Questions Regarding Site Visit for Mount Rushmore National Memorial Staining HQ Project.
| # |
| Question |
| Answer |
| 1 |
| There are certain areas of the building that are stained vs painted. |
Does the Park understand that there could be an aesthetic difference where stain is used vs where paint is used?
The Park is aware of this condition and understands a slight variation in color will be unchanged. It is the contractors responsibility to minimize the visual impact of the variations.
| 2 |
| Do the railings, steps and handrail on the 1st and 2nd levels of the |
backside of the Administration Building need to all be replaced or just where areas of rot are found?
According to specs 1.2.B.h Loose siding, trim, soffit and fascia will be properly re-secured using like fastener. If rotted out or damaged notify COR. All rotted or damaged areas will be replaced with similar materials as needed. Will be responsibility of successful bidder to coordinate with the COR for any questions about repairs/replacement or existing conditions which require more extensive evaluation.
| 3 |
| Does all of the existing overspray on the bricks, sidewalk, etc. need |
to be removed or just documented Park is aware of past conditions; past overspray is not the responsibility of the contractor. Please document areas of concern to verify existing conditions.
| 4 |
| Will the Energy Center be painted, as well |
| The Energy Center building re-stain is not a part of this Scope of Work , however the CO reserves the right to negotiate a modification to the contract with the successful offeror and following the original Notice to Proceed. |
| 5 |
| It was noted there were rotting wood conditions, will replacing these conditions be completed by the owner or should there be an alternate/allowance for replacing rotten wood? |
| Please see answer to # 2 above |
| 6 |
| Does this project include the currently not stained railing and deck railing on the rear of the building? |
| Yes. Section 1.2.B.c |
| 7 |
| May Diamond Vogel be approved as a supplier? |
Successful bidder (Contractor)will submit product info for approval according to project submittal requirements.
| 8 |
| It appears some areas are painted and some areas are stained, is it the intention to have areas previously painted to be repainted and areas previously stained re-stained? Please note that although the same color can be used the appearance and sheen may vary slightly. |
| See response to Question#1 |