements provided in Appendix F. A complete Traffic Control Plan will be included with bid submission for review.
• The contractor shall erect a temporary barrier fence to protect the work site to prevent wildlife from entering work site or exiting park boundaries. This enclosure shall be constructed of supported mesh-type fencing such as plastic construction/snow fencing, chain link, or other contractor submitted/park approved materials with a minimum height of 42 inches. Enclosure fencing shall extend beyond the project site and protect any/all work impacted locations and
Page | 5 shall connect to the existing perimeter wildlife fence in a solid manner. Proposed location for construction enclosure fence is included as Appendix F.
• Auto gate, foundations, and guardrails shall be installed using the road centerline of the Custer County Beaver Creek Road section which terminates at the auto gate edge as reference for center of installation.
• All park boundary fence and gates removal required for installation of the cattle guard shall be the responsibility of the contractor and limited to the sections annotated within the project location maps (Appendix F). Park personnel will be responsible for installation of new boundary fencing and gates after completion of this contract. Completion of this contract will not be impacted or withheld solely based on park boundary fence and gates re-construction which fall under the scope of park responsibility.
D. Period of performance: Work shall be completed within 90 calendar days of the start date provided on the Notice to Proceed.
• Clarification: The Notice to Proceed will be issued with a period of performance that is all inclusive of supply lead times, material deliveries, decommissioning, installation, anticipated average weather days for location, final commissioning, and acceptance of completed work. The contractor will be expected to provide a project schedule with adequate critical path details to ensure all work is completed within the stated calendar days from issuance of the Notice to Proceed. If weather impacts project beyond typical average weather patterns, contractor shall provide documentation in request for additional days.
1.3 Existing Condition Protections:
A. Preservation of Historical and Archeological Fabric:
i. The Historic and Archeological Data Preservation Act of 1974, provides for the preservation of historical and archeological data that might otherwise be lost as the result of alterations to the terrain caused by a federal or federally licensed activity or program.
ii. IF, in connection with operations under this contract, the Contractor, subcontractors, or employees of any of them, discovers, encounters or becomes aware of any possible historical or archeological data, objects or sites of cultural value on the project area, such as historical ruins, graves or grave markers, fossils, or artifacts, the Contractor shall immediately suspend all operations in the vicinity of the discovery and notify the Contracting Officer immediately, when safe to do so, and follow up in writing within 2 days, giving the location and nature of the findings. No objects of cultural resource value may be removed. Contracting Officer will contact other entities as required.
iii. Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with Changes clause.
iv. The Contractor will be responsible for protecting the cultural resources within and adjacent to the project area from damage. In addition, the Contractor will be liable for all damage to the cultural resources caused by their actions or the actions of their agents or representatives. The Contractor shall immediately notify the Contracting Officer or their representative if any damage occurs to any cultural resource and
Page | 6 immediately suspend work in the area in which damage has occurred until authorized to proceed.
v. The Contractor agrees to include this language within all subcontracts.
ITEM 2 – PROTECTING EXISTING UTILITIES
2.1 Protecting Existing Utilities: Notify Contracting Officer (CO), Contracting Officer’s Representative
(COR) and utility companies as required to request location services prior to and to coordinate any excavation/digging operations, and/or for demolition if within Scope of Work.
2.2 Contractor shall be responsible for locating and preventing damage to known utilities on site or indoors. If contractor damage occurs, alert CO and COR as soon as safely possible, and repair utility at no additional expense to the Government. If damage occurs to an unknown utility, contact CO and COR as soon as safely possible.
2.3 Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated below:
A. Notify CO and COR not less than two business days in advance of proposed utility interruptions.
B. Hours for Utility Shutdowns: Shutdowns shall not exceed 2 to 3 hours. Temporary provisions will be needed by the Contractor for periods longer than stated allowance or if required for critical systems as determined by COR.
ITEM 3 - CONTRACTOR’S USE OF PREMISES
3.1 Conduct of Operations: At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent in the Superintendent’s Compendium. For access use the following hyperlink. Superintendent's Compendium - Wind Cave National Park (U.S. National Park Service)
A. Communications: Contractor shall provide the Contracting Officer and COR with methods of communications including land and/or cell phone numbers (note some areas of work have limited service coverage), email and in case of emergency 24-hour contact options for duration of time operations.
B. No signs or advertisements (except those specified herein and as required for safety) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
C. Smoking is not permitted within any Federal building or within 25 feet of entrances, operable windows, or outdoor air intakes.
D. Public Use of Site: Contractor shall at all times conduct operations to ensure the least inconvenience to the public.
https://www.nps.gov/wica/learn/management/superintendent-s-compendium.htm https://www.nps.gov/wica/learn/management/superintendent-s-compendium.htm
Page | 7
3.2 On-site work hours: Work shall be generally performed during normal business working hours of
7:30 a.m. to 4:30 p.m., Monday through Friday, except when otherwise indicated.
A. Work on Saturdays, Sundays, Federal holidays, early morning, or at night may not be performed without prior consent from the CO and COR. Submit requests for work outside of the stated normal business hours to the CO and COR for approval at least 48 hours in advance of the work.
The following Federal holidays are observed by the National Park Service:
New Year Day Martin Luther King, Jr’s Birthday Washington’s Birthday Memorial Day Juneteenth National Independence Day Independence Day Labor Day Columbus Day Veterans Day Thanksgiving Day Christmas Day
B. Note: Any of the above holidays falling on a Saturday will be observed on the preceding
Friday; holidays falling on Sunday will be observed on the following Monday. The specific day that each holiday is recognized for each year can be found at the following site: Federal Holidays (opm.gov).
3.3 Contractor Use of Site:
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to the area identified in Appendix F. Do not disturb portions of Project site beyond areas in which the Work is indicated.
B. Driveways and Entrances: Keep driveways, access roads, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize use of driveways and entrances.
C. Do Not disturb site outside of noted disturbance area, including earthwork and clearing of vegetation, to:
1. Areas identified in Appendix F
2. 10 feet beyond surface walkways, patios, surface parking, and utilities less than 12 inches in diameter
3. 15 feet beyond primary roadway curbs and main utility branch trenches https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022 https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022
Page | 8
D. Utilities
1. General: Cost or use charges for temporary facilities shall be included in the Contract
Sum as required.
2. Water Service: N/A
3. Electric Power Service: N/A
4. Waste Operation:
a. Toilets: Contractor must provide toilets for contractor personnel, sufficiently lighted and ventilated toilet facilities in weatherproof, sight proof, handicap accessible (if required), sturdy enclosures with privacy locks. Coordinate with COR for approved location if not shown on attached site plan.
b. Waste Removal / Recycling: Contractor is responsible for removing all waste created by the project. Contractor shall recycle to the highest degree possible and empty dumpsters as necessary to avoid debris on site. Locate as shown on site plan or coordinated with COR.
E. Security and Protection facilities:
1. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with state and federal environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.
2. Cleaning of Equipment: The Contractor shall ensure that prior to moving on to the Project Area, all equipment, is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Ensure that all equipment has been pressure washed and is free of exotic species prior to start-up of operations and moving of equipment to Project Area.
Equipment shall be considered free of soil, seeds, and other debris when a visual inspection does not disclose such material. Disassembly of equipment components or specialized inspection tools are not required.
3. Tree and Plant Protection:
a. Provide Tree Protection fence at drip line of trees impacted in the construction area.
Coordinate with COR.
4. Pest Control: Follow best practices to minimize attraction and harboring of rodents, roaches, and other pests and to perform extermination and control procedures at regular intervals so Project will be free of pests and their residues at project completion. Perform control operations lawfully, using environmentally safe materials.
5. Temporary Enclosures: N/A
6. Site Enclosure Fence: N/A
7. Hot Work Permit: N/A
3.4 Storage - Staging Areas:
Page | 9
A. Confine Storage of materials and equipment to the project staging area noted on the plans/aerial. Specific storage units shall be provided by the contractor and exact location within staging area may be discussed at the preconstruction briefing. All storage units provided by the contractor shall be in a clean and acceptable condition to the COR. Security of the materials and equipment on site is the Contractor’s responsibility.
3.5 Preservation of Natural Features: Trees shall not be removed, limbed, or disturbed during the
Maternity Roosting time for Northern Long Eared Bat, June 1-July 15
3.6 Hauling Restrictions: Contractor shall verify and be responsible for the path accessing the site and obtaining / maintaining all local, state and federal permits/licenses associated with hauling/road requirements and dumping of materials associated with the project. Contractor shall coordinate any traffic with Custer County and Park COR prior to use of Custer County roads.
3.7 Housekeeping:
A. Keep project neat, orderly, and in a safe condition at all times.
1. Dispose of waste materials and recycling legally outside the park. The contractor shall not use park dumpsters
2. Address Recycling: Government goal is to salvage and recycle as much nonhazardous construction waste as possible. Use sustainable methods to extent possible during this project, recycling material as is probable with local means. Maintain accurate documentary records for submittal of all recycled materials used including fly ash and slag cement.
3.8 Occupancy Requirements for Buildings:
A. Existing Buildings: N/A B. New /Existing Buildings Unoccupied: N/A
3.9 Photo Documentation:
A. Contractor must provide existing condition, progress, and completion photos. All photos shall be in focus, show maximum range of depth of field general photo and then close up detail photo as needed. Shall be in JPEG digital form and submitted preferably electronically by email or optional via CD-R Archival Gold or DVD-R Archival Gold media with printed labels and 8 mega pixels minimum within 7 days from time of taken or as approved by COR.
B. Existing Condition Images:
1. Before starting construction, take color, dated, digital images of project site and adjacent property/roads/etc. that may be impacted by construction activity/traffic. Include existing items to remain or be salvaged from different vantage points and with context for location identification.
C. Construction Progress Images:
Page | 10
1. Document all sub-surface work/ trenches etc. prior to backfill with photos covering enough overall field view to show location and then zoom in for details. (Locations and dimensions shall also be noted on as built drawing set.)
2. Maintain organized index for photos with date, description, etc.
3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.
D. Completion Images:
1. Document all completed work within scope of work.
2. Maintain organized index for photos with date, description, etc..
3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.
3.10 Fire and Life Safety:
B. As a minimum, conduct one weekly 15 minute "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the following week. Document and submit meeting minutes to the CO and COR within one day after the meeting and document the meetings on the daily reports.
C. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations). Take all necessary precautions to prevent fire during construction. Provide adequate ventilation during use of volatile or noxious substances.
D. Store and handle hazardous materials in accordance with manufacturers and OSHA 29CFR1926 Subpart D requirements 1926 | Occupational Safety and Health Administration (osha.gov). Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for each chemical.
1. Immediately report all spills of hazardous materials to the CO, COR, and park.
2. Maintain a spill emergency response kit.
3. Train employees how to respond to a spill and use the emergency response kit.
3.11 Noise and Acoustics Management
A. Contractor shall not have personal radios or other media sources and they shall not be broadcast within NPS property.
ITEM 4 - COMMENCEMENT, PROSECUTION, AND COMPLETION
4.1 The Contractor shall commence work in accordance with the terms and conditions of the contract.
Contractor shall coordinate and incorporate long lead and delivery time items within the schedule.
ITEM 5 - EXAMINATION OF THE SITE
5.1 All bidders are urged to visit the job site and examine existing conditions before submitting bids.
Contractors will be accountable for understanding existing conditions. No cost changes for items visible during site visit will be allowed.
https://www.osha.gov/laws-regs/regulations/standardnumber/1926 https://www.osha.gov/laws-regs/regulations/standardnumber/1926
Page | 11
ITEM 6 - ABBREVIATIONS
6.1 The list of abbreviations, standards and organizations which may be used in/referred within the
Construction Specifications or Special Provisions, may be found linked from the listed page below. On the home page, follow the link under “Contracting and Procurement” labeled “NPS Reference Standards.” https://www.nps.gov/orgs/1671/do-business-with-us.htm
ITEM 7 - ACCIDENT PREVENTION
7.1 Description: The work of this section consists of establishing and implementing an effective accident prevention program (APP) and providing a safe environment for all personnel and visitors.
7.2 Submittals:
A. Accident Prevention (Safety) Plan (APP): Submit a site-specific accident prevention (safety) plan. The Plan shall be written to comply with OSHA and project requirements (a generic plan is not acceptable) including but not limited to the following:
1. Name and qualifications of responsible supervisor to carry out the program.
2. First aid and rescue procedures.
3. Training, both initial and continuing.
4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to provide for property protection and safety of the public, National Park Service personnel, and Contractor's employees. Identify the work included under each phase, with a Job Hazard Analysis (JHA)/Job Safety Analysis (JSA), etc. A sample JHA template may be provided upon request.
5. Planning for possible emergency situations, such as cave-ins, earthquake, explosions, fires, floods, power outages, slides, and windstorms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.
6. Contractor to identify nearest location of medical facility for emergencies
7. Recognition that works will be performed in remote areas with limited communication or cell phone coverage if applicable.
8. Supplemental hazard specific plans may be required IAW 29 CFR 1926 or 1910.
B. Meeting and Inspection Reports: Safety Meetings: As a minimum, conduct 15 minute
"toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite. Submit a report of safety meetings and inspections to CO and COR within one day after the meeting and document the meetings on the daily reports.
7.3 Qualification of Employees:
A. Ensure that employees are physically qualified to perform their assigned duties in a safe manner to include operators of vehicles and equipment. Provide operating instructions for all equipment.
https://www.nps.gov/orgs/1671/do-business-with-us.htm
Page | 12
B. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
7.4 Accident Reporting: The Contractor shall report all accidents to the CO and COR as soon as safely possible and assist the CO and COR and other officials as required in the investigation of the accident.
7.5 First Aid Facilities: Provide access to facilities for the number of employees and appropriate to the hazards associated with the types of ongoing construction work at the site.
7.6 Emergency Instructions: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
7.7 Personal Protective Equipment (PPE): It is the Contractor's responsibility to require all those working on or visiting the site to wear necessary protective equipment at all times.
A. PPE must meet requirements of applicable ANSI standards. Selection shall conform to OSHA 29CFR 1926 Subpart E.
B. A hard hat use area shall be designated by the Contractor. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.
C. All PPE will be serviceable at all times. At a minimum, maintain two (2) additional sets of PPE including hard hats and all other Accident Prevention Plan required equipment.
7.8 Hazardous Materials: It shall be the responsibility of all operators and contractors, functioning within the park to properly cleanup, mitigate and remediate if necessary, all unauthorized discharges of hazardous materials or non-hazardous chemical and biological products released from fleet and/or other support vehicles or stationary sources. Response shall be consistent with guidelines established by federal, state, and local regulations, and as outlined within the operator's Safety or Hazardous Materials Business Plan.
A. If a spill, leak, or other release occurs, the operator shall as soon as possible, without impeding cleanup, notify the local 911 Emergency Response, COR and or the National Park Service Emergency Dispatch.
ITEM 8 - PRECONSTRUCTION CONFERENCE
8.1 The Contracting Officer shall conduct a preconstruction conference, and the successful offeror will be notified and will be required to attend. The Contracting Officer’s notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed. See Item 9.1C below.
ITEM 9 - SUBMITTALS
9.1 General Contracting Submittal Procedures:
Page | 13
A. General: Prepare and submit submittals required by individual Technical Specification Sections. Types of submittals are indicated in individual specific sections.
1. CM-16 Transmittal Form: All submittals shall be transmitted via electronic email using
National Park Service form CM-16 form. The form will be provided by the Contracting Officer. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form. Submit completed CM-16 forms to the CO and the COR
B. Submittal List: administrative required submittals are listed below in 9.1.C and does not include technical section submittal requirements included in each technical section.
C. Preconstruction Conference Submittal: Satisfactory evidence of liability insurance coverage and workman’s compensation, and any applicable bonds, must be submitted within 10 calendar days of Notice of Award. The following items are to be submitted prior to the Preconstruction Conference or as specified at the CO’s discretion. The timeline for the documents to be submitted will be addressed at the pre-construction conference for those items that were not received and approved prior. Notice to Proceed may not be issued, and the Contracting Officer will consider other contractual remedies if not resolved as directed.
Work shall not commence until written Notice to Proceed has been issued. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference:
1. Letter designating Project Superintendent.
2. Construction Schedule. (Must include shop drawings, procurement time including long lead time items, mobilization, trade work progression and completion at minimum.)
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention (Safety) Plan (see section 7 of this document).
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses (SF1413).
7. Quality Control Plan.
8. Waste Management Plan.
9. Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP) Submitted to AHJ
(Authority Having Jurisdiction).
10. SDDOT Right-of-Way Occupancy Permit.
9.2 Project Submittal Process (Shop Drawings, Product Data, and Samples): Contracting Officer will provide sample cover sheet and a list of required submittals is included in each technical specification or attached at the end of this document.
A. Shop Drawings: Indicate all coordinating materials and work impacting the installation coordination, connection details, anchorage requirements, hardware locations, and installation details and locations.
1. Submit Shop Drawings according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and two full size hardcopy documents to COR.
B. Product Data: Provide component construction and specification data sheets, anchorage requirements and any other product specific data.
Page | 14
1. Submit Product Data according to Part 9.1 of this section to include one digital file (.PDF or .TIF) to COR.
C. Samples: Submit 2 color samples 4” x 6” minimum in size for all product color selections.
Paint samples shall be actual paint finish drawdown for all project colors.
1. Submit Samples CM-16 Transmittal Form according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and physical samples of actual material to COR.
D. For submittals specified above, forward submittals to Contracting Officer and COR at least 15 days before need for approval (depends on length of project).
E. After approving submittals, Contracting Officer and/or COR will return one copy to the
Contractor. If submittals are not approved, Contracting Officer will return all copies to Contractor with reasons for rejection. Resubmit, identifying changes. Any work done before approval shall be at Contractor's own risk.
9.3 Approved Equals: All brand names noted are subject to ‘or equal’ products. If an item in this solicitation is identified as “brand name or equal” or lists more than 1 manufacturer, the description of the proposed item must reflect the characteristics and level of quality that will satisfy the Government’s needs as demonstrated by the salient physical, functional, or performance characteristics that “equal” products must meet and/or exceed that as specified in the solicitation or relevant specification. Contractor shall incorporate and be responsible for all collateral costs due to the or equal proposed as required to provide a complete project.
A. For each item proposed as an “approved equal,” submit supporting data, including:
1. Drawings and samples as appropriate.
2. Comparison of the characteristics of the proposed item with that specified and with the salient characteristics provided.
3. Changes required in other elements of the work because of the substitution.
4. Name, address, and telephone number of vendor.
5. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists.
Describe availability of maintenance service, and state source of replacement materials.
B. A request for approval constitutes a representation that General Contractor:
1. Has investigated and shall provide documentation in request showing that the proposed item is equal or superior in all respects to the salient characteristics specified.
2. Will meet or exceed warranties for the proposed item specified.
3. Has determined that the proposed item is compatible with interfacing items.
4. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.
5. Waives all claims for additional expenses that may be incurred as a result of the substitution.
C. Approved Equals will be evaluated and approved/disapproved during the submittal process.
Page | 15
9.4 Schedule of Values: Submit the Schedule of Values a minimum of one week prior to the Preconstruction Conference for COR review. Schedule of Values shall include defined work line items with cost break downs including labor, material, and equipment for COR approval.
9.5 Progress Reporting: The initial Construction Schedule and Schedule of Values are required a minimum of one week prior to the Preconstruction Conference. After the Notice to Proceed is issued and after on-site work begins, progress will be documented via daily logs and by providing an updated Construction Schedule and Schedule of Values when requested, but minimally with each pay application. Submit digital copy electronically (PDF preferred) of all required documents.
Construction Schedules are normally in bar chart form and indicate estimated starting and completion dates for each part of the work. For a pay application to be reviewed and processed in a timely manner, the following information must either be submitted prior to or accompany submission of the pay application:
A. Daily/weekly progress reports during construction as part of the administration process.
B. Updated Schedule of Values: Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The Schedule of Values will form the basis for payment. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. A sample Schedule of Values format may be provided upon request.
ITEM 10 – TEMPORARY SERVICES
10.1 It is the Contractor’s responsibility to provide temporary services, equipment, tools, and skilled labor as required for the chosen means and methods to perform the work in accomplishing this Contract.
ITEM 11 - PROJECT CLOSEOUT
11.1 Description: The work of this section consists of final cleanup, closeout submittals, final inspection procedures working toward Final Acceptance.
11.2 Cleaning: Remove all tools, equipment, surplus materials, and rubbish. Move attic stock to location coordinated with COR. At time of final inspection, project shall be thoroughly clean and ready for intended use. Inspector holds the right to reschedule if project is not ready for inspection.
11.3 Completion and Final Inspection: Contractor shall submit written certification of project completion and request a final inspection to the Contracting Officer and COR. The Contracting Officer or designee will make an inspection within 10 days of receipt of request or at a mutually agreeable time.
A. If the work is determined to be complete following the final inspection with minor comments, the COR will prepare and provide the Contractor a Punch List noting outstanding items to be addressed.
Page | 16
B. If the work is not determined to be complete following the final inspection, the Contracting Officer will notify Contractor in writing, stating reasons. Contractor, after completing the work according to the Contract Documents, shall resubmit completion and request a new final inspection. Re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction contract clause.
C. Contractor shall complete the Punch List within 30 calendar days, or a time directed by the
CO.
D. Once Contractor completes all items of work on the Punch List and all contractually required items are accepted, Contracting Officer will issue Letter of Final Acceptance of Work and request the final pay application.
E. If the Contractor fails to complete the work within the time frame, the Contracting Officer may correct the work with an appropriate reduction in contract price or charge for re-inspection costs in accordance with the Inspection of Construction contract clause.
F. Disposition of any permits and warranties required by the specifications in this section.
11.4 Final Acceptance of the Work: After all punch list deficiencies have been corrected, a Letter of
Final Acceptance will be issued. A Release of Claims document must be executed and submitted to the Contracting Officer before final payment can occur.
11.5 Warranties
A. Construction Warranty shall be based on date of final acceptance of the work and remain in effect for one year.
B. Provide all manufacturer warranty information of products installed organized by Division. All contact information, extent of coverage and conditions shall be clearly noted as well as date of overall final acceptance.
C. Information shall include operation and maintenance manuals for each warranted product.
ITEM 12 - DEFINITION OF CONTRACT LINE ITEMS
12.1 Summary
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut off points where one item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
12.2 List of Contract Line Items
A. Contract Line Item 01
1. This item consists of all demolition, site work, earthwork, gate construction, and all other work associated with this endeavor.
Page | 17
2. Payment will be made per the contract and percentage of completion level.
PART 2 – PRODUCTS (NOT USED)
PART 3 – EXCUTION (NOT USED)
END OF SECTION
WICA - 248088 02 41 00 - 1
DEMOLITION
SECTION 02 41 00 - DEMOLITION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. General provisions applicable to all demolition and removals.
2. Civil/site demolition and removals.
3. Disposal of demolition debris, materials, and equipment.
B. Scope:
1. Contractor shall provide all labor, materials, equipment, tools, and incidentals as shown, specified and required for demolition, removals, and disposal Work.
2. The Work under this Specifications section includes, but is not necessarily limited to:
a. Demolition and removal of existing materials and equipment as shown or indicated in the Contract Documents. The Work includes demolition of pavement, curbs, sidewalks, gutters, fencing and similar existing materials, and items.
3. Demolitions and removals indicated in other Specifications Sections shall comply with requirements of this Specifications Section.
4. Perform demolition Work within areas shown or indicated.
5. Pay all costs associated with transporting and, as applicable, disposing of materials and equipment resulting from demolition and removals Work.
C. Related Requirements:
1. Division 31 – Earthwork.
1.2 QUALITY ASSURANCE
A. Referenced Standards:
1. National Fire Protection Association (NFPA):
a. 241, Safeguarding Construction, Alteration, and Demolition Operations.
B. Regulatory Requirements:
1. Demolition, removals, and disposal Work shall be in accordance with 29 CFR
1926.850 through 29 CFR 1926.860 (Subpart T – Demolition), and all other Laws and Regulations.
2. Comply with requirements of authorities having jurisdiction.
WICA - 248088 02 41 00 - 2
1.3 ADMINISTRATIVE REQUIREMENTS
A. Coordination:
1. Review procedures under this and other Specifications sections and coordinate the Work that will be performed with or before demolition and removals.
1.4 SUBMITTALS
A. Informational Submittals: Submit the following:
1. Procedure Submittals:
a. Demolition and Removal Plan: Not less than ten days prior to starting demolition Work, submit acceptable plan for demolition and removal Work, including:
1) Plan for coordinating shut-offs, capping, temporary services, and continuing utility services.
2) Other proposed procedures as applicable.
3) Equipment proposed for use in demolition operations.
4) Recycling/disposal facility(ies) proposed, including facility owner, facility name, location, and processes. Include copy of appropriate permits and licenses, and compliance status.
5) Planned demolition operating sequences.
6) Detailed schedule of demolition Work in accordance with the
Schedule accepted by Engineer.
2. Notification of Intended Demolition Start: Submit in accordance with Paragraph 3.1.A of this Specifications Section.
1.5 SITE CONDITIONS
A. Owner makes no representation of condition or structural integrity of area(s) to be demolished or where removals are required by the Contract Documents.
PART 2 - PRODUCTS - (NOT USED)
PART 3 - EXECUTION
3.1 PREPARATION
A. Notification:
1. Not less than 48 HRS prior to commencing demolition or removal, advise Contracting Officer in writing of planned start of demolition Work. Do not start removals without permission of Contracting Officer.
WICA - 248088 02 41 00 - 3
2. Where demolition or removals has potential to affect adjacent properties, occupants, streets, or other public thoroughfare, transportation facilities, and utilities, furnish required notices to owners and occupants of properties, buildings, and structures that may be affected by the demolition of removal.
3. In accordance with Laws and Regulations, furnish to authorities having jurisdiction, including emergency services as necessary, appropriate notices of planned demolition and removals.
4. Submit to Contracting Officer copies of notices furnished to adjacent property owners, occupants, and authorities having jurisdiction.
B. Protection of Adjacent Areas and Facilities:
1. Perform demolition and removal Work in manner that prevents damage and injury to property, structures, occupants, the public, and facilities. Do not interfere with use of, and free and safe access to and from, structures and properties unless allowed by the Contract Documents otherwise allowed in writing by Owner.
2. Closing or obstructing of roads, drives, sidewalks, and passageways adjacent to the Work is not allowed unless indicated otherwise in the Contract Documents.
Conduct the Work with minimum interference to vehicular and pedestrian traffic.
3. Repair damage to facilities that are to remain which such damages results from Contractor’s operations.
C. Existing Utilities: In addition to requirements of the General Conditions, Supplementary Conditions, and Division 01 Specifications, perform the following:
1. Should unforeseen, unknown, or incorrectly shown or indicated Underground Facilities be encountered, Contractor responsibilities shall be in accordance with the General Conditions as may be modified by the Supplementary Conditions.
Cooperate with utility owners in keeping adjacent services and facilities in operation.
2. Storm Water Sewerage: Existing storm water system shall remain in place until demolition of existing building or structure is complete. Upon completing demolition, cut and cap storm sewerage at locations shown on the Drawings.
Remove existing storm water piping and related structures between points of cutting, and backfill, restore to grade, and stabilize the area over the removed facilities in accordance with the Contract Documents.
3. Shutdown of utility services shall be coordinated by Contractor, assisted by Owner as required relative to contacting utility owners.
D. Remediation:
1. If unanticipated Hazardous Environmental Condition is believed to be encountered during demolition and removals, comply with requirements of the General Conditions, as may be modified by the Supplementary Conditions.
WICA - 248088 02 41 00 - 4
3.2 DEMOLITION - GENERAL
A. Locate construction equipment used for demolition Work and remove demolished materials and equipment to avoid imposing excessive loading on supporting and adjacent walls, floors, framing, facilities, and Underground Facilities.
B. Pollution Controls:
1. Use water sprinkling, temporary enclosures, and other suitable methods to limit emissions of dust and dirt to lowest practical level. Comply with Laws and Regulations.
2. Do not use water when water may create hazardous or objectionable conditions such as icing, flooding, or pollution.
3. Clean adjacent structures, facilities, properties, and improvements of dust, dirt, and debris caused by demolition Work, in accordance with the General Conditions.
C. Explosives:
1. Explosives are not allowed at the Site. Do not use explosives for demolition and removal Work.
3.3 DEMOLITION OF SITE IMPROVEMENTS
A. Pavement, Sidewalks, Curbs, and Gutters:
1. Demolition of asphalt or concrete foundations, pavement, sidewalks, curbs, and gutters, as applicable, shall terminate at cut edges. Edges shall be linear and have a vertical cut face.
2. To cut pavement, sidewalks, curbs, and gutters, use machinery or tools that provides a smooth-cut edge, appropriate for the required. Where cut edges are not smooth, repair the cut edge to remain to provide a smooth, even appearance.
B. Fencing, Guardrails, and Bollards:
1. Remove to the limits shown or indicated on the Drawings.
2. Completely remove below-grade posts and concrete.
C. Manholes, Vaults, Chambers, and Handholes:
1. Remove to the limits shown or indicated on the Drawings.
2. If not shown or indicated on the Drawings, remove to not less than three feet below finished grade indicated on the Drawings.
D. Underground Facilities Other than Manholes, Vaults, Chambers, and Handholes:
1. Remove to the extent shown or indicated on the Drawings.
2. Unless otherwise shown or indicated, cap ends of piping to remain in place in accordance with the “Mechanical Removals” Article in this Specifications section.
WICA - 248088 02 41 00 - 5
E. Other Site Improvements: When the Contract Documents require removal of other site improvements not addressed above, copy with Contract requirements for removal of buildings or structures.
3.4 DISPOSAL OF DEMOLITION DEBRIS
A. Disposal – General:
1. Promptly remove from the Site all debris, waste, rubbish, material, and equipment resulting from demolition and removal operations. Promptly upon completion of demolition and removal operations, remove from the Site construction equipment used in demolition Work.
2. Do not sell at the Site demolition materials or removed equipment. If materials, equipment or debris will be sold by Contractor, remove the items from the Site and perform the sale or transaction elsewhere, in accordance with Laws and Regulations.
B. Transportation and Disposal:
1. Non-Hazardous Materials, Equipment, and Debris: Properly transport and dispose of non-hazardous demolition materials, equipment, and debris at appropriate landfill or other suitable location, in accordance with Laws and Regulations. Non-hazardous material does not contain Constituents of Concern such as (but not limited to) asbestos, PCBs, petroleum, hazardous waste, radioactive material, or other material designated as hazardous in Laws or Regulations.
2. Hazardous Materials, Equipment, and Debris: When handling and disposal of items containing Constituents of Concern is included in the Work, properly transport and dispose of such items in accordance with the Contract Documents and Laws and Regulations.
C. Submit to Contracting Officer information required in this Specification Section on proposed facility(ies) where demolition materials, equipment, and debris will be recycled. Upon request, Engineer or Owner, shall be allowed to visit recycling facility(ies) to verify adequacy and compliance status. During such visits, recycling facility operator shall cooperate and assist Engineer and Owner.
WICA - 248088 31 23 00 - 1
EARTHWORK
SECTION 31 23 00 - EARTHWORK
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Earthwork - excavation, backfilling, grading, compaction, disposal of waste and surplus materials, placing crushed stone, construction of subgrade for cattle guard foundations, sheeting, bracing, dewatering and other Earthwork related work.
1.2 QUALITY ASSURANCE
A. Referenced Standards:
1. ASTM International (ASTM):