Atch_1_Questions_and_Answers_0001.pdf

PDF 173 KB Posted

Attached to
THRO North Unit Rehab Asphalt Riverbend Scenic Ove
Solicitation number
140P6323B0011
Issued by

About this file

This document contains questions and answers regarding Solicitation Number 140P6323B0011 from the National Park Service Midwest Region for rehabilitation work at the Theodore Roosevelt National Park North Unit Riverbend Scenic Overlook. The questions seek clarification on where materials and equipment can be stored on site according to the project plans. The government response indicates that the contractor should maintain a minimum footprint and refer to the general site notes for more details. Additionally, the response states that the National Park Service will assist the contractor in identifying tree driplines during the project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Theodore Roosevelt National Park NU Riverbend Scenic Overlook - 140P6323B0011 Questions and Answers

Question 1.

3.4 Storage – Staging Areas states that storage of material and equipment is noted on plans/ariel photos, and it is not. Is it possible to provide a marked-up drawing showing location?

Government Response:

Please see sheet C1 General Site Notes #4. The intention is to maintain as minimum a footprint as possible withing Construction Area Limits of Disturbance.

Question 2 .

Tree and Plant protection. Does the contractor have to identify where driplines are for trees or will National Park Service?

Government Response:

The NPS will assist the contractor in identifying driplines.