This is a Contractor Questions and NPS Response document for solicitation 140P6026Q0053 issued by the Department of the Interior National Park Service Midwest Region for the St. Croix National Scenic Riverway fence replacement project. The document addresses four key contractor inquiries regarding project specifications and responsibilities.

The responses clarify that the new 7-foot chain link fence will not include barbed wire, unlike the existing 6-foot fence with 3-strand barbed wire. Only one set of bin blocks will be provided, with the Contracting Officer Representative (COR) determining the placement between two possible locations shown in the project details. For electrical service to the gate operator, contractors may draw power from either the outdoor pedestal or indoor breaker panel, provided all connections comply with the National Electrical Code. Tree removal required for fence installation must be approved by the COR and will be performed by the National Park Service rather than the contractor.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contractor questions and NPS Response St. Croix National Scenic Riverway - Replace Fence - 140P6026Q0053

1. Existing fence is 6' with 3 strand barbed wire and the new fence is just a 7' chain link, will there be barbed wire installed on the new 7' fence?

There will not be barb wire on the 7' chain link fence.

2. Pictures with details shows 2 possible locations for block bins, will there be 2 of them or just one with the location unknown right now?

There will only be 1 set of bin blocks. The bin blocks will be placed at either location and determined by COR.

3. Where does the new gate operator get electrical power?

The gate operator electrical service can be pulled from either the outdoor pedestal or inside breaker panel as long as all work/connections conform to the National Electric Code (NEC).

4. Who is responsible for removing any trees that will be in the way of the new fence?

All tree removal will have to be approved by the COR, and will be performed by the NPS.